HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1485-2023
Submission Date : 27-12-2023 01:56:54 PM
Applicant Type : Company
Project Type: NEW




EMAAR INDIA LIMITED
EMAAR BUSINESS PARK, MG ROAD, SIKANDERPUR, SECTOR -28, GURUGRAM-122002
01244421155
9876888338 (Number Shared by Promoter in Public)
coordination.IN@emaar.ae
https://in.emaar.com/en/
XXXX308B
U45201DL2005PLC133161
 
 


 
 


 
 


 
 


 
 


 
 







THE 88
VILLAGE BAJGHERA, SECTOR 112, GURUGRAM
GURGAON
GURUGRAM
01244421155
9717776439 (Number Shared by Promoter in Public)
coordination.IN@emaar.ae
MANOJ SHARMA
01244421155
9717776439 (Number Shared by Promoter in Public)
coordination.IN@emaar.ae








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
130006608-12-2023256000HSBC BANKHRERA Gurugram
230061727-02-202415000HSBC BANKHRERA Gurugram







1.847 (Acre)
1.75
1.75
10.744 (Acre)
04 of 2013
No
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE-ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Annexure-B- COLLABORATOR
BY VIRTUE OF COLLABORATION AGREEMENT SIGNED BEFORE GRANT OF LICENSE
No
THE DEVELOPER AGREES TO COMPLETE THE PROJECT WITHIN VALIDITY PERIOD OF RERA REGISTRATION/ ANY EXTENSION THEREOF (FORCE MAJURE) FROM RECEIPT OF ALL APPROVALS INCLUDING RERA REGISTRATION AND HAND OVER THE OWNER'S SHARE TO THE OWNER'S COLLECTIVELY.
No
Yes
Yes







12555.50 Lakhs
2986.37 Lakhs
3823.00 Lakhs
4183.00 Lakhs
1563.13 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0.00
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.267
3CONSTRUCTION OF ROADS 0.750
4PAVEMENTS 0.00
5PARKS AND PLAYGROUNDS 0.346
6GREEN BELTS 0
7VEHICLE PARKINGS 0.296
8ELECTRICITY SUB-STATION 0.040
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0.012
13STP 0.025
14UNDERGROUNDWATERTANK 0.062
15AREAUNDERCOMMERCIALUNIT 0.016
16AREAUNDEREWS 0.032
Total1.846




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS250AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM37AS PER PROJECT REPORT
3STORM WATER DRAINAGE41AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM144AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL48AS PER PROJECT REPORT
6STREET LIGHTING125AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING120AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS108AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15ELECTRICAL SUB STATION600AS PER PROJECT REPORT
16UNDERGROUND WATER TANK16AS PER PROJECT REPORT
17EXTRA COST CLUB HOUSE EWS154AS PER PROJECT REPORT
18PARKING67AS PER PROJECT REPORT
19STP16AS PER PROJECT REPORT
20MISCELLANEOUS UPGRADE COST CONTINGENCIES LC GST2121AS PER PROJECT REPORT
21ELECTRIFICATION COST336AS PER PROJECT REPORT


30-01-2024 (date)
09-02-2024 (date)
01-04-2024
31-03-2029
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings72.14222
Apartment/Shops/Other Buildings72.23222
Apartment/Shops/Other Buildings72.18202
Apartment/Shops/Other Buildings72.1022
Apartment/Shops/Other Buildings98.49102
Apartment/Shops/Other Buildings98.49102
Apartment/Shops/Other Buildings98.5622
Apartment/Shops/Other Buildings17.55160
Apartment/Shops/Other Buildings9.4410
Apartment/Shops/Other Buildings8.9910
Apartment/Shops/Other Buildings9.3810





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments201201201402
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments402603603402
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments402201201201
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000.7
Sewerage treatment & garbage disposal000.90.5
Electricity Supply System0000
Storm Water Drainage0000.8
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Miscellaneous Upgrade Cost Contingencies LC GST5.66316.2
Electrical sub station12.0
Electrification Cost6.7

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements012.512.512.5
Water Supply System0.32.61.81.8
Sewerage treatment & garbage disposal3.32.42.44.8
Electricity Supply System7.27.214.414.4
Storm Water Drainage0.42.82.02.0
Parks and Playgrounds0005.4
Clubhouse/community centres0000
Shopping area0000
Other0000
Extra Cost Club House EWS3.14.67.7
Electrification Cost16.810.116.816.8
Electrical sub station30.018.030.030.0
Underground water tank0.20.30.3
STP0.20.30.3
Parking0.71.31.3
Security and fire fighting2.43.66.012.0
Miscellaneous Upgrade Cost Contingencies LC GST39.6465559
Street Lighting6.2

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.525.025.012.5
Water Supply System3.73.73.73.7
Sewerage treatment & garbage disposal4.84.84.82.4
Electricity Supply System7.214.47.221.6
Storm Water Drainage4.14.14.14.1
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Parking3.33.33.33.3
Street Lighting6.212.512.518.7
Play grounds and Parks5.410.810.816.2
Security and fire fighting12.06.012.06.0
Miscellaneous Upgrade Cost Contingencies LC GST1281089694
Electrical sub station30.030.090.030.0
Underground water tank0.80.80.80.8
STP0.80.80.80.8
Extra Cost Club House EWS15.415.415.47.7
Electrification Cost16.816.850.416.8

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.512.512.525.0
Water Supply System1.81.81.80.7
Sewerage treatment & garbage disposal2.42.41.03.9
Electricity Supply System7.27.27.27.2
Storm Water Drainage2.02.02.00.8
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and fire fighting18.06.06.06.0
Extra Cost Club House EWS7.77.77.715.4
Street Lighting6.218.76.26.2
Play grounds and Parks5.416.25.45.4
Parking3.33.33.31.3
STP0.80.80.80.3
Underground water tank0.80.80.80.3
Electrical sub station30.030.060.060.0
Electrification Cost16.816.833.633.6
Miscellaneous Upgrade Cost Contingencies LC GST8687211216

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements25.025.025.00
Water Supply System2.91.10.71.8
Sewerage treatment & garbage disposal1.51.02.42.4
Electricity Supply System7.27.27.20
Storm Water Drainage3.21.20.82.0
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lighting6.26.26.26.2
Miscellaneous Upgrade Cost Contingencies LC GST180202178137
Extra Cost Club House EWS15.415.415.4
Electrification Cost6.710.116.816.8
Electrical sub station12.018.030.030.0
Underground water tank0.50.81.63.1
STP0.50.81.63.1
Parking2.03.36.713.3
Security and fire fighting6.06.06.06.0
Play grounds and Parks5.45.45.45.4

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System1.8
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage2.0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Yes
Yes
RBL BANK LIMITED, GROUND FLOOR, BLOCK A, ABW TOWER, IFFCO CHOWK, GURGAON
409000449570
RATN0000116
110176003
116
RAHUL BINDLE Emaar Business Park, Sector 28, MG Road, Gurugram, Haryana -122002











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE NO. 04 OF 2013 ALREADY BEEN OBTAINED18-02-2013
II. AAI NOCALREADY BEEN OBTAINED02-08-2023
III. FOREST NOCALREADY BEEN OBTAINED23-07-2021
IV. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED24-12-2013
V. BR-IIIALREADY BEEN OBTAINED09-02-2024
VI. APPROVAL OF SERVICE PLAN ESTIMATESALREADY BEEN OBTAINED29-02-2024
VII. APPROVAL OF FIRE FIGHTING SCHEMEALREADY BEEN OBTAINED28-02-2024








Yes


Yes


As per draft prescribed by RERA Authority.







PALM HEIGHTS, SECTOR-77, GURUGRAM
5.5
297
0
297
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
200012000117408
Cost of the apartments179931799315238
Cost of the infrastructure808080
Others costs9869861149


24605 Lakhs
9477 Lakhs
0 Lakhs
0 Lakhs
No
28-02-2023
28-02-2024




EMAAR BUSINESS DISTRICT (EBD) 114, SECTOR-114, GURUGRAM
6.40625
0
86
0
80
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
11286112869330
Cost of the apartments000
Cost of the infrastructure282228222538
Others costs426842682661


2198.73 Lakhs
0 Lakhs
0 Lakhs
9330 Lakhs
No
11-03-2026
11-03-2026




MARBELLA PHASE 2, SECTOR 65 & 66, GURUGRAM
66.059
0
86
0
80
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
434324343242880
Cost of the apartments000
Cost of the infrastructure000
Others costs653265326244


2239.09 Lakhs
0 Lakhs
0 Lakhs
42880 Lakhs
No
31-12-2027
31-12-2027




EMAAR BUSINESS DISTRICT (EBD) 99, SECTOR-99, GURUGRAM
3.26875
0
35
0
9
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
946394637177
Cost of the apartments000
Cost of the infrastructure18311831773
Others costs287628761671


983.65 Lakhs
0 Lakhs
0 Lakhs
7177 Lakhs
No
17-08-2026
17-08-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEGOOD QUALITY ,STANDARD MAKE
2WALL FINISHING DETAILSGOOD QUALITY ,STANDARD MAKE
3KITCHEN DETAILSGOOD QUALITY ,STANDARD MAKE
4BATHROOM FITTINGSGOOD QUALITY ,STANDARD MAKE
5WOOD WORK ETCGOOD QUALITY ,STANDARD MAKE
6DOORS AND WINDOS FRAMESGOOD QUALITY ,STANDARD MAKE
7GLASS WORKGOOD QUALITY ,STANDARD MAKE
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSBEC/POLYPACK/AKG
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
1 . 2 WALLSGOOD QUALITY ,STANDARD MAKE
1 . 3 CEILINGGOOD QUALITY ,STANDARD MAKE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
2 . 2 WALLSGOOD QUALITY ,STANDARD MAKE
2 . 3 CEILINGGOOD QUALITY ,STANDARD MAKE
2 . 4 MODULAR WARDROBESGOOD QUALITY ,STANDARD MAKE
3 . MASTER TOILET
3 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
3 . 2 WALLSGOOD QUALITY ,STANDARD MAKE
3 . 3 CEILINGGOOD QUALITY ,STANDARD MAKE
3 . 4 COUNTERSGOOD QUALITY ,STANDARD MAKE
3 . 5 SANITARY WARE/CP FITTINGSGOOD QUALITY ,STANDARD MAKE
3 . 6 FITTING/FIXTURESGOOD QUALITY ,STANDARD MAKE
4 . BED ROOMS
4 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
4 . 2 WALLSGOOD QUALITY ,STANDARD MAKE
4 . 3 CEILINGGOOD QUALITY ,STANDARD MAKE
4 . 4 WARDROBESGOOD QUALITY ,STANDARD MAKE
5 . TOILET
5 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
5 . 2 WALLSGOOD QUALITY ,STANDARD MAKE
5 . 3 CEILINGGOOD QUALITY ,STANDARD MAKE
5 . 4 COUNTERSGOOD QUALITY ,STANDARD MAKE
5 . 5 SANITARY WARE/CP FITTINGSGOOD QUALITY ,STANDARD MAKE
5 . 6 FIXTURESGOOD QUALITY ,STANDARD MAKE
6 . KITCHEN
6 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
6 . 2 WALLSGOOD QUALITY ,STANDARD MAKE
6 . 3 CEILINGGOOD QUALITY ,STANDARD MAKE
6 . 4 COUNTERSGOOD QUALITY ,STANDARD MAKE
6 . 5 FIXTURESGOOD QUALITY ,STANDARD MAKE
6 . 6 KITCHEN APPLIANCESGOOD QUALITY ,STANDARD MAKE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
7 . 2 WALLS & CEILINGGOOD QUALITY ,STANDARD MAKE
7 . 3 TOILETGOOD QUALITY ,STANDARD MAKE
7 . 4 BALCONYGOOD QUALITY ,STANDARD MAKE
8 . SIT-OUTS
8 . 1 FLOORGOOD QUALITY ,STANDARD MAKE
8 . 2 WALLS & CEILINGGOOD QUALITY ,STANDARD MAKE
8 . 3 RAILINGSGOOD QUALITY ,STANDARD MAKE
8 . 4 FIXTURESGOOD QUALITY ,STANDARD MAKE












Sr. No.Document DescriptionDate of Document UploadView Document
1 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 26-12-2023 View Document
2 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 26-12-2023 View Document
3 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 26-12-2023 View Document
4 DEMARCATION PLAN 26-12-2023 View Document
5 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 26-12-2023 View Document
6 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 26-12-2023 View Document
7 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 26-12-2023 View Document
8 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 27-12-2023 View Document
9 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 22-05-2024 View Document
10 ENVIRONMENT CLEARANCE 22-05-2024 ------
11 CA CERTIFICATE COST AND FUNDS 22-05-2024 ------
12 APPROVAL LETTER OF SERVICE PLAN ESTIMATES 22-05-2024 ------
13 ASSURANCE FOR SEWERAGE CONNECTION FOR DISPOSAL OF 80 KLD SURPLUS_10.744 DT.24.11.2023 22-05-2024 ------
14 ASSURANCE FOR SUPPLY OF 50 KLD STP TREATED WATER FOR CONSTRUCTION_10.744 ACRES DT.24.11.2023 22-05-2024 ------
15 TOWER 2 TYPICAL 11TH FLOOR 23-05-2024 ------
16 APPROVED ESTIMATE REPORT THE 88 22-05-2024 ------
17 TOWER 2 GF 1ST 23-05-2024 ------
18 SITE PLAN FIRE LAYOUT PHASE-1 23-05-2024 ------
19 ZONING PLAN 22-05-2024 View Document
20 LAND TITLE SEARCH REPORT 22-05-2024 ------
21 NON ENCUMBRANCE 22-05-2024 ------
22 POWER ASSURANCE 22-05-2024 ------
23 TOWER 1 ELEVATION B D 23-05-2024 ------
24 WATER SUPPLY SHEMATIC 23-05-2024 ------
25 ROAD LAYOUT PHASE-1 23-05-2024 ------
26 AFFIDAVIT BANK ACCOUNT 4(2)(L)(D) 22-05-2024 ------
27 TOWER 1 SHOPPING GROUND 1ST FLOOR AREA COMP 23-05-2024 ------
28 NO DUES CERTIFICATE 22-05-2024 ------
29 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 23-05-2024 View Document
30 SEWER LAYOUT 23-05-2024 ------
31 TOWER 11 TYPICAL FLOOR 23-05-2024 ------
32 TOWER 2 ELEVATION A B 23-05-2024 ------
33 LOI 10.744 ACRES 22-05-2024 ------
34 PART SITE PLAN PHASE1 - 2 22-05-2024 ------
35 REPORT & ESTIMATE 23-05-2024 ------
36 EWS FLOOR PLAN 22-05-2024 ------
37 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 22-05-2024 View Document
38 SITE STORM WATER PLAN PHASE-1 23-05-2024 ------
39 TYPICAL FLOOR PLUMBING 23-05-2024 ------
40 ASSURANCE FOR STORM WATER CONNECTION FOR 10.744 ACRES DT.29.11.2023 22-05-2024 ------
41 IRRIGATION WATER LINE 22-05-2024 ------
42 LICENSE RENEWAL 22-05-2024 ------
43 PART SITE PLAN PHASE1 - 1 22-05-2024 ------
44 SECTION TOWER 2 23-05-2024 ------
45 SIJRA 23-05-2024 ------
46 TREE CUTTING PERMISSION 23-05-2024 ------
47 WATER SUPPLY LAYOUT 23-05-2024 ------
48 ASSURANCE FOR DOMESTIC WATER SUPPLY 22-05-2024 ------
49 BANK UNDERTAKING THE 88 22-05-2024 ------
50 FIRE FIGHTING SCHEME 22-05-2024 ------
51 SITE SEWAGE PLAN PHASE-1 23-05-2024 ------
52 APPROVAL LETTER OF SPE 22-05-2024 ------
53 CONSTRUCTION WATER NOC 10.744 ACRES 22-05-2024 ------
54 PART SITE PLAN PHASE1 22-05-2024 ------
55 RENEWAL OF LICENSE 23-05-2024 ------
56 SECTION TOWER 1 23-05-2024 ------
57 AIRPORT HEIGHT CLEARANCE 22-05-2024 ------
58 FOREST NOC 22-05-2024 ------
59 SITE SERVICES 23-05-2024 ------
60 TOWER 2 C D ELEVATION 23-05-2024 ------
61 SITE PLAN ELECTRICAL LAYOUT PHASE-1 23-05-2024 ------
62 BASEMENT PLAN & AREA DIAGRAM 22-05-2024 ------
63 APPROVED BUILDING PLAN BR III LETTER 22-05-2024 ------
64 TOWER ELEVATION A C 23-05-2024 ------
65 SITE WATER SUPPLY LAYOUT PHASE-1 23-05-2024 ------
66 STORM LAYOUT 23-05-2024 ------