HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1363-2023
Submission Date : 11-05-2023 12:16:38 PM
Applicant Type : Company
Project Type: NEW




HERO REALTY PRIVATE LIMITED
264, OKHLA INDUSTRIAL ESTATE, PHASE 3, NEW DELHI 110020
1147467000
9820702984 (Number Shared by Promoter in Public)
compliance@herorealty.in
https://herohomes.in/hero-earth.html
XXXX416L
U70109DL2006PTC152383
 
 


 
 


 
 


 
 


 
 







THE ARK
SECTOR 85, VILLAGE SIKANDARPUR BADHA, GURGRAM-122004
MANESAR
GURUGRAM
1147467000
9312736841 (Number Shared by Promoter in Public)
compliance@herorealty.in
MUKUL KANSAL
1147467000
9312736841 (Number Shared by Promoter in Public)
mukul.kansal@herorealty.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11280619-04-2023202850HDFC BANK-OKHLA INDUSTRIAL AREA PH3, NEW DELHI 110020HRERA Gurugram
21280719-04-202316227.80HDFC BANK-OKHLA INDUSTRIAL AREA PH3, NEW DELHI 110020HRERA Gurugram
32988631-05-2023194734KOTAK MAHINDRA BANKHRERA Gurugram







5.0125 (Acre)
1
1
5.0125 (Acre)
193 of 2022 dated 24.11.2022 valid upto 23.11.2027
Yes







13765 Lakhs
9672.7 Lakhs
0 Lakhs
954 Lakhs
3138 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD10126.328
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS4359.638
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1534.520
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION111.34
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES2028.501
12ANY OTHER0
13COMMERCIAL811.350
14AREA1424.514
Total20396.191




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNNo
WATER SUPPLYGMDANo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALGMDANo
STORM WATER DRAINAGEGMDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS137.76YET TO BE PREPARED
2WATER SUPPLY SYSTEM59.28YET TO BE PREPARED
3STORM WATER DRAINAGE146.35YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM82.08YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL22.48YET TO BE PREPARED
6STREET LIGHTING30YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS64.91YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15STP136.67YET TO BE PREPARED
16UNDERGROUND WATER TANK93.83YET TO BE PREPARED
17RAIN WATER HARVESTING39.47YET TO BE PREPARED
18ELECTRICAL SUB STATION80YET TO BE PREPARED
19CONSTRUCTION OF CIRCULATION ROAD 60.18YET TO BE PREPARED


24-11-2022 (date)
NA (date)
01-06-2023
30-06-2025
Plot Area(In Square Meter)Number of plots in the project
147.87517
149.9887
135.8766
117.24916
117.26316
149.9921
147.6161
135.6991
129.0891
129.85011


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage10.5731.71
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements27.5547.2353.576.89
Water Supply System0016.8013.17
Sewerage treatment & garbage disposal022.4800
Electricity Supply System00.4833.8019.31
Storm Water Drainage60.1743.9100
Parks and Playgrounds0015.1528.85
Clubhouse/community centres0000
Shopping area0000
Other0000
UGT21.3736.4920.85
STP31.1353.1530.37
ELECTRICAL SUB STATION0.6726.67

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System24.374.94
Sewerage treatment & garbage disposal00
Electricity Supply System28.490
Storm Water Drainage00
Parks and Playgrounds20.920
Clubhouse/community centres00
Shopping area00
Other00
RAIN WATER HARVESTING39.47
ELECTRICAL SUB STATION49.333.33
CONSTRUCTION OF CIRCULATION ROAD TWENTY FOUR METER AS PER CONDITION OF LICENSE60.18
STREET LIGHTING6.0024.00
STP22.02
UGT15.12












Yes
No
AXIS BANK LTD., FRONT GROUND FLOOR, 202, OKHLA IND. ESTATE PH- III , DELHI-110020
923020018069921
UTIB0005039
110211373
5039
Mr. Sunil Kant Munjal, Mr. Jogendra Singh, Mr. Amit Kumar Aggarwal, Mr. Dharmesh Pramod Shah, Mr. Brij Nandan Yadava, Mr. Rakesh Kumar Address 264, Okhla Industrial Estate, Phase III, New Delhi 110020
yes











Yes
Yes
No
No
No
No
No
No
No
No


Yes
No
Yes
No
Yes
Yes
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO, 193 OF 20222ALREADY BEEN OBTAINED24-11-2022
II. LAYOUT PLANALREADY BEEN OBTAINED24-11-2022








Yes


Yes


As per RERA norms







ALAKNANDA-4, UTTRAKHAND
31978.25
0
172
0
171
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
94001174
Cost of the apartments000
Cost of the infrastructure00534
Others costs00640


1406 Lakhs
1327.62 Lakhs
0 Lakhs
952 Lakhs
No
22-08-2023
22-08-2023




ALAKNANDA-5, UTTRAKHAND
16501.05
0
106
0
102
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
5300515
Cost of the apartments000
Cost of the infrastructure00100
Others costs00415


691.366 Lakhs
662.90 Lakhs
0 Lakhs
419 Lakhs
No
22-08-2023
22-08-2023




HERO HOMES LUDHIANA PHASE-1, PUNJAB
16248
279
0
268
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
17567.17017567.22
Cost of the apartments11200010695.399
Cost of the infrastructure901.38001043.94
Others costs5465.7905827.88


17021.09 Lakhs
942.194 Lakhs
10000 Lakhs
14034 Lakhs
Yes
12-06-2020
25-10-2021




HERO HOMES MOHALI PHASE-1, PUNJAB
26069
547
0
541
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
25300026099.43
Cost of the apartments17500017003.57
Cost of the infrastructure150001827.92
Others costs630007267.93


34581.12 Lakhs
1711.09 Lakhs
23900 Lakhs
24476 Lakhs
Yes
30-03-2021
08-02-2021




HERO HOMES MOHALI PHASE-2A, PUNJAB
16353.1
404
0
401
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
23194010112
Cost of the apartments1757606776
Cost of the infrastructure15340329
Others costs408403007


8936.76 Lakhs
23390.40 Lakhs
0 Lakhs
6112 Lakhs
No
31-12-2026
31-12-2026




HERO HOMES MOHALI PHASE-2B, PUNJAB
5360.7
246
0
193
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1408502580.85
Cost of the apartments880001087.54
Cost of the infrastructure153400.026
Others costs375101493.28


3292.37 Lakhs
18338.68 Lakhs
0 Lakhs
2303 Lakhs
No
31-07-2027
31-07-2027




ALAKNANDA-1, UTTRAKHAND
167066.37
0
569
0
569
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
157901638.68
Cost of the apartments000
Cost of the infrastructure157901579
Others costs0059.68


8872.37 Lakhs
192.83 Lakhs
0 Lakhs
6010 Lakhs
Yes
17-02-2014
17-02-2014




ALAKNANDA-2, UTTRAKHAND
93725.125
0
331
0
315
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
134101453
Cost of the apartments000
Cost of the infrastructure001341
Others costs00112


4892.94 Lakhs
460.022 Lakhs
0 Lakhs
3420 Lakhs
Yes
17-02-2014
17-02-2014




ALAKNANDA-3, UTTRAKHAND
31978.25
0
85
0
85
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
7050423
Cost of the apartments000
Cost of the infrastructure00101
Others costs00322


1329.52 Lakhs
1254.84 Lakhs
0 Lakhs
862 Lakhs
Yes
22-08-2023
22-08-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN10-05-2023 View Document
2CASH FLOW STATEMENT OF THE PROPOSED PROJECT10-05-2023 View Document
3DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD10-05-2023 View Document
4DEMARCATION PLAN10-05-2023 View Document
5A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS10-05-2023 View Document
6IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN10-05-2023 View Document
7NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT10-05-2023 View Document
8CHANGE OF DEVELOPER27-06-2023 ------
9SEWERAGE LAYOUT27-06-2023 ------
10ROAD LAYOUT27-06-2023 ------
11IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN27-06-2023 View Document
12STORM WATER LAYOUT27-06-2023 ------
13CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT27-06-2023 View Document
14WATER SUPPLY PLAN27-06-2023 ------
15BANK UNDERTAKING27-06-2023 ------
16DOMESTIC WATER SUPPLY LAYOUT27-06-2023 ------
17POWER ASSURANCE27-06-2023 ------
18ZONING PLAN27-06-2023 View Document
19COPY OF LICENSE ALONG WITH SCHEDULE OF LAND27-06-2023 View Document
20DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.27-06-2023 View Document
21REVISED PERT CHART27-06-2023 ------