264, OKHLA INDUSTRIAL ESTATE, PHASE 3,
NEW DELHI 110020
1147467000
9820702984 (Number Shared by Promoter in Public)
compliance@herorealty.in
https://herohomes.in/hero-earth.html
XXXX416L
U70109DL2006PTC152383
THE ARK
SECTOR 85, VILLAGE SIKANDARPUR BADHA, GURGRAM-122004
MANESAR
GURUGRAM
1147467000
9312736841 (Number Shared by Promoter in Public)
compliance@herorealty.in
MUKUL KANSAL
1147467000
9312736841 (Number Shared by Promoter in Public)
mukul.kansal@herorealty.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
12806
19-04-2023
202850
HDFC BANK-OKHLA INDUSTRIAL AREA PH3, NEW DELHI 110020
HRERA Gurugram
2
12807
19-04-2023
16227.80
HDFC BANK-OKHLA INDUSTRIAL AREA PH3, NEW DELHI 110020
HRERA Gurugram
3
29886
31-05-2023
194734
KOTAK MAHINDRA BANK
HRERA Gurugram
5.0125 (Acre)
1
1
5.0125 (Acre)
193 of 2022 dated 24.11.2022 valid upto 23.11.2027
Yes
13765 Lakhs
9672.7 Lakhs
0 Lakhs
954 Lakhs
3138 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
10126.328
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
4359.638
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1534.520
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
111.34
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
2028.501
12
ANY OTHER
0
13
COMMERCIAL
811.350
14
AREA
1424.514
Total
20396.191
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVPN
No
WATER SUPPLY
GMDA
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
GMDA
No
STORM WATER DRAINAGE
GMDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
137.76
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
59.28
YET TO BE PREPARED
3
STORM WATER DRAINAGE
146.35
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
82.08
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
22.48
YET TO BE PREPARED
6
STREET LIGHTING
30
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
64.91
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
STP
136.67
YET TO BE PREPARED
16
UNDERGROUND WATER TANK
93.83
YET TO BE PREPARED
17
RAIN WATER HARVESTING
39.47
YET TO BE PREPARED
18
ELECTRICAL SUB STATION
80
YET TO BE PREPARED
19
CONSTRUCTION OF CIRCULATION ROAD
60.18
YET TO BE PREPARED
24-11-2022 (date)
NA (date)
01-06-2023
30-06-2025
Plot Area(In Square Meter)
Number of plots in the project
147.875
17
149.988
7
135.876
6
117.249
16
117.263
16
149.992
1
147.616
1
135.699
1
129.089
1
129.850
11
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
0
Storm Water Drainage
10.57
31.71
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
27.55
47.23
53.57
6.89
Water Supply System
0
0
16.80
13.17
Sewerage treatment & garbage disposal
0
22.48
0
0
Electricity Supply System
0
0.48
33.80
19.31
Storm Water Drainage
60.17
43.91
0
0
Parks and Playgrounds
0
0
15.15
28.85
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
UGT
21.37
36.49
20.85
STP
31.13
53.15
30.37
ELECTRICAL SUB STATION
0.67
26.67
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
24.37
4.94
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
28.49
0
Storm Water Drainage
0
0
Parks and Playgrounds
20.92
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
RAIN WATER HARVESTING
39.47
ELECTRICAL SUB STATION
49.33
3.33
CONSTRUCTION OF CIRCULATION ROAD TWENTY FOUR METER AS PER CONDITION OF LICENSE
60.18
STREET LIGHTING
6.00
24.00
STP
22.02
UGT
15.12
Yes
No
AXIS BANK LTD., FRONT GROUND FLOOR, 202, OKHLA IND. ESTATE PH- III , DELHI-110020
923020018069921
UTIB0005039
110211373
5039
Mr. Sunil Kant Munjal, Mr. Jogendra Singh, Mr. Amit Kumar Aggarwal, Mr. Dharmesh Pramod Shah, Mr. Brij Nandan Yadava, Mr. Rakesh Kumar Address 264, Okhla Industrial Estate, Phase III,
New Delhi 110020
yes
Yes
Yes
No
No
No
No
No
No
No
No
Yes
No
Yes
No
Yes
Yes
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO, 193 OF 20222
ALREADY BEEN OBTAINED
24-11-2022
II. LAYOUT PLAN
ALREADY BEEN OBTAINED
24-11-2022
Yes
Yes
As per RERA norms
ALAKNANDA-4, UTTRAKHAND
31978.25
0
172
0
171
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
940
0
1174
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
534
Others costs
0
0
640
1406 Lakhs
1327.62 Lakhs
0 Lakhs
952 Lakhs
No
22-08-2023
22-08-2023
ALAKNANDA-5, UTTRAKHAND
16501.05
0
106
0
102
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
530
0
515
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
100
Others costs
0
0
415
691.366 Lakhs
662.90 Lakhs
0 Lakhs
419 Lakhs
No
22-08-2023
22-08-2023
HERO HOMES LUDHIANA PHASE-1, PUNJAB
16248
279
0
268
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
17567.17
0
17567.22
Cost of the apartments
11200
0
10695.399
Cost of the infrastructure
901.380
0
1043.94
Others costs
5465.79
0
5827.88
17021.09 Lakhs
942.194 Lakhs
10000 Lakhs
14034 Lakhs
Yes
12-06-2020
25-10-2021
HERO HOMES MOHALI PHASE-1, PUNJAB
26069
547
0
541
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
25300
0
26099.43
Cost of the apartments
17500
0
17003.57
Cost of the infrastructure
1500
0
1827.92
Others costs
6300
0
7267.93
34581.12 Lakhs
1711.09 Lakhs
23900 Lakhs
24476 Lakhs
Yes
30-03-2021
08-02-2021
HERO HOMES MOHALI PHASE-2A, PUNJAB
16353.1
404
0
401
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
23194
0
10112
Cost of the apartments
17576
0
6776
Cost of the infrastructure
1534
0
329
Others costs
4084
0
3007
8936.76 Lakhs
23390.40 Lakhs
0 Lakhs
6112 Lakhs
No
31-12-2026
31-12-2026
HERO HOMES MOHALI PHASE-2B, PUNJAB
5360.7
246
0
193
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
14085
0
2580.85
Cost of the apartments
8800
0
1087.54
Cost of the infrastructure
1534
0
0.026
Others costs
3751
0
1493.28
3292.37 Lakhs
18338.68 Lakhs
0 Lakhs
2303 Lakhs
No
31-07-2027
31-07-2027
ALAKNANDA-1, UTTRAKHAND
167066.37
0
569
0
569
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1579
0
1638.68
Cost of the apartments
0
0
0
Cost of the infrastructure
1579
0
1579
Others costs
0
0
59.68
8872.37 Lakhs
192.83 Lakhs
0 Lakhs
6010 Lakhs
Yes
17-02-2014
17-02-2014
ALAKNANDA-2, UTTRAKHAND
93725.125
0
331
0
315
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1341
0
1453
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
1341
Others costs
0
0
112
4892.94 Lakhs
460.022 Lakhs
0 Lakhs
3420 Lakhs
Yes
17-02-2014
17-02-2014
ALAKNANDA-3, UTTRAKHAND
31978.25
0
85
0
85
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
705
0
423
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
101
Others costs
0
0
322
1329.52 Lakhs
1254.84 Lakhs
0 Lakhs
862 Lakhs
Yes
22-08-2023
22-08-2023
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NA
2
WALL FINISHING DETAILS
NA
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
NA
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
NA
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
NA
14.1
MAIN DOORS
NA
14.2
INTERNAL DOORS
NA
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT