HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1230-2022
Submission Date : 22-12-2022 05:03:37 PM
Applicant Type : Company
Project Type: NEW




AVIANA GREENS ESTATES PVT LTD
OFFICE NO-15,2NDFLOORE,MGF MEGACITYMALL,MG ROAD
01244268070
9812041109 (Number Shared by Promoter in Public)
amarjeetdhillon5665@gmail.com
https://www.avianagreen.com/
XXXX735B
U70109DL2016PTC306330
 
 


 
 


 
 


 
 


 
 







CHINTAMANIS
SECTOR 103,VILL DAULTABAD, GURUGRAM
KADIPUR ST
GURUGRAM
01244268070
9812041109 (Number Shared by Promoter in Public)
vikrant.kamboj@chintamanis.co.in
AMARJEET DHILLON
01244268070
9812041109 (Number Shared by Promoter in Public)
amarjeetdhillon5665@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
14793628-01-2022850678AXIS BANKHRERA Gurugram
24874719-12-20221100000AXIS BANKHRERA Gurugram
350394420-01-2023159000ICICI BANK HRERA Gurugram







4.1875 (Acre)
2.62
2.62
4.1875 (Acre)
LICENCE NO 97 OF 2021 DATED 12-11-2021
No
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Address     GURUGRAM
Annexure-B- COLLABORATOR
BEFORE GRANT OF LICENCE
Yes
IMPORTANT POINTS
No
Yes
Yes







30860.14 Lakhs
5433.42 Lakhs
14140.66 Lakhs
2862.60 Lakhs
8423.46 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.6417
3CONSTRUCTION OF ROADS1.5320
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1.1060
6GREEN BELTS0
7VEHICLE PARKINGS0.7961
8ELECTRICITY SUB-STATION0.0398
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.0078
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13STORMWATERDRAINAGE0.0135
14STP0.0680
15UGT0.0870
Total4.2919




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNHAIYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNLYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS108.33AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM343.18AS PER PROJECT REPORT
3STORM WATER DRAINAGE42.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM300.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL335.00AS PER PROJECT REPORT
6STREET LIGHTING39.07AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING30.00AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS16.20AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15PARKING166.67AS PER PROJECT REPORT
16RAIN WATER HARVESTING22.68AS PER PROJECT REPORT
17ELECTRICAL SUB STATION226.80AS PER PROJECT REPORT
18MAINTENANCE CHARGES FOR ELEVEN YEARS174.27AS PER PROJECT REPORT
19PODIUM BASEMENT PARKING AND STILT PARKING AND PODIUM PARK AND AMENITIES 1058.40AS PER PROJECT REPORT


12-11-2021 (date)
13-01-2023 (date)
01-05-2023
11-09-2026
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings133.17761
Apartment/Shops/Other Buildings125.3541
Apartment/Shops/Other Buildings215.4641
Apartment/Shops/Other Buildings112.51361
Apartment/Shops/Other Buildings172.0841
Apartment/Shops/Other Buildings96.61361
Apartment/Shops/Other Buildings162.5641
Apartment/Shops/Other Buildings92.281441
Apartment/Shops/Other Buildings147.9741
Apartment/Shops/Other Buildings20491





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1732.231484.77989.85742.38
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1060.551060.551060.551060.55
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments883.79883.79883.79883.79
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments636.33636.33141.41
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10.00
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.3916.3916.3916.39
Water Supply System36.1254.1954.1954.19
Sewerage treatment & garbage disposal35.2652.8952.8952.89
Electricity Supply System0000
Storm Water Drainage3.009.009.009.00
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical Sub Station0048.6048.60
Parking25.025.025.025.0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.3916.3900
Water Supply System54.1954.1936.120
Sewerage treatment & garbage disposal52.8952.8935.260
Electricity Supply System112.50112.5075.000
Storm Water Drainage9.003.0000
Parks and Playgrounds0016.200
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Light15.6323.44
Security and Firefighting7.5022.50
Rainwater Harvesting17.015.67
Electrical Sub Station48.6048.6032.400
Parking25.025.016.67
Podium Basement Parking and Stilt Parking and Podium Park and Amenities352.80352.80352.80












Yes
No
AXIS BANK, SHOP NO 3,3A,4,5 MEGA CITY MALL,M G ROAD ,GURUGRAM, HARYANA
921020051630933
UTIB0000540
110211047
540
AMARJEET DHILLON
YES











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE NO 97 OF 2021 DATED 12-11-2021 BY TOWN AND COUNTRY PLANNING ALREADY BEEN OBTAINED12-11-2021








Yes


Yes


YES













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES
2WALL FINISHING DETAILSOBD
3KITCHEN DETAILSISI MARKED
4BATHROOM FITTINGSISI MARKED
5WOOD WORK ETCHARD WOOD
6DOORS AND WINDOS FRAMESHARD WOOD FRAMES/FLUSH DOORS
7GLASS WORKISI MARKED
8ELECTRIC FITTINGSISI MARKED
9CONDUCTING AND WIRING DETAILSISI MARKED
10CUPBOARD DETAILSWOODEN
11WATER STORAGEISI MARKED
12LIFT DETAILSAS PER STANDERDS
13EXTERNAL GLAZINGSMS
13.1WINDOWS/GLAZINGSMS
14DOORSFLUSH DOORS
14.1MAIN DOORSHARD WOOD
14.2INTERNAL DOORSFLUSH DOORS
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTUR PAINT
20INTERNAL FINISHINGPAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD
1 . 3 CEILINGOBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSOBD
2 . 3 CEILINGOBD
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORVITRIFIED TILES
3 . 2 WALLSOBD
3 . 3 CEILINGOBD
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSISI MARKED
3 . 6 FITTING/FIXTURESISI MARKED
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOBD
4 . 3 CEILINGOBD
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORVITRIFIED TILES
5 . 2 WALLSOBD
5 . 3 CEILINGOBD
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSISI MARKED
5 . 6 FIXTURESISI MARKED
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSOBD
6 . 3 CEILINGOBD
6 . 4 COUNTERSNA
6 . 5 FIXTURESISI MARKED
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES
7 . 2 WALLS & CEILINGOBD
7 . 3 TOILETISI MARKED
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORVITRIFIED TILES
8 . 2 WALLS & CEILINGOBD
8 . 3 RAILINGSMS
8 . 4 FIXTURESISI MARKED












Sr. No.Document DescriptionDate of Document UploadView Document
1ZONING PLAN21-12-2022 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND21-12-2022 View Document
3SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN21-12-2022 View Document
4TOWER A - 22ND, TERRACE & MUMTY FLOOR PLANS & AREA DIAGRAM05-06-2023 ------
5TOWER A SECTION05-06-2023 ------
6CASH FLOW STATEMENT OF THE PROPOSED PROJECT05-06-2023 View Document
7TOWER C ELEVATIONS105-06-2023 ------
8TOWER C ELEVATIONS205-06-2023 ------
9TOWER'S UNIT CARPET AREA DETAIL05-06-2023 ------
10FIRST FLOOR LEVEL_SITE PLAN05-06-2023 ------
11TOWER D - FLOOR PLANS & AREA DIAGRAM05-06-2023 ------
12IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN05-06-2023 View Document
13TOWER A - TERRACE PLAN & PLUMBING LAYOUT05-06-2023 ------
14SEWERAGE PLAN05-06-2023 ------
15TOWER A ELEVATIONS205-06-2023 ------
16TOWER B - STILT FLOOR PLAN & AREA DIAGRAM05-06-2023 ------
17TOWER B - TERRACE PLAN & PLUMBING LAYOUT05-06-2023 ------
18TOWER B SECTION05-06-2023 ------
19TOWER B - 1ST TO 18TH FLOOR PLANS & AREA DIAGRAM05-06-2023 ------
20TOWER C1-C2 - STILT, 1ST TO 18TH FLOOR PLANS & AREA DIAGRAM05-06-2023 ------
21TOWER B ELEVATIONS105-06-2023 ------
22DOMESTIC WATER SUPPLY05-06-2023 ------
23TOWER A - STILT, 1ST TO 19TH FLOOR PLANS & AREA DIAGRAM05-06-2023 ------
24TOWER B ELEVATIONS205-06-2023 ------
25BUILDING PLAN APPROVAL LETTER05-06-2023 ------
26LOI05-06-2023 ------
27TOWER A - 20TH & 21ST FLOOR PLANS & AREA DIAGRAM05-06-2023 ------
28TOWER B - TYPICAL FLOOR PLAN & PLUMBING LAYOUT05-06-2023 ------
29STILT FLOOR SITE LEVEL PLAN & STILT, PODIUM, PARKING DIAGRAM & CALCULATION05-06-2023 ------
30IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN05-06-2023 View Document
31NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT05-06-2023 View Document
32AIRPORT HEIGHT CLEARANCE05-06-2023 ------
33FLUSHING & IRRIGATION WATER SUPPLY05-06-2023 ------
34LANDSCAPE PLAN05-06-2023 ------
35STILT SITE SERVICE PLAN05-06-2023 ------
36TOWER C1 & C2, TERRACE PLAN & PLUMBING LAYOUT05-06-2023 ------
37ROAD PAVEMENT PLAN05-06-2023 ------
38SOLID WASTE MANAGEMENT PLAN05-06-2023 ------
39STORM WATER DRAINAGE PLAN05-06-2023 ------
40STREET LIGHT PLAN05-06-2023 ------
41AVIANA BR-305-06-2023 ------
42BASEMENT PARKING PLAN & AREA CALCULATION05-06-2023 ------
43GREEN & OPEN AREA PARKING CALCULATION05-06-2023 ------
44TOWER A ELEVATIONS105-06-2023 ------
45TOWER A - TYPICAL FLOOR PLAN & PLUMBING LAYOUT05-06-2023 ------
46TOWER B - 19TH & 20TH FLOOR PLAN & AREA DIAGRAM05-06-2023 ------
47TOWER B - TERRACE & AREA DIAGRAM05-06-2023 ------
48TOWER C & D SECTION05-06-2023 ------
49TOWER C1 & C2, TYPICAL FLOOR PLAN & PLUMBING LAYOUT05-06-2023 ------
50TOWER D ELEVATIONS05-06-2023 ------
51TOWER D_ALL FLOOR PLAN PLUMBING LAYOUT05-06-2023 ------
52DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.23-06-2023 View Document
53TOWER C1 & C2 - 19TH & 20TH FLOOR PLAN & AREA DIAGRAM12-07-2023 ------