HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1166-2022
Submission Date : 15-03-2023 05:11:32 PM
Applicant Type : Firm
Project Type: NEW


DCM LTD. (IN JOINT DEVELOPMENT WITH GCD PRIME, LC NO. 179 OF 2022)
2050-2052, 2ND FLOOR, PLAZA-II, CENTRAL SQUARE, 20 MANOHAR LAL KHURANA MARG, BARA HINDU RAO, DELHI-110006
01141539181
9999395319 (Number Shared by Promoter in Public)
hisarproject@dcm.in
L74899DL1889PLC000004
AAACD1012E























GULMOHAR PARK
SECTOR 23 IN REVENUE ESTATE OF VILLAGE BIR, HISAR
HISAR
HISAR
01244052395
9811787243 (Number Shared by Promoter in Public)
greencitydevelopers21@gmail.com
JITENDER KUMAR
01244052395
9811787243 (Number Shared by Promoter in Public)
greencitydevelopers21@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
197903-12-2022731500HDFC BANKHRERA Panchkula







67.275 (Acre)
NA
0
67.275 (Acre)
179 of 2022
Yes







28298.75 Lakhs
8745.75 Lakhs
0 Lakhs
12000 Lakhs
7553 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD37.62
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS17.5109
4PAVEMENTS0
5PARKS AND PLAYGROUNDS5.33
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.084
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES6.73
12ANY OTHER0
Total67.2749




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNONo
WATER SUPPLYHSVPNo
ELECTRICITYDHVBNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS3225YET TO BE PREPARED
2WATER SUPPLY SYSTEM1984YET TO BE PREPARED
3STORM WATER DRAINAGE995YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM600YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL1246YET TO BE PREPARED
6STREET LIGHTING45YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS79YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER3827YET TO BE PREPARED


07-11-2022 (date)
NA (date)
01-01-2023
31-12-2025
Plot Area(In Square Meter)Number of plots in the project
149.99822
129.7543
129.9985
149.881
146.731
142.211
137.691
133.171
128.651
124.131
132.621
127.041
124.11
122.021
10866.741


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots6086.27

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements105150201403
Water Supply System101165189209
Sewerage treatment & garbage disposal5560143178
Electricity Supply System0000
Storm Water Drainage83111115156
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other256414552854

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements668666540156
Water Supply System336256165254
Sewerage treatment & garbage disposal15835627620
Electricity Supply System15416616778
Storm Water Drainage15616783124
Parks and Playgrounds0202027
Clubhouse/community centres0000
Shopping area0000
Other628319319200

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements84848484
Water Supply System77777777
Sewerage treatment & garbage disposal0000
Electricity Supply System20202020
Storm Water Drainage0000
Parks and Playgrounds3333
Clubhouse/community centres0000
Shopping area0000
Other75707070












No
No
HDFC BANK, 209-214, KAILASH BUILDING 26, KASTURBA GANDHI MARG
00030350008901
HDFC0000003
110240001
0003
Ashwani Singhal, Jitender Tuli, Sumant Bharat Ram. 2050-2052, 2nd floor, Plaza-II, Central square, 20 Manohar Lal Khurana Marg, Bara Hindu Rao, Delhi-110006
Uploaded











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED07-11-2022
II. DEMARCATIONAPPLIED FOR BUT YET TO RECEIVE16-11-2022
III. ZONINGAPPLIED FOR BUT YET TO RECEIVE16-11-2022
IV. SERVICE ESTIMATESYET TO FILE FOR APPROVAL31-12-2022








Yes


Yes


As per HRERA













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND14-11-2022 View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN14-11-2022 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN14-11-2022 View Document
4DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.25-11-2022 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT25-11-2022 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 registration is kept in abeyance till further order 24-04-2023 View Document