HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1123-2022
Submission Date : 12-09-2022 06:37:58 PM
Applicant Type : Company
Project Type: NEW




ATS REALWORTH PVT LTD
ATS TOWER, PLOT NO-16, SECTOR 135, NOIDA (UP) PIN -201305
01207111500
9643007884 (Number Shared by Promoter in Public)
Compliance@homekraft.in
http://homekraft.in
XXXX065F
U70109DL2010PTC243081
 
 


 
 


 
 


 
 







RAINBOW PARK
SECTOR- 99A,VILLAGE- GOPALPUR,
GURGAON
GURUGRAM
1207111500
9313329015 (Number Shared by Promoter in Public)
Compliance@homekraft.in
GOVIND MADHAV SHARMA
1207111500
9313329015 (Number Shared by Promoter in Public)
Compliance@homekraft.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
172585609-09-20221187027YES BANKHRERA Gurugram







8.352 (Acre)
89,334.52
200.69
11.5875 (Acre)
37 of 2013 (02-06-2024)
No
Address     296, FOREST LANE. SAINK FARMS, NEB SARAI, NEW DELHI-110068
Annexure-B- BIP
TO BE CHANGED
Yes
YES
No
Yes
Yes







51058.34 Lakhs
9796 Lakhs
15175.35 Lakhs
5918.88 Lakhs
20168.11 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 3.633
3CONSTRUCTION OF ROADS 1.389
4PAVEMENTS 0.71
5PARKS AND PLAYGROUNDS 1.371
6GREEN BELTS 0
7VEHICLE PARKINGS 0.791
8ELECTRICITY SUB-STATION 0.128
9CLUB HOUSE 0.12
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.21
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total8.352




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS110YET TO BE PREPARED
2WATER SUPPLY SYSTEM864YET TO BE PREPARED
3STORM WATER DRAINAGE13YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM961YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL130YET TO BE PREPARED
6STREET LIGHTING32YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING307YET TO BE PREPARED
8PLAYGROUNDS AND PARKS44YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE173YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM56YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER53YET TO BE PREPARED
15PARKING174YET TO BE PREPARED
16RAIN WATER HARVESTING17YET TO BE PREPARED
17ELECTRIC SUB STATION62YET TO BE PREPARED
18MISCELLANEOUS ACTIVITY1566YET TO BE PREPARED
19MANPOWER COST968YET TO BE PREPARED
20INSURANCE AND OTHER COST290YET TO BE PREPARED
21SEWAGE SYSTEM97YET TO BE PREPARED


NA (date)
NA (date)
01-08-2022
31-07-2029
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings132.08161
Apartment/Shops/Other Buildings163.32701
Apartment/Shops/Other Buildings126.162003
Apartment/Shops/Other Buildings103.861381
Apartment/Shops/Other Buildings16.991281





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments648.00
Shops0
Plots0
EDC and IDC209.08
Land Cost457.36

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments201.00540
Shops00
Plots00
EDC and IDC162.50
Land Cost359.18359.18
EDC and IDC162.50

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments540540540540
Shops0000
Plots0000
Land Cost359.18353.65353.65353.65
EDC and IDC162.50162.42162.42162.42

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments591.49591.49591.49591.49
Shops0000
Plots0000
Land Cost353.65359.18353.65359.18
EDC and IDC162.42162.50162.42162.50

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments591.49591.49591.49621.33
Shops0000
Plots0000
Land Cost353.65353.65353.65353.65
EDC and IDC162.42162.42162.42162.42

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments621.33621.33621.33621.33
Shops0000
Plots0000
EDC and IDC162.42162.42162.42162.50
Land Cost353.65353.65353.65359.18

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments621.33621.33621.33621.33
Shops0000
Plots0000
Land Cost353.65353.65359.18359.18
EDC and IDC162.42162.42162.50162.50

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments621.33621.33621.3329.84
Shops0000
Plots0000
Land Cost359.18353.65353.65359.18
EDC and IDC162.50162.42162.42162.50




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements35
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System35
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres8.06
Shopping area0
Other200
Manpower Cost58

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0003.25
Water Supply System00037.56
Sewerage treatment & garbage disposal0000
Electricity Supply System001.9636.96
Storm Water Drainage0000.56
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other00050.64
Electrification3.84
Insurance and other cost11.15
Man Power2
Man Power Cost36.33
Insurance and Other Cost11.15
Elecrification3.84

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.253.253.253.25
Water Supply System37.5637.5637.5637.56
Sewerage treatment & garbage disposal4.214.214.214.21
Electricity Supply System36.9636.9636.9636.96
Storm Water Drainage0.560.560.560.56
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other50.6450.6450.6450.64
Man Power36.33
Electrification3.843.843.84
Others Boundary Wall Entry and Exit Gate Signage etc2.30
Insurance and Other Cost11.1511.1511.1511.15
Manpower Cost36.3336.3336.33
Others Boundary Wall Entry and Exit Gate Signage etc2.302.30
Others Boundary Wall Entry and Exit Gate Signage etc0
Elecrification3.84

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.253.253.253.25
Water Supply System37.5637.5637.5637.56
Sewerage treatment & garbage disposal4.214.214.214.21
Electricity Supply System36.9636.9636.9636.96
Storm Water Drainage0.560.560.560.56
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other50.6450.6450.6450.64
Others Boundary Wall Entry and Exit Gate Signage etc2.32.302.30
Electrification Cost3.84
Insurance and Other Cost11.15
Manpower Cost36.3336.3336.3336.33
Security and Firefighting services16.1916.1916.1916.19
Insurance and Other Cost11.1511.1511.15
Others Boundary Wall Entry and Exit Gate Signage e2.30
Electrification cost3.84
Electrification3.843.84

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.253.253.253.25
Water Supply System37.5637.5637.5637.56
Sewerage treatment & garbage disposal4.214.214.214.21
Electricity Supply System36.9636.9636.9636.96
Storm Water Drainage0.560.560.560.56
Parks and Playgrounds0000
Clubhouse/community centres0004.11
Shopping area0000
Other50.6450.6450.6450.64
Security and Firefighting services16.1916.1916.1916.19
Electrification3.843.843.84
Street Light16.0016.00
STP1.372.682.682.68
Underground tank7.487.487.487.48
Manpower Cost36.3336.3336.3336.33
Insurance and Other Cost11.1511.1511.1511.15
Others Boundary Wall Entry and Exit Gate Signage etc2.302.302.30
Others Boundary Wall Entry and Exit Gate Signage etc2.30

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.253.253.253.25
Water Supply System37.5637.5637.5637.56
Sewerage treatment & garbage disposal4.214.214.214.21
Electricity Supply System36.9636.9636.9636.96
Storm Water Drainage0.560.560.560.56
Parks and Playgrounds0000
Clubhouse/community centres13.4613.4613.4613.46
Shopping area0000
Other50.6450.6450.6450.64
Manpower Cost36.3336.3336.3336.33
Others Boundary Wall Entry and Exit Gate Signage etc2.302.302.302.30
Insurance and Other Cost11.1511.1511.1511.15
Underground tank7.487.487.487.48
STP2.682.682.682.68
Parking19.3319.3319.3319.33
Electrification3.843.843.84
Security and Firefighting services16.1916.1916.1916.19
Electrical Sub Station6.906.906.906.90
Electrification cost3.84

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.253.253.253.25
Water Supply System37.5637.5637.5637.56
Sewerage treatment & garbage disposal4.214.214.214.21
Electricity Supply System36.9636.9636.9636.96
Storm Water Drainage0.560.560.560.56
Parks and Playgrounds008.808.80
Clubhouse/community centres13.4614.4614.4614.46
Shopping area0000
Other50.6450.6450.6450.64
Security and Firefighting services16.1916.1916.1916.19
Electrification3.843.843.843.84
Parking19.3319.3319.3319.33
Electrical Sub Station6.906.906.906.90
Others Boundary Wall Entry and Exit Gate Signage etc2.302.302.30
Insurance and Other Cost11.1511.1511.1511.15
Manpower Cost36.3336.3336.3336.33
Underground tank7.487.487.487.48
STP2.682.682.683.18
Rain water harvesting4.508.0
Others Boundary Wall Entry and Exit Gate Signage etc2.30

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.183.2500
Water Supply System37.9337.5600
Sewerage treatment & garbage disposal4.784.214.210
Electricity Supply System37.5036.9636.9636.96
Storm Water Drainage0.660.5600
Parks and Playgrounds8.418.808.800
Clubhouse/community centres14.4614.4614.466.40
Shopping area0000
Other50.9150.6450.6450.64
Others Boundary Wall Entry and Exit Gate Signage etc2.532.302.302.30
Electrification cost3.84
Security and Firefighting services17.0216.1915.19
Renewable energy system LA and PV PLANT and Misc14.3114.0014.0014.00
Manpower Cost36.1236.3336.3336.33
Insurance and Other Cost11.5511.1511.1511.55
Electrification3.84
Electrification Cost3.983.84
Parking19.21
Rain water harvesting4.10
Underground tank7.32
STP1.78
Electrical Sub Station7.11












Yes
No
YES BANK, SECTOR 63 NOIDA
001480200000234
YESB0000014
110532007
000014
Mr Getamber Anand, ATS Tower Plot- 16, Sector 135, Noida, GB Nagar UP. 201305
Attached











Yes
Yes
Yes
Yes
Yes
No
No
No
Yes
No


Yes
Yes
Yes
Yes
No
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. AAIALREADY BEEN OBTAINED18-09-2013
II. HARYANA STATE POLLUTION BOARDALREADY BEEN OBTAINED29-10-2016
III. FOREST (NOC)ALREADY BEEN OBTAINED27-12-2013
IV. BUILDING PLAN APPROVALALREADY BEEN OBTAINED26-05-2014
V. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED29-05-2014
VI. FIRE SCHEME APPROVAL REPORTALREADY BEEN OBTAINED27-11-2014
VII. FRESH WATERALREADY BEEN OBTAINED29-11-2013
VIII. NBWL CLEARANCEALREADY BEEN OBTAINED11-03-2014
IX. POWER LOADALREADY BEEN OBTAINED27-11-2013
X. RELEASE OF SEWAGE TREATED WATER FOR CONSTRUCTIONALREADY BEEN OBTAINED09-09-2013
XI. REQUEST LETTER OF HASTA FOR ADDITIONAL LICENSEALREADY BEEN OBTAINED08-07-2016
XII. STP UNDERTAKINGALREADY BEEN OBTAINED09-09-2013
XIII. UNDERTAKING FOR DHBVN POWER LOADALREADY BEEN OBTAINED27-11-2013








Yes


Yes


Attached







ATS GRANDSTAND PHASE-1, SECTOR -99A, VILLAGE GOPALPUR , DISTRICT - GURUGRAM, STATE HARYANA-122001
2.62
236
0
205
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
12543.23150606054.5
Cost of the apartments500085432656.32
Cost of the infrastructure113434151090.49
Others costs6409.2931012307.69


3576 Lakhs
12681.92 Lakhs
18522.9 Lakhs
16717.8 Lakhs
No
28-11-2022
27-11-2028










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES FLOORING IN LIVING, DINING & LOBBY WOODEN/ VITRIFIED TILES FLOORING INBEDROOMS VITRIFIED TILES IN KITCHEN, UTILITY & SERVANT ROOM AND CERAMIC TILES INTOILETS. BALCONIES WILL BE IN ANTI-SKID CERAMIC FLOORING
2WALL FINISHING DETAILSGLAZED TILES OF REQUIRED HEIGHT IN TOILETS & 600MM HEIGHT ABOVE KITCHEN COUNTERSLAB IN APPROPRIATE COLOUR & PAINT
3KITCHEN DETAILSALL KITCHEN COUNTERS IN PRE-POLISHED GRANITE/ MARBLE STONE, ELECTRICAL POINTS FORKITCHEN CHIMNEY & HOB, WASHING MACHINE & FRIDGE TO BE PROVIDED. KITCHEN WILL BEPROVIDED WITH MODULAR CABINETS OF APPROPRIATE FINISH
4BATHROOM FITTINGSPREMIUM SANITARY FIXTURES, PREMIUM CHROME PLATED FITTINGS
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESMAIN ENTRANCE DOORS – PLYWOOD FRAMES WITH POLISHED VENEER ON TOP. ALL INTERNALDOORS-LAMINATED PLYWOOD FRAMES . WINDOW FRAMES AND WINDOW PANELS OFALUMINIUM/ UPVC SECTIONS.
7GLASS WORKNA
8ELECTRIC FITTINGSPROVISION FOR ADEQUATE LIGHT & POWER POINTS. TELEPHONE & T.V. OUTLETS IN DRAWING,DINING AND ALL BEDROOM; MOULDED MODULAR PLASTIC SWITCHES & PROTECTIVE MCB'S
9CONDUCTING AND WIRING DETAILSALL ELECTRICAL WIRING IN CONCEALED CONDUITS
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSLIFTS TO BE PROVIDED FOR ACCESS TO ALL FLOORS FROM COMMON LOBBY
13EXTERNAL GLAZINGSREFER SR NO 13.1
13.1WINDOWS/GLAZINGSWINDOW PANELS OF SEASONED HARDWOOD/ALUMINIUM/ UPVC SECTIONS. ALL HARDWARE INPOWDER COATED ALUMINIUM. SIZE AND SECTION AS PER DESIGN OF THE ARCHITECT
14DOORSNA
14.1MAIN DOORSFLUSH DOORS - POLISHED/ENAMEL PAINTED; STAINLESS STEEL/ BRASS FINISHED HARDWAREFITTINGS FOR MAIN DOOR & ALUMINIUM POWDER COATED HARDWARE FITTING AND LOCKS OFBRANDED MAKES
14.2INTERNAL DOORSFLUSH DOORS - POLISHED/ENAMEL PAINTED
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSPROVISION FOR ADEQUATE LIGHT & POWER POINTS. TELEPHONE & T.V. OUTLETS IN DRAWING,DINING AND ALL BEDROOM; MOULDED MODULAR PLASTIC SWITCHES & PROTECTIVE MCB'S
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYPROVISION OF FTTH NETWORK
19EXTERNAL FINISHING/COLOUR SCHEMEAPPROPRIATE FINISH OF TEXTURE PAINT OF EXTERIOR GRADE WATER PROOF PAINT
20INTERNAL FINISHINGOIL BOUND DISTEMPER OF APPROPRIATE COLOUR ON INTERIOR WALLS & CEILINGS
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSPLASTER WITH OBD
1 . 3 CEILINGPLASTER WITH OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN FLOORING/VITRIFIED TILES
2 . 2 WALLSPLASTER WITH OBD
2 . 3 CEILINGPLASTER WITH OBD
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES
3 . 2 WALLSGLAZED TILES
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSPREMIUM SANITARY FIXTURES, PREMIUM CHROME PLATED FITTINGS
3 . 6 FITTING/FIXTURESPREMIUM CHROME PLATED FITTINGS
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSPLASTER WITH OBD
4 . 3 CEILINGPLASTER WITH OBD
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORCERAMIC TILES
5 . 2 WALLSGLAZED TILES
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSPREMIUM SANITARY FIXTURES, PREMIUM CHROME PLATED FITTINGS
5 . 6 FIXTURESPREMIUM CHROME PLATED FITTINGS
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSGLAZED TILES 600MM HEIGHT ABOVE KITCHEN COUNTER SLAB IN APPROPRIATE COLOUR& PAINT
6 . 3 CEILINGPLASTER WITH OBD
6 . 4 COUNTERSALL KITCHEN COUNTERS IN PRE-POLISHED GRANITE/ MARBLE STONE
6 . 5 FIXTURESELECTRICAL POINTS FOR KITCHEN CHIMNEY & HOB, KITCHEN WILL BE PROVIDED WITHMODULAR CABINETS OF APPROPRIATE FINISH
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES IN UTILITY & SERVANT ROOM
7 . 2 WALLS & CEILINGPLASTER WITH OBD
7 . 3 TOILETGLAZED TILES OF REQUIRED HEIGHT IN TOILETS & CERAMIC TILES IN TOILETS FORFLOORING
7 . 4 BALCONYBALCONIES WILL BE IN ANTI SKID CERAMIC FLOORING
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 07-09-2022 View Document
2 LC-IV 07-09-2022 ------
3 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 07-09-2022 View Document
4 ENVIRONMENT CLEARANCE 07-09-2022 ------
5 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 07-09-2022 View Document
6 DEMARCATION PLAN 07-09-2022 View Document
7 ZONING PLAN 07-09-2022 View Document
8 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 07-09-2022 View Document
9 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 07-09-2022 View Document
10 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 07-09-2022 View Document
11 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN PART 2 07-09-2022 ------
12 AAI 07-09-2022 ------
13 LOI 07-09-2022 ------
14 SUPRIMPOSED DEMARCATION OF PLAN 07-09-2022 ------
15 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 12-09-2022 View Document
16 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 12-09-2022 View Document
17 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 12-09-2022 View Document
18 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 12-09-2022 View Document