13TH FLOOR, DR. GOPAL DAS BHAWAN, 28 BARAKHAMBA ROAD, CONNAUGHT PLACE, NEW DELHI CENTRAL DELHI DL 110001 IN
01149281700
9810899381 (Number Shared by Promoter in Public)
COMPLIANCE@SIGNATUREGLOBAL.IN
https://www.signatureglobal.in/
XXXX807M
U70100DL2000PLC104787
SIGNATURE GLOBAL CITY 63A (1)
VILLAGE KADARPUR SECTOR 63
GURGAON
GURUGRAM
01149281700
9810899381 (Number Shared by Promoter in Public)
COMPLIANCE@SIGNATUREGLOBAL.IN
SANJAY KUMAR VARSHNEY
01149281700
9810899381 (Number Shared by Promoter in Public)
COMPLIANCE@SIGNATUREGLOBAL.IN
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
564881
02-05-2022
384607
YES BANK LTD.
HRERA Gurugram
2
564882
02-05-2022
144025
YES BANK LTD.
HRERA Gurugram
5.0125 (Acre)
2.64
2.47
5.0125 (Acre)
110 of 2021 dated 17.12.2021
Yes
19267.94 Lakhs
2904.85 Lakhs
8700 Lakhs
534.20 Lakhs
7128.89 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
1.234
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
0
4
PAVEMENTS
1.198
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0.469
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.06
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.11
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.501
12
ANY OTHER
0
13
AREA UNDER COMMERCIAL UNITS
0.201
Total
3.773
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
ALREADY CONNECTED
Yes
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
NA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
185.03
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
112.51
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
37.56
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
60.19
SUBMITTED TO HUDA
6
STREET LIGHTING
7.69
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
10.57
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
MAINTENACE
0
YET TO BE PREPARED
20-12-2021 (date)
05-05-2022 (date)
01-04-2022
28-02-2025
Plot Area(In Square Meter)
Number of plots in the project
0
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
88.25
52
13
Apartment/Shops/Other Buildings
71.924
80
20
Apartment/Shops/Other Buildings
54.23
16
4
Apartment/Shops/Other Buildings
723.421
57
1
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
EDC
112.52
Land Cost
2904.85
Others Cost
1972.39
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
0
0
0
Plots
0
0
0
Cost of construction
1000.00
800.00
1000.00
Others cost
428.97
435.38
480.51
External development charges
56.26
56.26
Infrastructure development charges
83.91
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Cost of construction
1000.00
800.00
1000.00
1000.00
External development charges
56.26
56.26
Others cost
489.35
389.35
496.49
353.63
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
External development charges
56.26
56.26
Cost of construction
500.00
500.00
500.00
300.00
Others cost
360.77
287.90
250.04
257.18
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Others cost
214.32
71.45
53.59
35.73
Cost of construction
300.00
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Others cost
17.86