HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1044-2022
Submission Date : 15-04-2022 04:51:40 AM
Applicant Type : Firm
Project Type: NEW


SMN REALTY LLP
FIRST FLOOR, HOUSE NO. 37, BLOCK-C, POCKET-2, SECTOR-11, ROHINI, DELHI-110085
9205596375 (Number Shared by Promoter in Public)
shrIgreencity@gmail.com
AAP4654
ADYFS4488F















SHRI GREENS CITY
VILLAGE RATHDHANA SECTOR 26 SONEPAT HARYANA
SONIPAT
SONIPAT
9205596375 (Number Shared by Promoter in Public)
shrIgreencity@gmail.com
RAVINDER KUMAR
9205596375 (Number Shared by Promoter in Public)
shrIgreencity@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
12239412-04-2022255000HDFC BANK NEW DELHIHRERA Panchkula







5.76875 (Acre)
0
0
5.76875 (Acre)
33 OF 2022 DATED 30.03.2022
Yes







2720.88 Lakhs
1581.49 Lakhs
0 Lakhs
432.66 Lakhs
706.73 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD3.162
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS1.006
4PAVEMENTS0.431
5PARKS AND PLAYGROUNDS0.460
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.577
12ANY OTHER0.007
13COMMERCIAL0.125
Total5.768




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS91.66AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM41.85AS PER PROJECT REPORT
3STORM WATER DRAINAGE33.64AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM87.95AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL51.44AS PER PROJECT REPORT
6STREET LIGHTING10.15AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS17.31AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER7.93AS PER PROJECT REPORT
15BOUNDARY WALL GATE AND GUARD ROOM90.72AS PER PROJECT REPORT


01-04-2022 (date)
NA (date)
01-05-2022
29-03-2027
Plot Area(In Square Meter)Number of plots in the project
141.7316
135.9720
106.2016
116.905
117.589
137.7614
115.457
91.141
1471
98.086
1001
114.887
0.1251


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.338.338.33
Water Supply System3.803.803.80
Sewerage treatment & garbage disposal4.684.684.68
Electricity Supply System8.008.008.00
Storm Water Drainage3.063.063.06
Parks and Playgrounds1.571.571.57
Clubhouse/community centres000
Shopping area000
Other0.720.720.72
Boundary Wall Gate and Guard Room8.258.258.25
STREET LIGHTING0.920.920.92

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.338.338.338.33
Water Supply System3.803.803.803.80
Sewerage treatment & garbage disposal4.684.684.684.68
Electricity Supply System8.008.008.008.00
Storm Water Drainage3.063.063.063.06
Parks and Playgrounds1.571.571.571.57
Clubhouse/community centres0000
Shopping area0000
Other0.720.720.720.72
STREET LIGHTING0.920.920.920.92
Boundary Wall Gate and Guard Room8.258.258.258.25

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.338.338.338.33
Water Supply System3.803.803.803.80
Sewerage treatment & garbage disposal4.684.684.684.68
Electricity Supply System8.008.008.008.00
Storm Water Drainage3.063.063.063.06
Parks and Playgrounds1.571.571.571.57
Clubhouse/community centres0000
Shopping area0000
Other0.720.720.720.72
STREET LIGHTING0.920.920.920.92
Boundary Wall Gate and Guard Room8.258.258.258.25












Yes
No
HDFC BANK, VIKAS PURI, NEW DELHI
59209999401111
HDFC0001408
110049036
110240167
RAVINDER KUMAR R/O 6 51 CENTRAL MARKET PUNJABI BAGH PUNJABI BAGH WEST DELHI MOBILE NO. 9205596375











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
Yes
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED30-03-2022
II. LAYOUT PLANALREADY BEEN OBTAINED01-04-2022








Yes


Yes


FULL AGREEMENT













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND09-04-2022 View Document
2IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN09-04-2022 View Document
3A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS09-04-2022 View Document
4IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN09-04-2022 View Document
5DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD09-04-2022 View Document
6DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.14-04-2022 View Document
7NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT14-04-2022 View Document
8CASH FLOW STATEMENT OF THE PROPOSED PROJECT14-04-2022 View Document
9ZONING PLAN14-04-2022 View Document
10DEMARCATION PLAN14-04-2022 View Document