HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1037-2022
Submission Date : 02-12-2022 01:01:56 PM
Applicant Type : Company
Project Type: NEW




PARYAPT INFRASTRUCTUREPRIVATE LIMITED
6TH FLOOR, M3M TEE POINT, NORTH BLOCK, SECTOR- 65, GURUGRAM GURGAON HR 122101 IN
01244732000
9711348349 (Number Shared by Promoter in Public)
paryaptinfrastructure@gmail.com
https://paryaptinfrastructure.com
XXXX951F
U70109HR2020PTC090042
 
 


 
 


 
 


 
 







M3M PARAGON57
BLOCK A SUSHANT LOK- III, SECTOR-57 GURUGRAM MANESAR URBAN COMPLEX
WAZIRABAD ST
GURUGRAM
01244732000
9711348349 (Number Shared by Promoter in Public)
paryaptinfrastructure@gmail.com
PARDEEP AGARWAL
01244732000
9711348349 (Number Shared by Promoter in Public)
paryaptinfrastructure@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150068129-11-2022470000ICICI BANKHRERA Gurugram
250068229-11-20223453800ICICI BANKHRERA Gurugram







3.16 (Acre)
3.67
3.66
3.16 (Acre)
10 to 16 of 1996 dated 16.02.1996, 3 to 5 and 8 of 1999 dated 4.01.1999, 2 to 4 of 2000 dated 6.02.2000, 102 to 114 of 2004 dated 27.07.2004
No
Address     NA
Annexure-B- THIRD PARTY RIGHT HOLDER VIDE CONVEYANCE DEED (VASIKA NO 7936) DATED 13-09-2021
NA
Yes
CONVEYANCE DEED ANNEXED IN FOLDER-A
No
No
Yes







56100.76 Lakhs
14071.43 Lakhs
23703.48 Lakhs
2807.80 Lakhs
15518.05 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 1.8923
3CONSTRUCTION OF ROADS 0.7631
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0.5046
Total3.16




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS GMDAYes
WATER SUPPLY GMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSAL GMDAYes
STORM WATER DRAINAGE GMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS331.96AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM104.53AS PER PROJECT REPORT
3STORM WATER DRAINAGE20.50AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM200.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL45.00AS PER PROJECT REPORT
6STREET LIGHTING15.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING172.00AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15CONSTRUCTION OF CIRCULATION ROAD AND BOUNDARY WALL9.46AS PER PROJECT REPORT
16ELECTRICAL SUB STATION287.30AS PER PROJECT REPORT
17RAIN WATER HARVESTING26.00AS PER PROJECT REPORT
18ELECTRIFICATION TO SITE1434.81AS PER PROJECT REPORT
19STP96.00AS PER PROJECT REPORT
20PARKING 10.25AS PER PROJECT REPORT
21WATER TANK55.00AS PER PROJECT REPORT


01-12-2022 (date)
01-12-2022 (date)
01-12-2022
31-08-2026
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings31415.288580





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
EDC IDC403.60
Land14071.43
Others1017.60

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments436.7
Shops0
Plots0

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments842.22183.62266.62233.8
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2440.62987.93466.33146.7
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1906.1909.4650.2233.3
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3.323.3213.28
Water Supply System02.094.18
Sewerage treatment & garbage disposal00.901.80
Electricity Supply System000
Storm Water Drainage00.210.82
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
STP04.80
Parking0.200.41
Security and Firefighting services3.446.88
Underground tank1.659.35
Rain water harvesting0.784.42
Electrical sub station014.37
Circulation of roads and Boundary Wall0.470.47
Electricity upto site71.7471.74
Electrification4.008.0

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements29.8833.2033.2049.79
Water Supply System9.4110.4513.5915.68
Sewerage treatment & garbage disposal4.054.505.856.75
Electricity Supply System0000
Storm Water Drainage1.852.052.053.08
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and Firefighting services15.4817.2022.3625.80
Rain water harvesting1.302.602.602.60
Electrical sub station14.3728.7328.7328.73
Circulation of roads and Boundary Wall0.950.950.950.95
STP4.809.609.609.60
Underground tank2.755.505.505.50
Street Light00.150.753.00
Parking0.921.021.331.54
Electricity upto site143.48143.48143.48143.48
Electrification18.0020.0026.0030.00

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements49.7949.7936.5229.88
Water Supply System15.6813.5910.459.41
Sewerage treatment & garbage disposal6.755.854.504.05
Electricity Supply System0000
Storm Water Drainage3.283.082.261.85
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrification30.0026.0020.0018.00
Parking1.541.331.020.92
Electricity to site286.96215.22143.4871.74
Security and Firefighting services25.8022.3617.2015.48
STP9.6019.2019.209.60
Underground tank5.508.255.505.50
Rain water harvesting2.603.902.602.60
Electrical sub station28.7357.4657.4628.73
Street Light3.302.852.702.25
Circulation of roads and Boundary Wall1.891.420.950.47












Yes
No
ICICI BANK LIMITED AND BRANCH SUNCITY, SECTOR-54, GURGAON-122002
777705991122
ICIC0000399
110229060
000399
1) Mr. Vyom Shakti Nigam-D3/103 Paras city E3 Arera Colony Bhopal M.P. 462016 2) MS. Amarjot Kaur Sahni-3/66 Subhash Nagar West Delhi 110027 3) Ms. Shubhra Bakshi- House No 10/6, DLF Phase-1, Sikanderpur Ghosi, Gurgaon, Haryana- 122002 4) Ms. Surbhi- Flat No-3-905, 9th floor, Sector-103, grandiva, Daultabad, Gurgaon, Haryana-122006 5) Mr. Vidya Sagar-3G-208, Faridabad, NIT Faridabad, Haryana- 121001 6) Mr. Pratap Singh-10A Pocket 2 Mayur Vihar East Delhi 110096 7) Mr. Pradeep Kumar Katiyar- 357, Bakhothi Purwa, Thana Bilaur, Kanpur- 209202, Uttar Pradesh
Yes











Yes
No
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LOIALREADY BEEN OBTAINED20-12-2021
II. NOC FOR HEIGHT CLEARANCEALREADY BEEN OBTAINED29-11-2021
III. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED25-03-2022
IV. BUILDING PLAN APPROVALALREADY BEEN OBTAINED01-12-2022








Yes


Yes


As per HARERA Norms







M3M ATRIUM57
1.4250
274
0
173
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
7683.620954.91
Cost of the apartments4136.070743.21
Cost of the infrastructure816.1400
Others costs2731.410211.7


7190.712 Lakhs
14766.59 Lakhs
0 Lakhs
0 Lakhs
No
15-05-2025
15-05-2025










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEBARE R.C.C SLAB, STUDIO- TILE / STONE OR AS APPROVED
2WALL FINISHING DETAILSLEVEL PLAST / WHITE PUTTY ,STUDIO - OBD / EMULSION OR AS APPROVED
3KITCHEN DETAILSSTUDIO- OBD / EMULSION OR AS APPROVED
4BATHROOM FITTINGSN.A.
5WOOD WORK ETCN.A.
6DOORS AND WINDOS FRAMESALUMINIUM FRAME
7GLASS WORKGLASS WITH ALUMINIUM FRAME
8ELECTRIC FITTINGSLED TYPE FITTING
9CONDUCTING AND WIRING DETAILSPVC / MS CONDUIT WITH FR / FRLS PVC WIRES
10CUPBOARD DETAILSN.A.
11WATER STORAGEUGT (FIRE, RAW & DOMESTIC)
12LIFT DETAILSPASSENGER LIFTS AND SERVICE LIFTS
13EXTERNAL GLAZINGSEXTERNAL FAÇADE SGU / ACP / EXTERNAL PAINT OR AS APPROVED, STUDIO- EXTERNAL FAÇADE SGU
13.1WINDOWS/GLAZINGSSTUDIO-SGU / DGU WITH ALUMINIUM FRAME OR AS PER DESIGN
14DOORSSTUDIO- LAMINATED / VENEER / POLISHED FLUSH DOOR SHUTTER OR AS APPROVED ,STUDIO-LAMINATED / VENEER / POLISHED FLUSH DOOR SHUTTER OR AS APPROVED
14.1MAIN DOORSALUMINIUM AND GLASS FOR RETAIL OR AS APPROVED ,STUDIO-LAMINATED / VENEER / POLISHED FLUSH DOOR SHUTTER OR AS APPROVED
14.2INTERNAL DOORSALUMINIUM AND GLASS FOR RETAIL / LAMINATED DOORS OR AS APPROVED ,STUDIO-LAMINATED / VENEER / POLISHED FLUSH DOOR SHUTTER OR AS APPROVED
15AIR CONDITIONINGPROVISION IN RETAIL & COMMON AREA NON A/C
16ELECTRICAL FITTINGSLED TYPE FITTINGS IN COMMON AREA ONLY
17CNG PIPE LINEF&B / FOOD COURT
18PROVISION OF WIFI AND BROADBAND FACILITYBROADBAND PROVIDED OR AS APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEME"GLASS WITH STONE OR ALUMINUM CLADDING"
20INTERNAL FINISHINGGYPSUM PLASTER & PAINT OR AS APPROVED
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORSTUDIO -TILE / STONE OR AS APPROVED
1 . 2 WALLSSTUDIO-OBD / EMULSION OR AS APPROVED
1 . 3 CEILINGSTUDIO- OBD / EMULSION OR AS APPROVED
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORSTUDIO- TILE / LAMINATED WOODEN FLOORING OR AS APPROVED
2 . 2 WALLSSTUDIO-OBD / EMULSION OR AS APPROVED
2 . 3 CEILINGSTUDIO-OBD / EMULSION OR AS APPROVED
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOORSTUDIO-TILE / STONE OR AS APPROVED
3 . 2 WALLSSTUDIO-TILE / STONE / OBD / EMULSION OR AS APPROVED
3 . 3 CEILINGSTUDIO- FALSE CEILING / OBD / EMULSION OR AS APPROVED
3 . 4 COUNTERSSTUDIO-STONE OR AS APPROVED
3 . 5 SANITARY WARE/CP FITTINGSN.A.
3 . 6 FITTING/FIXTURESN.A.
4 . BED ROOMS
4 . 1 FLOORN.A.
4 . 2 WALLSN.A.
4 . 3 CEILINGN.A.
4 . 4 WARDROBESN.A.
5 . TOILET
5 . 1 FLOORN.A.
5 . 2 WALLSN.A.
5 . 3 CEILINGN.A.
5 . 4 COUNTERSN.A.
5 . 5 SANITARY WARE/CP FITTINGSN.A.
5 . 6 FIXTURESN.A.
6 . KITCHEN
6 . 1 FLOORN.A.
6 . 2 WALLSN.A.
6 . 3 CEILINGN.A.
6 . 4 COUNTERSN.A.
6 . 5 FIXTURESN.A.
6 . 6 KITCHEN APPLIANCESN.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN.A.
7 . 2 WALLS & CEILINGN.A.
7 . 3 TOILETN.A.
7 . 4 BALCONYN.A.
8 . SIT-OUTS
8 . 1 FLOORN.A.
8 . 2 WALLS & CEILINGN.A.
8 . 3 RAILINGSN.A.
8 . 4 FIXTURESN.A.












Sr. No.Document DescriptionDate of Document UploadView Document
1 FOURTH FLOOR PLAN 02-12-2022 ------
2 ELEVATION 1 02-12-2022 ------
3 ASSURANCE STROM WATER 24-11-2022 ------
4 BR III 01-12-2022 ------
5 ENVIRONMENT CLEARANCE 24-11-2022 ------
6 1ST BASEMENT PLAN 02-12-2022 ------
7 THIRD FLOOR PLAN 02-12-2022 ------
8 LANDSCAPE PLAN 01-12-2022 ------
9 ASSURANCE CONSTRUCTION WATER 24-11-2022 ------
10 SECTION PLAN 02-12-2022 ------
11 ZONING PLAN 01-12-2022 View Document
12 ASSURANCE DRINKING WATER 02-12-2022 ------
13 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 02-12-2022 View Document
14 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 01-12-2022 View Document
15 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 01-12-2022 View Document
16 SECOND FLOOR PLAN 02-12-2022 ------
17 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 28-11-2022 View Document
18 AAI NOC 24-11-2022 ------
19 6TH, 8TH, 10TH , 11TH & 13TH FLOOR PLAN 02-12-2022 ------
20 PARKING PLAN 02-12-2022 ------
21 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 01-12-2022 View Document
22 FIFTH FLOOR PLAN 02-12-2022 ------
23 ELEVATION 3 02-12-2022 ------
24 FIRST FLOOR PLAN 02-12-2022 ------
25 ELEVATION 2 02-12-2022 ------
26 GROUND FLOOR PLAN 02-12-2022 ------
27 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 02-12-2022 View Document
28 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 02-12-2022 View Document
29 SITE PLAN SERVICES 02-12-2022 ------
30 7TH ,9TH & 12TH FLOOR PLAN 02-12-2022 ------
31 ELECTRICAL & STREET LIGHT PLAN 07-12-2022 ------
32 SEWER LAYOUT PLAN 07-12-2022 ------
33 ROAD LAYOUT PLAN 07-12-2022 ------
34 FIRE PLAN -1 07-12-2022 ------
35 FIRE PLAN -2 07-12-2022 ------
36 1ST BASEMENT STRUCTURE PLAN 07-12-2022 ------
37 FIRE FIGHTING PLAN 07-12-2022 ------
38 GROUND FLOOR STRUCTURE PLAN 07-12-2022 ------
39 SECOND FLOOR STRUCTURE PLAN 07-12-2022 ------
40 STROM WATER PLAN 07-12-2022 ------
41 TYPICAL FLOOR STRUCTURE PLAN 07-12-2022 ------
42 WATER SUPPLY PLAN 07-12-2022 ------
43 PERT CHART 17-12-2022 ------
44 FIRST FLOOR- FIRE PLAN 5 15-12-2022 ------
45 SITE PLAN- FIRE PLAN 1 15-12-2022 ------
46 1ST BASEMENT - FIRE PLAN 2 15-12-2022 ------
47 2ND BASEMENT- FIRE PLAN 4 15-12-2022 ------
48 2ND FLOOR- FIRE PLAN 3 15-12-2022 ------
49 5TH FLOOR- FIRE PLAN 6 15-12-2022 ------
50 4TH FLOOR- FIRE PLAN 7 15-12-2022 ------
51 GROUND FLOOR - FIRE PLAN 8 15-12-2022 ------
52 ELECTRICAL LOAD ASSURANCE 16-12-2022 ------
53 ASSURANCE SEWAGE WATER 17-12-2022 ------