HRERA GurugramTemp Project Id : RERA-GRG-PROJ-891-2021
Submission Date : 27-07-2021 04:51:02 PM
Applicant Type : Company
Project Type: NEW




DLF UTILITIES LIMITED
3RD FLOOR, SHOPPING MALL, ARJUN MARG, DLF CITY PHASE I, GURUGRAM 122002
1244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
https://www.dlf.in/
XXXX199A
U01300HR1989PLC030646
 
 


 
 


 
 


 
 


 
 







INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
DLF GARDENCITY, SECTOR 91/92, GURUGRAM, HARYANA
HARSARU ST
GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
YUDHVEER SINGH
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
151676219-07-2021362050ICICI BANKHRERA Gurugram







1.096 (Acre)
2.4 (FAR Factor) / 2.63 Acres (FAR Area)
2.63
1.096 (Acre)
Licence No. 59 of 2011 dt. 28.06.2011 for 101.218 acres, for which Part Completion Certificate has been granted on 02.07.2014. Licence No. 14 of 2012 dt. 27.02.2012 for 62.956 acres. Part Completion Certificate for an area of 60.14 acres has been granted on 18.03.2016. Licence No. 13 of 2019 dt. 06.02.2019 for 16.25 acres.
Yes







7459.99 Lakhs
1326.63 Lakhs
4535.14 Lakhs
0 Lakhs
1598.22 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS4436.9
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total4436.9




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY EXISTINGNo
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM0AS PER PROJECT REPORT
3STORM WATER DRAINAGE0AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL0AS PER PROJECT REPORT
6STREET LIGHTING0AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT


NA (date)
NA (date)
20-12-2021
19-11-2024
Plot Area(In Square Meter)Number of plots in the project
317.931
328.321
343.758
350.111
270.531
420.001


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings154.28141
Apartment/Shops/Other Buildings164.39841
Apartment/Shops/Other Buildings167.687328
Apartment/Shops/Other Buildings175.85441
Apartment/Shops/Other Buildings130.13741
Apartment/Shops/Other Buildings206.40741





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments1088.29
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments682.83303.97
Shops00
Plots00

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments185.94226.76314.06407.03
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments453.51453.51453.51453.51
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments633.79633.79226.760
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments942.74
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2025)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
ICICI / 9A- PHELPS BUILDING, CONNAUGHT PLACE, NEW DELHI-110001
000705051929
ICIC0000007
110229002
0007
Mr. Vivek Anand (B-1102, Palm Spring, Golf Course Road,Sector 54, Gurgaon) Mr. Puneet Rakheja (386, Sector-31,Faridabad) Mr. Saurabh Kumar Gupta (1116 Vikaskunj,Vikaspuri, New Delhi) Mr. Pankaj Jain (C 701, Apex ArcadiaValley, Sector 3, Vaishali, Gaziabad) Mr. Ashok Nanda (NewDelhi) Ms. Sandhya Singla (Neelachal Apts, Plot No. 3,Dwarka, New Delhi) Mr..Rajeev Singhal (New Delhi)
No Default on the Project











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE 59 OF 2011 APPROVAL ALREADY BEEN OBTAINED26-06-2011
II. LICENSE 14 OF 2012 APPROVALALREADY BEEN OBTAINED27-02-2012
III. LICENSE 13 OF 2019 APPROVALALREADY BEEN OBTAINED06-02-2019
IV. ENVIRONMENT CLEARANCE (SEIAA(126)/HR/2021/192) FOR PLOTTED DEVELOPMENTALREADY BEEN OBTAINED18-02-2021
V. SERVICE PLAN ESTIMATES APPROVAL (MEMO NO. LC-2523-K/ASSTT.(AK) /2019/2574)ALREADY BEEN OBTAINED27-01-2020
VI. FOREST NOC (XRR-CAU-LW82)ALREADY BEEN OBTAINED18-10-2019
VII. NATURAL CONSERVATION ZONE NOC (22/AM0B0)ALREADY BEEN OBTAINED23-06-2020
VIII. TREE CUTTING PERMISSION/ NOC (XU5-RRE-V3XX)ALREADY BEEN OBTAINED10-03-2021
IX. BUILDING PLAN / SITE PLAN APPROVAL (FOR G19-12)APPLIED FOR BUT YET TO RECEIVE08-07-2021
X. BUILDING PLAN / SITE PLAN APPROVAL (FOR G19-14)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XI. BUILDING PLAN / SITE PLAN APPROVAL (FOR G21-18)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XII. BUILDING PLAN / SITE PLAN APPROVAL (FOR G21-19)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XIII. BUILDING PLAN / SITE PLAN APPROVAL (FOR G21-16)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XIV. BUILDING PLAN / SITE PLAN APPROVAL (FOR G16-21)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XV. BUILDING PLAN / SITE PLAN APPROVAL (FOR G8-8)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XVI. BUILDING PLAN / SITE PLAN APPROVAL (FOR SA-1G)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XVII. BUILDING PLAN / SITE PLAN APPROVAL (FOR B12-5)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XVIII. BUILDING PLAN / SITE PLAN APPROVAL (FOR G17-19)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XIX. BUILDING PLAN / SITE PLAN APPROVAL (FOR NCA-12)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XX. BUILDING PLAN / SITE PLAN APPROVAL (FOR NCA-14)APPLIED FOR BUT YET TO RECEIVE08-07-2021
XXI. BUILDING PLAN / SITE PLAN APPROVAL (FOR NCA-15)APPLIED FOR BUT YET TO RECEIVE08-07-2021








Yes


Yes


As per RERA Act







INDEPENDENT FLOORS AT GARDENCITY SECTOR 91/92
0.969
72
18
72
18
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4847.045126.00415.00
Cost of the apartments4112.794414.00198.00
Cost of the infrastructure000
Others costs1603.931582.00333.00


751.00 Lakhs
7943.46 Lakhs
0 Lakhs
30.37 Lakhs
No
20-06-2024
20-06-2024




SIRIS ESTATE, DLF CITY PHASE - III, SECTOR 24, GURUGRAM, HARYANA
1.243
48
12
48
12
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
5343.836214.751032.38
Cost of the apartments3941.65084.66615.08
Cost of the infrastructure000
Others costs7792.888100.002025.74


2886.43 Lakhs
14329.43 Lakhs
0 Lakhs
580.54 Lakhs
No
31-10-2024
31-10-2024










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEIPS FLOORING / TILES / GRANITE
2WALL FINISHING DETAILSWHITE WASH / OBD
3KITCHEN DETAILSWHITE WASH / OBD
4BATHROOM FITTINGSN.A.
5WOOD WORK ETCNIL
6DOORS AND WINDOS FRAMESMS / AL
7GLASS WORKPLAIN GLASS
8ELECTRIC FITTINGSMODULAR FITTINGS
9CONDUCTING AND WIRING DETAILSPVC CONDUITS, FRLS WIRING
10CUPBOARD DETAILSNIL
11WATER STORAGEOHT WATER TANKS
12LIFT DETAILSBRANDED MAKE
13EXTERNAL GLAZINGSSINGLE GLASS UNIT WITH CLEAR GLASS UPVC/AL FRAMES AND SHUTTERS IN HABITABLE ROOMS. CLEAR/FROSTED GLASS IN TOILETS
13.1WINDOWS/GLAZINGSSINGLE GLASS UNIT WITH CLEAR GLASS UPVC/AL FRAMES AND SHUTTERS IN HABITABLE ROOMS. CLEAR/FROSTED GLASS IN TOILETS
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGLIVING, DINING & BEDROOMS
16ELECTRICAL FITTINGSMODULAR FITTING (AS PER RAJAN)
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYNIL
19EXTERNAL FINISHING/COLOUR SCHEMEWEATHER SHIELD PAINT ON EXTERNAL SURFACES, OBD IN STILTS.
20INTERNAL FINISHINGAS PER STANDARDS
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORIMPORTED MARBLE
1 . 2 WALLSACRYLIC EMULSION / OBD
1 . 3 CEILINGACRYLIC EMULSION / OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN
2 . 2 WALLSACRYLIC EMULSION / OBD
2 . 3 CEILINGACRYLIC EMULSION / OBD
2 . 4 MODULAR WARDROBESNIL
3 . MASTER TOILET
3 . 1 FLOORANTI-SKID TILES
3 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSION PAINT & MIRROR, PAINT
3 . 3 CEILINGACRYLIC EMULSION PAINT / OBD
3 . 4 COUNTERSGRANITE / SYNTHETIC STONE
3 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, FLOOR MOUNTED / WALL-HUNG WC
3 . 6 FITTING/FIXTURESEXHAUST FAN, TOWEL RAIL / RING,
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSACRYLIC EMULSION PAINT / OBD
4 . 3 CEILINGACRYLIC EMULSION PAINT / OBD
4 . 4 WARDROBESNIL
5 . TOILET
5 . 1 FLOORIPS FLOORING / TILES
5 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSION PAINT & MIRROR, PAINT
5 . 3 CEILINGWHITEWASH / OBD
5 . 4 COUNTERSGRANITE / SYNTHETIC STONE
5 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, FLOOR MOUNTED / WALL-HUNG WC
5 . 6 FIXTURESPVC FIXTURES, GEYSER
6 . KITCHEN
6 . 1 FLOORANTI-SKID TILES
6 . 2 WALLSTILES UP-TO 2’ ABOVE COUNTER & OBD EMULSION PAINT IN BALANCE AREA
6 . 3 CEILINGOBD / ACRYLIC EMULSION PAINT
6 . 4 COUNTERSGRANITE /SYNTHETIC STONE
6 . 5 FIXTURESCP FITTINGS, SS SINK, EXHAUST FAN
6 . 6 KITCHEN APPLIANCESNIL
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORIPS / TILES
7 . 2 WALLS & CEILINGWHITEWASH
7 . 3 TOILETCERAMIC TILE FLOORING & CLADDING, CONVENTIONAL CP FITTINGS, CHINAWARE
7 . 4 BALCONYNIL
8 . SIT-OUTS
8 . 1 FLOORIPS / TILES
8 . 2 WALLS & CEILINGOBD
8 . 3 RAILINGSMS RAILINGS
8 . 4 FIXTURESN.A.












Sr. No.Document DescriptionDate of Document UploadView Document
1DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD19-07-2021 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN19-07-2021 View Document
3ZONING PLAN19-07-2021 View Document
4IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN19-07-2021 View Document
5DEMARCATION PLAN20-07-2021 View Document
6COPY OF LICENSE ALONG WITH SCHEDULE OF LAND20-07-2021 View Document
7IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN26-07-2021 View Document
8CASH FLOW STATEMENT OF THE PROPOSED PROJECT27-07-2021 View Document
9CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT27-07-2021 View Document
10NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT27-07-2021 View Document
11DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.27-07-2021 View Document
12A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS27-07-2021 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 OC uploaded 08-08-2024 View Document