9910050495 (Number Shared by Promoter in Public)
sudhir.jain@ril.com
http://www.modeleconomictownship.com
XXXX037Q
U70109HR2006PLC036416
MET CITY
POCKET-L, SECTOR-8, YAKUBPUR & SONDHI, JHAJJAR
BADLI
JHAJJAR
9999898710 (Number Shared by Promoter in Public)
sudhir.jain@ril.com
RAKESH SINHA
9999898710 (Number Shared by Promoter in Public)
rakesh.sinha@ril.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
909959
13-07-2021
1678975
HDFC BANK
HRERA Panchkula
79.756 (Acre)
NA
0
1016.1 (Acre)
06 OF 2012,16 OF 2018, 129 OF 2019 and 11 OF 2021
Yes
15964.95 Lakhs
7271.94 Lakhs
0 Lakhs
8476.00 Lakhs
217.01 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
32.762
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
33.904
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
3.660
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.470
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.730
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
COMMUNITY
2.000
14
PU SITE
1.250
15
UNDETERMINED
4.980
Total
79.756
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
PWD
Yes
WATER SUPPLY
METL
Yes
ELECTRICITY
UHBVN
Yes
SEWAGE DISPOSAL
IRRIGATION DEPARTMENT
No
STORM WATER DRAINAGE
IRRIGATION DEPARTMENT FOR DISPOSAL IN DRAIN NO 08
No
LAYOUT PLAN
DTCP, HARYANA
Yes
LICENSE FOR PROJECT
DTCP, HARYANA
Yes
ZONING PLAN
DTCP, HARYANA
No
SERVICE PLAN ESTIMATE
DTCP, HARYANA
No
ENVIRONMENTAL CLEARANCE
MOEF
Yes
CTE PERMISSION
HARYANA STATE POLLUTION CONTROL BOARD
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
2220.79
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
689.4
YET TO BE PREPARED
3
STORM WATER DRAINAGE
1068.19
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
2969.36
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
490.22
YET TO BE PREPARED
6
STREET LIGHTING
182.74
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
HORTICULTURE
211.16
YET TO BE PREPARED
16
CONSULTANCY FEE ETC
644.14
YET TO BE PREPARED
12-03-2021 (date)
NA (date)
01-07-2021
30-06-2026
Plot Area(In Square Meter)
Number of plots in the project
150.000
143
140.000
20
130.032
102
120.000
6
109.480
402
98.000
38
84.150
91
77.500
4
3723.108
1
8093.712
1
8093.712
1
2023.428
1
5058.570
1
11654.945
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
250.62
Sewerage treatment & garbage disposal
0
Electricity Supply System
117.7
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
236
236
118
Water Supply System
29
29
29
Sewerage treatment & garbage disposal
40
40
40
Electricity Supply System
0
0
240
Storm Water Drainage
70
70
65
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Horticulture
0
Consultancy fee and Gate complex and Community Centres etc
42
Street Lighting
0
11.8
Consultancy fee Gate complex and Community Centres etc
42
42
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
100
100
100
100
Water Supply System
29
29
29
29
Sewerage treatment & garbage disposal
40
40
40
23.6
Electricity Supply System
240
240
240
190
Storm Water Drainage
65
65
65
65
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
1
0
0
0
Other
0
0
0
0
Consultancy fee Gate complex and Community Centres etc
42
42
42
42
Street lighting
11.8
Street Lighting
11.8
11.8
11.8
Horticulture
11.8
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
100
100
100
100
Water Supply System
60
40
40
40
Sewerage treatment & garbage disposal
24
24
24
24
Electricity Supply System
165
165
137.5
137.5
Storm Water Drainage
65
65
65
65
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Lighting
11.8
11.8
11.8
11.8
Consultancy fee Gate complex and Community Centres etc
42
42
42
42
Horticulture
11.8
11.8
11.8
11.8
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
150
150
150
Water Supply System
20
20
10
Sewerage treatment & garbage disposal
24
40
40
Electricity Supply System
137.5
137.5
147.5
Storm Water Drainage
65
65
65
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Street Lighting
11.8
11.8
11.8
Horticulture
11.8
23.6
23.6
Consultancy fee Gate complex and Community Centres etc
42
42
42
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Horticulture
22
Street Lighting
0
Consultancy fee Gate complex and Community Centres etc
0
Yes
No
HDFC BANK LTD. A-12THE SHOPPING MALL,DLF QUTUB ENCLAVE, GURGAON-122002
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT