Sr. No. | Name of the facility | Estimated cost (In Lakhs)(Within the project area only) | Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C) |
1 | INTERNAL ROADS AND PAVEMENTS | 285.10 | SUBMITTED TO TOWN & COUNTRY PLANNING |
2 | WATER SUPPLY SYSTEM | 94.53 | SUBMITTED TO TOWN & COUNTRY PLANNING |
3 | STORM WATER DRAINAGE | 73.36 | SUBMITTED TO TOWN & COUNTRY PLANNING |
4 | ELECTRICITY SUPPLY SYSTEM | 250.00 | SUBMITTED TO TOWN & COUNTRY PLANNING |
5 | SEWAGE TREATMENT & GARBAGE DISPOSAL | 97.61 | SUBMITTED TO TOWN & COUNTRY PLANNING |
6 | STREET LIGHTING | 34.58 | SUBMITTED TO TOWN & COUNTRY PLANNING |
7 | SECURITY AND FIRE FIGHTING | 0 | AS PER PROJECT REPORT |
8 | PLAYGROUNDS AND PARKS | 21.82 | SUBMITTED TO TOWN & COUNTRY PLANNING |
9 | CLUB HOUSE/COMMUNITY CENTRE | 0 | AS PER PROJECT REPORT |
10 | SHOPPING AREA | 0 | AS PER PROJECT REPORT |
11 | RENEWABLE ENERGY SYSTEM | 0 | AS PER PROJECT REPORT |
12 | SCHOOL | 0 | AS PER PROJECT REPORT |
13 | HOSPITAL/DISPENSARY | 0 | AS PER PROJECT REPORT |
14 | ANY OTHER | 0 | YET TO BE PREPARED |
15 | OTHER COST | 317 | SUBMITTED TO TOWN & COUNTRY PLANNING |