HRERA GurugramTemp Project Id : RERA-GRG-PROJ-710-2020
Submission Date : 02-04-2021 10:37:08 AM
Applicant Type : Company
Project Type: ONGOING




HERITAGE MAX REALTECH PVT. LTD.
K1-GREEN PARK MAIN , NEW DELHI-10016
01242803000
9810030178 (Number Shared by Promoter in Public)
sanjay.rastogi@conscient.in
https://www.elevate.in/
XXXX172E
U70200DL2015PTC286008
 
 


 
 


 
 


 
 


 
 







ELEVATE (PHASE II)
VILLAGE BEHRAMPUR, SECTOR-59, GURUGRAM
WAZIRABAD ST
GURUGRAM
01242803000
9810030178 (Number Shared by Promoter in Public)
sanjay.rastogi@conscient.in
AVINASH NAGPAL
01242803000
9999014121 (Number Shared by Promoter in Public)
avinash.nagpal@conscient.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11860123-02-2021720500HDFC BANK LIMITEDHRERA Gurugram
21860323-02-2021406500HDFC BANK LIMITEDHRERA Gurugram
31860223-02-2021360250HDFC BANK LIMITEDHRERA Gurugram







2.96875 (Acre)
1.87
1.87
8.91875 (Acre)
1. 16 of 2008 2. 28 of 2008 3. 44 of 2011
No
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, NEW DELHI -110017
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, NEW DELHI -110017
Address     305, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     304, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, NEW DELHI -110017
Address     304, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, NEW DELHI-110017
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, NEW DELHI-110017
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA COMMERCIAL COMPLEX, NEW DELHI-110015
Address     C-4, 1ST FLOOR, MALVIYA NAGAR, NEW DELHI-110017
Annexure-B- "COLLABORATOR/ DEVELOPER" COLLABORATION AGREEMENT AND POA ARE ANNEXED
AFTER GRANT OF LICENSE
Yes
COLLABORATION AGREEMENT DATED MARCH 2, 2016 DULY REGISTERED WITH SUB REGISTRAR SOHNA VIDE REGN. NO. 3687 DATED MARCH 2, 2016.
No
Yes
Yes







54349.90 Lakhs
18284.73 Lakhs
26068.79 Lakhs
259.99 Lakhs
9736.39 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.60
3CONSTRUCTION OF ROADS0.22
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.46
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER1.689
Total2.969




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNANo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS68.02SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM99.93SUBMITTED TO HUDA
3STORM WATER DRAINAGE27.2SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL51.19SUBMITTED TO HUDA
6STREET LIGHTING9.94SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS3.71SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15RAIN WATER HARVESTING0SUBMITTED TO HUDA
16ELECTRICAL SUB STATION0SUBMITTED TO HUDA


25-04-2019 (date)
25-04-2019 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK (S)107.6831001
2APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK (L)118.3364001
3APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK + STUDY113.0333001
4APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK (S)107.6831001
5APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK (L)118.3329001
6APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK + STUDY133.0360001






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
3 BHK (S)0PROJECTED DATE OF COMPLETION- JANURAY 2025
3 BHK (L)0PROJECTED DATE OF COMPLETION- JANURAY 2025
3 BHK + STUDY0PROJECTED DATE OF COMPLETION- JANURAY 2025
3 BHK (S)0PROJECTED DATE OF COMPLETION- JANURAY 2025
3 BHK (L)0PROJECTED DATE OF COMPLETION- JANURAY 2025
3 BHK + STUDY0PROJECTED DATE OF COMPLETION- JANURAY 2025


01-04-2021
31-01-2025
31-01-2025
01-04-2021
0
31-01-2025
ATTACHED IN CX


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-04-2021
0
31-01-2025


381
0
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
Land cost expenditure including EDC and IDC payment to owners17123.85

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments150925.65783.37982.55
Shops0000
Plots0000
Other Cost408.50297.50373.14
Land Cost212.91370.460
IDW000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1440.451930.092543.213321.04
Shops0000
Plots0000
IDW0000
Other Cost547.04732.99965.831261.22
Land Cost540.7936.72

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3547.583380.131876.03375.06
Shops0094.4094.40
Plots0000
Other Cost1347.261283.66748.31178.28
IDW0053.00105.00

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2176.091709.64401.270
Shops136.32107.1094.400
Plots0000
IDW60.0033.008.990
Other Cost796.34608.10188.240

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00014
Water Supply System003050
Sewerage treatment & garbage disposal001526.19
Electricity Supply System0000
Storm Water Drainage00814.1
Parks and Playgrounds0001
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lighting0002

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements202770
Water Supply System20000
Sewerage treatment & garbage disposal10000
Electricity Supply System0000
Storm Water Drainage5000
Parks and Playgrounds11.7100
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Light341

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000












Particulars Remarks, if any
i. No. of Flats/Apartments constructed0
ii. No. of Flats/ Apartments booked212
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter58159.47 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter11461.09 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter46698.38 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter1181.58 Lakhs
vii. Amount invested in the project upto the date of application24803.22 Lakhs
Land cost (If any)6353.65 Lakhs
Apartments9004.00 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.9445.57 LakhsOther Cost
viii. Balance cost to be incurred for completion of the project and delivery of possession122259.66 Lakhs
(a) In respect of existing allottees48846.34 Lakhs
(b) In respect of rest of the project73413.32 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
26000.00 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 6869.27 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS68.020
II. WATER SUPPLY SYSTEM99.930
III. STORM WATER DRAINAGE27.20
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL51.190
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.3.710
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT9.940









Yes
Yes
HDFC BANK LIMITED, SEC 53 VATIKA ATRIUM BRANCH, GURGAON.
57500000622122
HDFC0000572
110240093
0572
1. Mr. Lalit Jain R/o 12 Sultanpur Farms, Mehrauli, New Delhi- 110030 2. Mr. Sumeet Kumar R/o H.No.-62, Zone-H 4/5 Suvidha Kunj, Pitampura, Delhi-110034 3. Mr. Ajay Kumar Agrawal R/o H.No. 32, Sector-16A, Faridabad 4. Mr. Amit Diwan R/o D-181, Westend Heights, Near Paras Hospital DLF Phase - 5, Galleria DLF -IV Farrukhnagar, Gurgaon - 122009 5. Mrs. Tina Rawla R/o B-51, Pinnacle Apartments, DLF Phase-5, Galleria DLF IV, Gurgaon-122009 6. Mr. Monish Krishna R/o E-52, Greater Kailash-2, Delhi-110048
ENCLOSED











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED18-03-2019
II. HEIGHT CLEARANCEALREADY BEEN OBTAINED10-08-2017
III. FIRE PLANALREADY BEEN OBTAINED13-09-2019
IV. MINNING PLANALREADY BEEN OBTAINED24-01-2019
V. TREE CUTTING PERMISSIONALREADY BEEN OBTAINED23-11-2020
VI. BUILDING PLAN APPROVAL (BR-III)ALREADY BEEN OBTAINED25-04-2019
VII. BENEFICIAL INTEREST PERMISSION ALREADY BEEN OBTAINED27-04-2017








Yes


Yes


As per Agreement







ELEVATE PHASE I
5.95
308
0
212
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
68057.7168057.7118449.57
Cost of the apartments40439.0440439.049004.00
Cost of the infrastructure1397.061397.060
Others costs26221.6026221.609445.57


11461.09 Lakhs
46698.38 Lakhs
20000.00 Lakhs
9200 Lakhs
No
31-12-2024
30-06-2025










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILES
2WALL FINISHING DETAILSPAINT SURFACE
3KITCHEN DETAILSFLOOR TILES AND PAINT
4BATHROOM FITTINGSSTANDARD CP FITTING + WC+WASHBASIN
5WOOD WORK ETCFLUSH DOOR
6DOORS AND WINDOS FRAMESDOUBLE/ SINGLE GLASS
7GLASS WORKNA
8ELECTRIC FITTINGSLED FIXTURES
9CONDUCTING AND WIRING DETAILSFRLS INSULATED COPPER CONDUCTOR WIRE
10CUPBOARD DETAILSNA
11WATER STORAGEWATER TANK UG/OH
12LIFT DETAILSHIGH RISE – 8 NOS. PASSENGER LIFT & 2 NOS. SERVICE/FIREMAN LIFT COMMERCIAL 1 NOS. PASSENGER LIFT
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSDOUBLE/ SINGLE GLASS + CLEAR TENTED GLASS WITH UPVC FRAMES IN ALL HABITABLE AREA
14DOORSNA
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSBOTH SIDE LAMINATED
15AIR CONDITIONINGVRV SYSTEM
16ELECTRICAL FITTINGSLED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT
20INTERNAL FINISHINGPAINT SURFACE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORSTONE/TILES
1 . 2 WALLSPAINT
1 . 3 CEILINGPAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN/TILE
2 . 2 WALLSPAINT
2 . 3 CEILINGPAINT
2 . 4 MODULAR WARDROBESNO
3 . MASTER TOILET
3 . 1 FLOORTILES
3 . 2 WALLSTILES
3 . 3 CEILINGPAINT
3 . 4 COUNTERSSTONE
3 . 5 SANITARY WARE/CP FITTINGSSTANDARD CP FITTINGS
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORWOODEN/TILES
4 . 2 WALLSPAINT SURFACE
4 . 3 CEILINGPAINT SURFACE
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORTILES
5 . 2 WALLSTILES
5 . 3 CEILINGPAINT SURFACE
5 . 4 COUNTERSSTONE
5 . 5 SANITARY WARE/CP FITTINGSSTANDARD CP FITTINGS
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORTILES
6 . 2 WALLSPAINT SURFACE
6 . 3 CEILINGPAINT SURFACE
6 . 4 COUNTERSMARBLE / GRANITE / SYNTHETIC STONE
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESSTANDARD MODULAR KITCHEN WITH HOB AND CHIMNEY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES
7 . 2 WALLS & CEILINGPAINT SURFACE
7 . 3 TOILETCP FITTINGS & SANITARY WIRE
7 . 4 BALCONYTILES/PAINT
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DEMARCATION PLAN02-03-2021 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN03-03-2021 View Document
3IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN03-03-2021 View Document
4A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS03-03-2021 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND14-06-2021 View Document
6A-33-TOWER-D TYPICAL (22ND TO 31ST) FLOOR PLANS & AREA DIAGRAM29-07-2021 ------
7A-35-TOWER-D MACHINE ROOM & WATER TANK FLOOR PLAN & AREA DIAGRAM29-07-2021 ------
8A-43-TOWER-E ELEVATIONS E1 & E229-07-2021 ------
91_KHASRA PLAN WITH PHASE DEMARCATION-MODEL29-07-2021 ------
10A-41-TOWER-E TYPICAL (22ND TO 30TH) FLOOR PLANS & AREA DIAGRAM29-07-2021 ------
11ROAD PLAN LAYOUT29-07-2021 ------
12DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD29-07-2021 View Document
13SEWERAGE LAYOUT29-07-2021 ------
14STORM WATER LAYOUT29-07-2021 ------
15WATER SUPPLY LAYOUT29-07-2021 ------
16A-31-TOWER-D GROUND FLOOR PLAN & AREA DIAGRAM & GROUND COVERAGE29-07-2021 ------
17A-32-TOWER-D TYPICAL (1ST TO 21ST) FLOOR PLANS & AREA DIAGRAM29-07-2021 ------
18A-34-TOWER-D 32ND, 33RD. & TERRACE FLOOR PLANS & AREA DIAGRAM29-07-2021 ------
19A-36-TOWER-D ELEVATIONS E1 & E229-07-2021 ------
20A-37-TOWER-D ELEVATIONS E3 & E429-07-2021 ------
21A-38-TOWER-D SECTIONS A-A & B-B29-07-2021 ------
22A-39-TOWER-E GROUND FLOOR PLAN & AREA DIAGRAM & GROUND COVERAGE29-07-2021 ------
23A-40-TOWER-E TYPICAL (1ST TO 21ST) FLOOR PLANS & AREA DIAGRAM29-07-2021 ------
24A-42-TOWER-E 31ST, TERRACE & MACHINE ROOM FLOOR PLANS & AREA DIAGRAM29-07-2021 ------
25A-44-TOWER-E ELEVATIONS E3 & E429-07-2021 ------
26A-45-TOWER-E SECTIONS A-A & B-B29-07-2021 ------
27BR-III-25.04.201929-07-2021 ------
28C4 .SITE PLAN GREEN AREA & PARKING CALCULATION 29-07-2021 ------
29DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.29-07-2021 View Document
30NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT29-07-2021 View Document
31IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN29-07-2021 View Document
32ZONING PLAN29-07-2021 View Document