As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
503681
27-07-2017
226715
ICICI
HRERA Gurugram
13152 (Sqr/mtrs)
23017.31
174.45
81624 (Sqr/mtrs)
licence no. 50 of 2012 and 250 of 2007
Yes
15541 Lakhs
838 Lakhs
8000 Lakhs
2000 Lakhs
4703 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1032
3
CONSTRUCTION OF ROADS
1742
4
PAVEMENTS
361
5
PARKS AND PLAYGROUNDS
7000
6
GREEN BELTS
634
7
VEHICLE PARKINGS
1500
8
ELECTRICITY SUB-STATION
25
9
CLUB HOUSE
480
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
378
Total
13152
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
SELF
Yes
WATER SUPPLY
HUDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HUDA
Yes
STORM WATER DRAINAGE
HUDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
275
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
180
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
70
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
501
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
91
AS PER PROJECT REPORT
6
STREET LIGHTING
10
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
300
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
103
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
330
AS PER PROJECT REPORT
10
SHOPPING AREA
120
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
20
AS PER PROJECT REPORT
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
26-07-2013 (date)
26-07-2013 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT
14566
120
52
68
3
2
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER -3
144.17
40
3
37
1
3
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER -4
114.81
40
21
19
1
4
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER -5
105.17
40
28
12
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
APARTMENT
52
OCCUPATION CERTIFICATE RECEIVED ON 12.02.2019
01-04-2014
31-12-2018
30-06-2019
01-04-2014
100
31-12-2018
AS PER ANNEXURE
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-04-2014
100
31-12-2018
AS PER ANNEXURE
257
30
287
52
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
8000
Shops
0
Plots
0
Land Cost
838
Other Charges EDC and IDC
4703
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
275
Water Supply System
180
Sewerage treatment & garbage disposal
91
Electricity Supply System
501
Storm Water Drainage
70
Parks and Playgrounds
113
Clubhouse/community centres
330
Shopping area
0
Other
0
Covered Parking
83
Open Parking
4
Solid Waste Collection
10
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
120
ii. No. of Flats/ Apartments booked
52
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
7511 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
4673 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
2838 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
2838 Lakhs
vii. Amount invested in the project upto the date of application
10026 Lakhs
Land cost (If any)
838 Lakhs
Apartments
8000 Lakhs
Infrastructure
2000 Lakhs
EDC/ Taxes Etc.
4703 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
0 Lakhs
(a) In respect of existing allottees
400 Lakhs
(b) In respect of rest of the project
600 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
275
275
II. WATER SUPPLY SYSTEM
180
180
III. STORM WATER DRAINAGE
70
70
IV. ELECTRICITY SUPPLY SYSTEM
501
501
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
91
91
VI. CLUB HOUSE/COMMUNITY CENTRE
330
330
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
10
10
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
113
113
XIII. COVERED PARKING
83
83
XIV. OPEN PARKING
4
4
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
Yes
ICICI BANK SECTOR 23 GURUGRAM
091005000894
ICIC0000910
110229093
0910
Prashant Solomon, 44 Golf link New Delhi 110003
Attached
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. OCCUPATION CERTIFICATE
ALREADY BEEN OBTAINED
12-02-2019
Yes
Yes
Possession offered in March, 2019
CHINTELS SERENITY SECTOR 109 GURUGRAM
13152
120
0
52
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
14703
14703
14703
Cost of the apartments
8000
8000
8000
Cost of the infrastructure
2000
2000
2000
Others costs
4703
4703
4703
4673 Lakhs
2838 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2018
31-12-2018
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
LIVING DINING LOBBY ENGINEERING MARBLE BEDROOMS WOODEN FLOORING TOILETS
2
WALL FINISHING DETAILS
PLASTER AND PAINTED
3
KITCHEN DETAILS
MODULAR KITCHEN
4
BATHROOM FITTINGS
KOHLER
5
WOOD WORK ETC
CUPBOARD AND KITCHEN
6
DOORS AND WINDOS FRAMES
EXTERNAL ALUMINUM INTERNAL WOODEN
7
GLASS WORK
TOUGHENED GLASS
8
ELECTRIC FITTINGS
PANASONIC SWITCHES AND SOCKETS
9
CONDUCTING AND WIRING DETAILS
FRLS PVC CONDUITING WIRING POLY CAB
10
CUPBOARD DETAILS
PRE- LAMINATED MDF WITH PU FINISHED PAINT
11
WATER STORAGE
OVERHEAD WATER TANK
12
LIFT DETAILS
2NOS PER TOWER
13
EXTERNAL GLAZINGS
ALUMINUM AND GLASS WORK
13.1
WINDOWS/GLAZINGS
ALUMINUM AND GLASS WORK
14
DOORS
WOODEN FLUSH DOOR
14.1
MAIN DOORS
WOODEN FLUSH DOOR
14.2
INTERNAL DOORS
WOODEN FLUSH DOOR
15
AIR CONDITIONING
VRV SYSTEM LG MAKE
16
ELECTRICAL FITTINGS
PANASONIC SWITCHES AND SOCKETS
17
CNG PIPE LINE
GAS PIPELINE
18
PROVISION OF WIFI AND BROADBAND FACILITY
FTTS SERVICES
19
EXTERNAL FINISHING/COLOUR SCHEME
TEXTURE PAINT
20
INTERNAL FINISHING
PLASTER AND PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
ENGINEERED MARBLE STONE
1 . 2
WALLS
PLASTER AND PAINT
1 . 3
CEILING
PLASTER AND WHITEWASH
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
WOODEN FLOORING
2 . 2
WALLS
PLASTER AND PAINT
2 . 3
CEILING
PLASTER AND WHITEWASH
2 . 4
MODULAR WARDROBES
PRE-LAMINATED MDF WITH LAMINATION AND PU PAINT FINISH
3 . MASTER TOILET
3 . 1
FLOOR
TILES
3 . 2
WALLS
TILES
3 . 3
CEILING
GYPSUM FALSE CEILING
3 . 4
COUNTERS
STONE COUNTERS TOP
3 . 5
SANITARY WARE/CP FITTINGS
KOHLER
3 . 6
FITTING/FIXTURES
KOHLER
4 . BED ROOMS
4 . 1
FLOOR
WOODEN FLOORING
4 . 2
WALLS
PLASTER AND PAINT
4 . 3
CEILING
PLASTER AND WHITEWASH
4 . 4
WARDROBES
PRE-LAMINATED MDF WITH LAMINATION AND PU PAINT
5 . TOILET
5 . 1
FLOOR
TILES
5 . 2
WALLS
TILES
5 . 3
CEILING
GYPSUM FALSE CEILING
5 . 4
COUNTERS
STONE COUNTER TOP
5 . 5
SANITARY WARE/CP FITTINGS
KOHLER
5 . 6
FIXTURES
KOHLER
6 . KITCHEN
6 . 1
FLOOR
TILES
6 . 2
WALLS
DADO TILES / PLASTER AND PAINT
6 . 3
CEILING
PLASTER AND WHITEWASH
6 . 4
COUNTERS
STONE COUNTER TOP
6 . 5
FIXTURES
KOHLER
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
TILES
7 . 2
WALLS & CEILING
WALLS PLASTER AND PAINT. CEILING PLASTER AND WHITEWASH
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT