HRERA GurugramTemp Project Id : RERA-GRG-PROJ-455-2019
Submission Date : 26-12-2019 03:14:18 AM
Applicant Type : Company
Project Type: NEW




ESSEL HOUSING PROJECTS PRIVATE LIMITED
SUNCITY BUSINESS TOWER,224, 2ND FLOOR,SECTOR-54, GOLF COURSE ROAD GURGAON 122002
01244691000
9654128130 (Number Shared by Promoter in Public)
info@suncityprojects.com
https://www.platinum-towers.com/
XXXX693G
U70109DL1999PTC099190
 
 


 
 


 
 







PLATINUM TOWERS
SECTOR 28,
GURGAON
GURUGRAM
01244691000
0124469100 (Number Shared by Promoter in Public)
info@suncityprojects.com
NAVNEET KUMAR
01244691000
9654128130 (Number Shared by Promoter in Public)
info@suncityprojects.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques/Online Banking:-

Drafts/ Banker’s Cheques

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150707804-04-2018617150ICICI BANKHRERA Gurugram
250719327-04-201873100ICICI BANKHRERA Gurugram
351209612-11-2020406421ICICI BANKHRERA Gurugram
451209512-11-2020626505ICICI BANKHRERA Gurugram

Online Banking








5.56875 (Acre)
2.775
2.775
36.51875 (Acre)
License No 32 of 2009 , License No. 33 of 2009, License No. 21 of 2016, License No. 22 of 2016, License No 48 of 1995, License No 61 of 2004
No
Address     PILOT COURT CLUB, SECTOR 28, MAIN M. G. ROAD, GURUGRAM.
Address     75 E, HIMALIA HOUSE, 26 KG MARG, NEW DELHI
Address     845 , SECTOR 4, URBAN ESTATE, GURUGRAM
Annexure-B- COLLABORATION AGREEMENT
COLLABORATION AGREEMENT
Yes
ATTACHED
No
No
Yes







38389.29 Lakhs
668 Lakhs
24959.55 Lakhs
2340.45 Lakhs
10421.29 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 4788.486
3CONSTRUCTION OF ROADS 4778
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 2406
6GREEN BELTS 4046
7VEHICLE PARKINGS 87.50
8ELECTRICITY SUB-STATION 150
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 6280.744
Total22536.73




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSDTCP AND GMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYDHVBN (APPLIED)Yes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS128.83SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM185.37SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE36.33SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM170SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL218.35SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING21.36SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING306.24SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS54.67SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE1185SUBMITTED TO TOWN & COUNTRY PLANNING
10SHOPPING AREA14.3SUBMITTED TO TOWN & COUNTRY PLANNING
11RENEWABLE ENERGY SYSTEM20SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
09-06-2020 (date)
13-11-2017
30-06-2024
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings49123.0512646
Apartment/Shops/Other Buildings197.796121
Apartment/Shops/Other Buildings94.93553





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments12773.96
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments000400
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4005005001000
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1000130013001900
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1960.061100700125.53
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements40.8
Water Supply System95
Sewerage treatment & garbage disposal40.5
Electricity Supply System131.37
Storm Water Drainage15.6
Parks and Playgrounds34
Clubhouse/community centres0
Shopping area0
Other106.4

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5
Water Supply System2
Sewerage treatment & garbage disposal5
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres50
Shopping area0
Other0

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5557
Water Supply System2255
Sewerage treatment & garbage disposal10101012
Electricity Supply System0000
Storm Water Drainage0111
Parks and Playgrounds0000
Clubhouse/community centres50100110110
Shopping area1112
Other0000
Security and Fire Fighting System101010
Street Light22

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements771010
Water Supply System10101010
Sewerage treatment & garbage disposal22222222
Electricity Supply System0055
Storm Water Drainage111.51.5
Parks and Playgrounds0233
Clubhouse/community centres110110110110
Shopping area21.51.51
Other0000
Security and Fire Fighting System20222727
Street Light2222

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements7774.83
Water Supply System8876.37
Sewerage treatment & garbage disposal171275.35
Electricity Supply System5555
Storm Water Drainage1.52.54.52.83
Parks and Playgrounds3232.67
Clubhouse/community centres1101105550
Shopping area1110.3
Other0000
Renewable Energy555
Street Light21.51.51.38
Security and Fire Fighting System22211712.24

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.2
Water Supply System5
Sewerage treatment & garbage disposal1.5
Electricity Supply System8.63
Storm Water Drainage1.4
Parks and Playgrounds2
Clubhouse/community centres0
Shopping area0
Other0
Street Light0.98
Renewable Energy5
Security and Fire Fighting System3.6








Cash Flow in each quarter (In Lakhs)












Yes
Yes
Account Details
ICICI BANK
777705225019
ICIC0000007
110229002
000007
Arpit Goel, Suncity Business Tower,224, 2nd Floor,Sector-54, Golf Course Road Gurgaon 122002
Attached











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. BUILDING PLAN APPROVALALREADY BEEN OBTAINED09-06-2020
II. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED15-05-2018
III. CONSENT TO ESTABLISHALREADY BEEN OBTAINED29-06-2018
IV. SERVICE ESTIMATE APPROVALALREADY BEEN OBTAINED10-02-2014
V. ELECTRICAL LOAD SANCTIONALREADY BEEN OBTAINED30-06-2003
VI. AIRPORT HEIGHT CLEARANCEALREADY BEEN OBTAINED21-06-2016
VII. ZONING PLAN 1ALREADY BEEN OBTAINED25-11-2009
VIII. ZONING PLAN 2ALREADY BEEN OBTAINED18-11-2016
IX. FOREST NOCALREADY BEEN OBTAINED25-10-2012
X. DC NOC 1ALREADY BEEN OBTAINED04-01-2013
XI. DC NOC 2ALREADY BEEN OBTAINED25-10-2016
XII. WATER CONNECTIONALREADY BEEN OBTAINED06-02-2012








Yes


Yes


Attached













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEIMPORTED MARBLE
2WALL FINISHING DETAILSACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING
3KITCHEN DETAILSIMPORTED MARBLE FLOOR, GYPSUM PLASTER ON WALL
4BATHROOM FITTINGSSANITARY FITTING OF GESSI/DURAVIT/TATO OR EQUIVALENT , CP FITTING OF GESSI/ FROHE /KOHLER OR EQUIVALENT , BATHTUB IN MASTER BED ROOM
5WOOD WORK ETCOPTIONAL ONLY IN PLATINUM FINISH UNITS
6DOORS AND WINDOS FRAMESHARD WOOD / ALUMINIUM
7GLASS WORKGLASS IN EXTERNAL DOORS AND WINDOW IN BALCONY & RAILING
8ELECTRIC FITTINGSELECTRICAL SWITCHES BY LEGRAND /HAVELS/PHILIPS OR EQUIVALENT
9CONDUCTING AND WIRING DETAILSCOPPER WIRE, FRLF
10CUPBOARD DETAILSONLY IN PLATINUM FINISH UNITS
11WATER STORAGEUNDERGROUND TANK 100 KL AND OVER HEAD TANK 5 KL
12LIFT DETAILS18 LIFTS WITH LOAD BEARING 10 PERSONS
13EXTERNAL GLAZINGSALUMINUM SLIMLINE
13.1WINDOWS/GLAZINGSALUMINUM SLIMLINE
14DOORSHARD WOOD FRAMED POLISH SOLID WOOD DOORS
14.1MAIN DOORSHARD WOOD FRAMED POLISH SOLID WOOD DOORS
14.2INTERNAL DOORSHARD WOOD FRAMED POLISH VENEER FINISH FLUSH DOORS
15AIR CONDITIONINGVRV
16ELECTRICAL FITTINGSELECTRICAL SWITCHES BY LEGRAND /HAVELS/PHILIPS OR EQUIVALENT
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYNIL
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT
20INTERNAL FINISHINGACRYLIC EMULSION PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOOR( 1 ). PLATINUM FINISH : IMPORTED MARBLE ( 2 ).GOLD FINISH : IMPORTED MARBLE ( 3 ).SILVER FINISH : IMPORTED MARBLE ( 4 ).BARESHELL : CONCRETE.
1 . 2 WALLS( 1 ). PLATINUM FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 2 ).GOLD FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 3 ).SILVER FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 4 ). BARESHELL : NA.
1 . 3 CEILING( 1 ). PLATINUM FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 2 ).GOLD FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 3 ).SILVER FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 4 ).BARESHELL : CONCRETE.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOOR( 1 ). PLATINUM FINISH : IMPORTED MARBLE ( 2 ).GOLD FINISH : IMPORTED MARBLE ( 3 ).SILVER FINISH : IMPORTED MARBLE ( 4 ).BARESHELL : CONCRETE
2 . 2 WALLS( 1 ). PLATINUM FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 2 ).GOLD FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 3 ).SILVER FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 4 ).BARESHELL : NA
2 . 3 CEILING( 1 ). PLATINUM FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 2 ).GOLD FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 3 ).SILVER FINISH : ACRYLIC EMULSION PAINT WITH LIMITED FALSE CEILING AS PER DESIGN ( 4 ).BARESHELL : CONCRETE
2 . 4 MODULAR WARDROBES( 1 ). PLATINUM FINISH : MODULAR WOODWORK ( 2 ).GOLD FINISH : NA ( 3 ).SILVER FINISH : NA ( 4 ).BARESHELL : NA
3 . MASTER TOILET
3 . 1 FLOOR( 1 ). PLATINUM FINISH : IMPORTED MARBLE ( 2 ).GOLD FINISH : IMPORTED MARBLE ( 3 ).SILVER FINISH : IMPORTED MARBLE ( 4 ).BARESHELL : CONCRETE
3 . 2 WALLS( 1 ). PLATINUM FINISH : IMPORTED MARBLE & ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 2 ).GOLD FINISH : IMPORTED MARBLE & ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 3 ).SILVER FINISH : IMPORTED MARBLE & ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 4 ).BARESHELL : NA
3 . 3 CEILING( 1 ). PLATINUM FINISH : FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 2 ).GOLD FINISH : FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 3 ).SILVER FINISH : FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 4 ).BARESHELL : CONCRETE
3 . 4 COUNTERS( 1 ). PLATINUM FINISH : IMPORTED MARBLE / GRANITE COUNTERS WITH WASH BASINS ( 2 ).GOLD FINISH : IMPORTED MARBLE / GRANITE COUNTERS WITH WASH BASINS ( 3 ).SILVER FINISH : IMPORTED MARBLE / GRANITE COUNTERS WITH WASH BASINS ( 4 ).BARESHELL : NA
3 . 5 SANITARY WARE/CP FITTINGS( 1 ). PLATINUM FINISH : SANITARY FITTINGS OF GESSI/ DURAVIT / TOTO OR EQUIVALENT, CP FITTINGS OF GESSI/ GROHE / KOHLER OR EQUIVALENT, BATHTUB IN MASTER BATHROOM IN 4BHK’S ONLY, ( 2 ).GOLD FINISH : & ( 3 ).SILVER FINISH : SANITARY FITTINGS OF GESSI/ DURAVIT / TOTO OR EQUIVALENT, CP FITTINGS OF GESSI/ GROHE / KOHLER OR EQUIVALENT, BATHTUB IN MASTER BATHROOM IN 4BHK’S ONLY ( 4 ).BARESHELL : NA
3 . 6 FITTING/FIXTURES( 1 ). PLATINUM FINISH : PROVISION OF GEYSER ( 2 ).GOLD FINISH : PROVISION OF GEYSER ( 3 ).SILVER FINISH : PROVISION OF GEYSER ( 4 ).BARESHELL : NA
4 . BED ROOMS
4 . 1 FLOOR( 1 ). PLATINUM FINISH : WOODEN FLOORING ( 2 ).GOLD FINISH : IPC FLOORING WITH PROVISION FOR WOODEN FLOORING/IMPORTED MARBLE AS PER DESIGN ( 3 ).SILVER FINISH : IPC FLOORING WITH PROVISION FOR WOODEN FLOORING/IMPORTED MARBLE AS PER DESIGN ( 4 ).BARESHELL : CONCRETE
4 . 2 WALLS( 1 ). PLATINUM FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 2 ).GOLD FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 3 ).SILVER FINISH : ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 4 ).BARESHELL : NA
4 . 3 CEILING( 1 ). PLATINUM FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 2 ).GOLD FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 3 ).SILVER FINISH : ACRYLIC EMULSION PAINT WITH LIMITED FALSE CEILING AS PER DESIGN ( 4 ).BARESHELL : CONCRETE
4 . 4 WARDROBES( 1 ). PLATINUM FINISH : MODULAR WOOD WORK ( 2 ).GOLD FINISH : NA ( 3 ).SILVER FINISH : NA ( 4 ).BARESHELL : NA
5 . TOILET
5 . 1 FLOOR( 1 ). PLATINUM FINISH : IMPORTED MARBLE ( 2 ).GOLD FINISH : IMPORTED MARBLE ( 3 ).SILVER FINISH : IMPORTED MARBLE ( 4 ).BARESHELL : CONCRETE.
5 . 2 WALLS( 1 ). PLATINUM FINISH : IMPORTED MARBLE & ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 2 ).GOLD FINISH : IMPORTED MARBLE & ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 3 ).SILVER FINISH : TILES, GLASS PARTITIONS & ACRYLIC EMULSION PAINT ON GYPSUM PLASTER PUNNING ( 4 ).BARESHELL : NA
5 . 3 CEILING( 1 ). PLATINUM FINISH : FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 2 ).GOLD FINISH : FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 3 ).SILVER FINISH : FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 4 ).BARESHELL : CONCRETE
5 . 4 COUNTERS( 1 ). PLATINUM FINISH : IMPORTED MARBLE / GRANITE COUNTERS WITH WASH BASINS ( 2 ).GOLD FINISH : IMPORTED MARBLE / GRANITE COUNTERS WITH WASH BASINS ( 3 ).SILVER FINISH : IMPORTED MARBLE / GRANITE COUNTERS WITH WASH BASINS ( 4 ).BARESHELL : NA
5 . 5 SANITARY WARE/CP FITTINGS( 1 ). PLATINUM FINISH : SANITARY FITTINGS OF GESSI/ DURAVIT / TOTO OR EQUIVALENT, CP FITTINGS OF GESSI/ GROHE / KOHLER OR EQUIVALENT ( 2 ).GOLD FINISH : SANITARY FITTINGS OF GESSI/ DURAVIT / TOTO OR EQUIVALENT, CP FITTINGS OF GESSI/ GROHE / KOHLER OR EQUIVALENT ( 3 ).SILVER FINISH : SANITARY FITTINGS OF GESSI/ DURAVIT / TOTO OR EQUIVALENT, CP FITTINGS OF GESSI/ GROHE / KOHLER OR EQUIVALENT ( 4 ).BARESHELL : NA
5 . 6 FIXTURES( 1 ). PLATINUM FINISH : VANITIES, PROVISION OF GYSER ( 2 ).GOLD FINISH : PROVISION OF GYSER ( 3 ).SILVER FINISH : PROVISION OF GEYSER ( 4 ).BARESHELL : NA
6 . KITCHEN
6 . 1 FLOOR( 1 ). PLATINUM FINISH : PREMIUM IMPORTED MARBLE ( 2 ).GOLD FINISH : IMPORTED MARBLE ( 3 ).SILVER FINISH : IMPORTED MARBLE ( 4 ).BARESHELL : CONCRETE
6 . 2 WALLS( 1 ). PLATINUM FINISH : GYPSUM PLASTER ( 2 ).GOLD FINISH : GYPSUM PLASTER ( 3 ).SILVER FINISH : GYPSUM PLASTER & GRANITE ( 4 ).BARESHELL : NA
6 . 3 CEILING( 1 ). PLATINUM FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 2 ).GOLD FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 3 ).SILVER FINISH : POP/GYPSUM PLASTER FALSE CEILING WITH ACRYLIC EMULSION PAINT ( 4 ).BARESHELL : CONCRETE
6 . 4 COUNTERS( 1 ). PLATINUM FINISH : GRANITE ( 2 ).GOLD FINISH : NA ( 3 ).SILVER FINISH : NA ( 4 ).BARESHELL : NA
6 . 5 FIXTURES( 1 ). PLATINUM FINISH : MODULAR KITCHEN WORK , PROVISIONS FOR CHIMNEY, HOP, REFRIGERATOR, MICROWAVE, DISHWASHER ( 2 ).GOLD FINISH : PROVISIONS FOR CHIMNEY, HOP, REFRIGERATOR, MICROWAVE, DISHWASHER ( 3 ).SILVER FINISH : PROVISIONS FOR CHIMNEY, HOP, REFRIGERATOR, MICROWAVE, DISHWASHER ( 4 ).BARESHELL : NA
6 . 6 KITCHEN APPLIANCES( 1 ). PLATINUM FINISH : NA ( 2 ).GOLD FINISH : NA ( 3 ).SILVER FINISH : NA ( 4 ).BARESHELL : NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOOR( 1 ). PLATINUM FINISH : CERAMIC TILES ( 2 ).GOLD FINISH : CERAMIC TILES ( 3 ).SILVER FINISH : CERAMIC TILES ( 4 ).BARESHELL : CONCRETE
7 . 2 WALLS & CEILING( 1 ). PLATINUM FINISH : OIL-BOUND DISTEMPER ( 2 ).GOLD FINISH : OIL-BOUND DISTEMPER ( 3 ).SILVER FINISH : OIL-BOUND DISTEMPER ( 4 ).BARESHELL : CONCRETE
7 . 3 TOILET( 1 ). PLATINUM FINISH : CERAMIC TILE FLOORING & DADO, INDIAN MAKE SANITARY-WARE ( 2 ).GOLD FINISH : CERAMIC TILE FLOORING & DADO, INDIAN MAKE SANITARYWARE ( 3 ).SILVER FINISH : CERAMIC TILE FLOORING & DADO, INDIAN MAKE SANITARYWARE ( 4 ).BARESHELL : PROVISION OF WET POINT IN SHAFT & CUT OUT IN FLOORS
7 . 4 BALCONY( 1 ). PLATINUM FINISH : TILES AND GRANITE ( 2 ).GOLD FINISH : TILES AND GRANITE ( 3 ).SILVER FINISH : TILES AND GRANITE ( 4 ).BARESHELL : TEXTURE PAINT ON WALLS
8 . SIT-OUTS
8 . 1 FLOOR( 1 ). PLATINUM FINISH : TILES AND GRANITE ( 2 ).GOLD FINISH : TILES AND GRANITE ( 3 ).SILVER FINISH : TILES AND GRANITE ( 4 ).BARESHELL : TILES AND GRANITE
8 . 2 WALLS & CEILING( 1 ). PLATINUM FINISH : TEXTURE PAINT & OIL-BOUND DISTEMPER ( 2 ).GOLD FINISH : TEXTURE PAINT & OIL-BOUND DISTEMPER ( 3 ).SILVER FINISH : TEXTURE PAINT & OIL-BOUND DISTEMPER ( 4 ).BARESHELL : TEXTURE PAINT & OIL-BOUND DISTEMPER
8 . 3 RAILINGS( 1 ). PLATINUM FINISH : GLASS RAILINGS ( 2 ).GOLD FINISH : GLASS RAILINGS ( 3 ).SILVER FINISH : GLASS RAILINGS ( 4 ).BARESHELL : GLASS RAILINGS
8 . 4 FIXTURES( 1 ). PLATINUM FINISH : NA ( 2 ).GOLD FINISH : NA ( 3 ).SILVER FINISH : NA ( 4 ).BARESHELL : NA












Sr. No.Document DescriptionDate of Document UploadView Document
1 PAYMENT PLAN 24-12-2020 View Document
2 AFFIDAVIT 18-12-2020 24-12-2020 View Document
3 BALANCE SHEET ESSEL HOUSING 2020 24-12-2020 View Document
4 BANKS UNDERTAKING 24-12-2020 View Document
5 NON DEFAULT CERTIFICATE 24-12-2020 View Document
6 REP II 18-12-2020 24-12-2020 View Document
7 BR-III 24-12-2020 View Document
8 PERT CHART 24-12-2020 View Document
9 SERVICE APPROVAL LETTER 24-12-2020 View Document
10 MUTATION PLATINUM TOWERS 24-12-2020 View Document
11 DC NOC 24-12-2020 View Document
12 SERVICE ETIMATE 24-12-2020 View Document
13 DEMARCATION PLAN 24-12-2020 View Document
14 LOAN SANCTION LETTER & STATEMENT 24-12-2020 View Document
15 SHIJRA 24-12-2020 View Document
16 FIRE NOC 24-12-2020 View Document
17 SITE PLAN, BUILDING PLAN 24-12-2020 View Document
18 JAMABANDI PLATINUM TOWER 24-12-2020 View Document
19 TITLE SEARCH REPORT 24-12-2020 View Document
20 LC-IV 24-12-2020 View Document
21 TOD PERMISSION NOC 24-12-2020 View Document
22 LICENSE 24-12-2020 View Document
23 TOD ZONING PLAN REVISION 24-12-2020 View Document
24 LOI TOD 24-12-2020 View Document
25 ZONING TOD 24-12-2020 View Document
26 LOI 24-12-2020 View Document
27 EC NOC 24-12-2020 View Document
28 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 09-12-2019 View Document
29 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 09-12-2019 View Document
30 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 09-12-2019 View Document
31 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 09-12-2019 View Document
32 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 09-12-2019 View Document
33 (Supplementary Document) 14-04-2021 View Document
34 (Supplementary Document) 14-04-2021 View Document