HRERA GurugramTemp Project Id : RERA-GRG-PROJ-447-2019
Submission Date : 07-12-2019 04:52:23 AM
Applicant Type : Company
Project Type: ONGOING




RAMPRASTHA PROMOTERS & DEVELOPERS PRIVATE LIMITED
PLOT NO. 114, SECTOR 44, GURUGRAM, HARYANA - 122002
01244333433
9810553404 (Number Shared by Promoter in Public)
risehrera@ramprastha.com
http://www.ramprastha.com/
XXXX481J
u45400hr2007ptc064534
 
 


 
 


 
 


 
 







RISE
RAMPRASTHA CITY, SECTOR-37D, GURUGRAM
KADIPUR ST
GURUGRAM
8178365385 (Number Shared by Promoter in Public)
satish@ramprastha.com
SATISH SHARMA
8178365385 (Number Shared by Promoter in Public)
satish@ramprastha.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
17905529-07-2017484000CORPORATION BANKHRERA Gurugram
25324106-06-2019483640CORPORATION BANKHRERA Gurugram
310895409-01-2020301915HDFC BANKHRERA Gurugram
457368277720-07-20212258135HDFC BANK(RTGS)HRERA Gurugram







13998.08 (Sqr/mtrs)
175
175
244879.38 (Sqr/mtrs)
33 of 2008(19-02-2008)
Yes







18732.28 Lakhs
261.21 Lakhs
14306.75 Lakhs
1307.32 Lakhs
2857.00 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2784.24
3CONSTRUCTION OF ROADS3952.43
4PAVEMENTS1850.76
5PARKS AND PLAYGROUNDS4686.26
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE461.34
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13COMMERCIAL263.05
Total13998.08




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPYes
WATER SUPPLYHUDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVP/GMDANo
STORM WATER DRAINAGEHSVP/GMDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS79.20SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM33.71SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE63.87SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM189.48SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL37.41SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING27.83SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING242.33SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS16.50SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0SUBMITTED TO TOWN & COUNTRY PLANNING
10SHOPPING AREA0SUBMITTED TO TOWN & COUNTRY PLANNING
11RENEWABLE ENERGY SYSTEM10.00SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL0SUBMITTED TO TOWN & COUNTRY PLANNING
13HOSPITAL/DISPENSARY0SUBMITTED TO TOWN & COUNTRY PLANNING
14ANY OTHER606.99SUBMITTED TO TOWN & COUNTRY PLANNING


23-12-2011 (date)
12-04-2012 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK TYPE 1120.59010610605
2APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK TYPE 2119.48520820625
3APARTMENT/SHOPS/OTHER BUILDINGS Type DUPLEX A192.0806423
4APARTMENT/SHOPS/OTHER BUILDINGS Type DUPLEX B192.0802112






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
3 BHK TYPE 110653% COMPLETED
3 BHK TYPE 220653% COMPLETED
DUPLEX A453% COMPLETED
DUPLEX B153% COMPLETED


22-03-2013
30-12-2020
31-12-2023
01-01-2017
20
31-12-2023


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-01-2017
20
31-12-2023


483
0
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments8241.43
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots00

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0760
Shops00
Plots00

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments840910935785
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments720620495
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements16
Water Supply System11
Sewerage treatment & garbage disposal17
Electricity Supply System58
Storm Water Drainage23
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other225

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System04.00
Sewerage treatment & garbage disposal05.00
Electricity Supply System08.00
Storm Water Drainage07.00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Electric Sub Station24.00
Security and Fire Fighting13.00
Underground Water Tank8.00

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements08.0011.0012.00
Water Supply System6.006.003.004.00
Sewerage treatment & garbage disposal4.003.006.003.00
Electricity Supply System13.0021.0014.0022.00
Storm Water Drainage9.0011.008.006.00
Parks and Playgrounds0005.0
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank4.008.0012.000
Security and Fire Fighting18.0023.0031.0029.00
STP3.002.004.001.00
Maintenance14.0018.0021.00
Electric Sub Station29.0034.0041.0031.00
Street Lighting7.00

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.009.007.00
Water Supply System000
Sewerage treatment & garbage disposal4.0000
Electricity Supply System17.0016.0020.00
Storm Water Drainage000
Parks and Playgrounds3.005.004.00
Clubhouse/community centres000
Shopping area000
Other000
Maintenance23.0025.0027.00
Electric Sub Station39.0045.0038.00
Security and Fire Fighting17.0021.0025.00
Street Lighting11.006.004.00












Particulars Remarks, if any
i. No. of Flats/Apartments constructed322
ii. No. of Flats/ Apartments booked317
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter26153 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter20142 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter6011 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application11072.57 Lakhs
Land cost (If any)261.21 Lakhs
Apartments8241.43 Lakhs
Infrastructure350 Lakhs
EDC/ Taxes Etc.2219.93 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession7658.39 Lakhs
(a) In respect of existing allottees7539.47 Lakhs
(b) In respect of rest of the project118.92 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
2644.66 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS79.2016
II. WATER SUPPLY SYSTEM33.7111
III. STORM WATER DRAINAGE63.8723
IV. ELECTRICITY SUPPLY SYSTEM189.4858
V. SEWAGE TREATMENT & GARBAGE DISPOSAL37.4112
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER27.830
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.16.500
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM242.3365
XVII. OTHER FACILITIES AS PER PROJECT REPORT619.99165









Yes
Yes
SBI, 91,IDC, MID CORP. BRANCH, GURUGRAM
40206750032
SBIN0050933
110002777
050933
Mr Arvind Walia, Address-A-105 Ground Floor Vasant Vihar New Delhi - 110057











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE RENEWALALREADY BEEN OBTAINED18-02-2020
II. ARAVALI NOC ALREADY BEEN OBTAINED04-04-2011
III. FOREST NOC ALREADY BEEN OBTAINED18-01-2011
IV. WATER ASSURANCE ALREADY BEEN OBTAINED10-01-2018
V. HEIGHT CLEARANCE ALREADY BEEN OBTAINED05-05-2017
VI. BUILDING PLAN BR III ALREADY BEEN OBTAINED12-04-2012
VII. REVISED BUILDING PLAN APPROVAL BR III ALREADY BEEN OBTAINED04-09-2019
VIII. ENVIRONMENTAL CLEARANCE APPLIED FOR BUT YET TO RECEIVE31-08-2017








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEMASTER BEDROOM - LAMINATED WOODEN FLOORING LIVING / DINING / LOBBY & OTHER BEDROOMS - VITRIFIED TILES BALCONIES / TERRACES - ANTI SKID TILES KITCHEN & TOILETS - ANTI SKID TILES
2WALL FINISHING DETAILSBEDROOMS LIVING / DINING / LOBBY - ACRYLIC EMULSION BALCONIES/TERRACES - ACRYLIC EMULSION / WEATHER PROOF PAINT KITCHEN & TOILETS - COMBINATION OF CERAMIC TILES
3KITCHEN DETAILSSTAINLESS STEEL SINK WITH DRAINBOARD
4BATHROOM FITTINGS SINGLE LEVER CP FITTINGS, WHITE CHINAWARE, SHOWER PARTITION ONLY IN THE MASTER BATHROOM
5WOOD WORK ETCN/A
6DOORS AND WINDOS FRAMESINTERNAL DOORS - HARDWOOD DOOR FRAMES VENEERED & POLISHED / SKIN MOULDED SHUTTERS / FLUSH DOOR SHUTTER EXTERNAL GLAZING - UPVC DOORS & GLAZING
7GLASS WORKGLASS PARTITION ONLY IN THE MASTER BATHROOM
8ELECTRIC FITTINGSSPLIT AIR CONDITIONERS IN ALL BEDROOMS, DRAWING & DINING. MODULAR TYPE SWITCHES & SOCKETS, COPPER WIRING (FITTINGS LIKE FANS, LIGHT FIXTURES, GEYSERS APPLIANCES ETC. NOT PROVIDED).
9CONDUCTING AND WIRING DETAILSCOPPER WIRING
10CUPBOARD DETAILSNA
11WATER STORAGEOHT
12LIFT DETAILS3 LIFTS IN EACH TOWER
13EXTERNAL GLAZINGSUPVC DOORS & GLAZING
13.1WINDOWS/GLAZINGSUPVC
14DOORSHARDWOOD DOOR FRAMES VENEERED & POLISHED / SKIN MOULDED SHUTTERS / FLUSH DOOR SHUTTER
14.1MAIN DOORSHARDWOOD DOOR FRAMES VENEERED & POLISHED / SKIN MOULDED SHUTTERS / FLUSH DOOR SHUTTER
14.2INTERNAL DOORSHARDWOOD DOOR FRAMES VENEERED & POLISHED / SKIN MOULDED SHUTTERS / FLUSH DOOR SHUTTER
15AIR CONDITIONING5 SPLIT AC IN EACH UNIT
16ELECTRICAL FITTINGSSPLIT AIR CONDITIONERS IN ALL BEDROOMS, DRAWING & DINING. MODULAR TYPE SWITCHES & SOCKETS, COPPER WIRING (FITTINGS LIKE FANS, LIGHT FIXTURES, GEYSERS APPLIANCES ETC. NOT PROVIDED).
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYCAT5E CABLE CONNECTIVITY
19EXTERNAL FINISHING/COLOUR SCHEMEWEATHERPROOF PAINT
20INTERNAL FINISHINGWALL OBD
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSACRYLIC EMULSION
1 . 3 CEILINGCEMENT PLASTER WITH OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSCEMENT PLASTER WITH OBD
2 . 3 CEILINGCEMENT PLASTER WITH OBD
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORANTI SKID TILES
3 . 2 WALLSANTI SKID TILES
3 . 3 CEILINGACRYLIC EMULSION
3 . 4 COUNTERSMARBLE/GRANITE
3 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER CP FITTINGS
3 . 6 FITTING/FIXTURESWHITE CHINAWARE, SHOWER PARTITION ONLY IN THE MASTER BATHROOM
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSACRYLIC EMULSION
4 . 3 CEILINGCEMENT PLASTER WITH OBD
4 . 4 WARDROBESN/A
5 . TOILET
5 . 1 FLOORANTI SKID TILES
5 . 2 WALLSCOMBINATION OF CERAMIC TILES
5 . 3 CEILINGACRYLIC EMULSION
5 . 4 COUNTERSMARBLE/GRANITE
5 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER CP FITTINGS
5 . 6 FIXTURESWHITE CHINAWARE, SHOWER PARTITION ONLY IN THE MASTER BATHROOM
6 . KITCHEN
6 . 1 FLOORANTI SKID VITRIFIED TILES
6 . 2 WALLSCOMBINATION OF CERAMIC TILES
6 . 3 CEILINGACRYLIC EMULSION
6 . 4 COUNTERSMARBLE/GRANITE
6 . 5 FIXTURESSTAINLESS STEEL SINK WITH DRAINBOARD
6 . 6 KITCHEN APPLIANCESN/A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVIRTIFIED
7 . 2 WALLS & CEILINGACRYLIC EMUSLION/OBD
7 . 3 TOILETNA
7 . 4 BALCONYANTI SKID TILES
8 . SIT-OUTS
8 . 1 FLOORN/A
8 . 2 WALLS & CEILINGN/A
8 . 3 RAILINGSN/A
8 . 4 FIXTURESN/A












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND06-12-2019 View Document
2A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS (.PDF,JPG,JPEG,PNG06-12-2019 ------
3SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN (.PDF,JPG,JPEG,PNG)06-12-2019 ------
4IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN06-12-2019 View Document
5SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN (.PDF,JPG,JPEG,PNG)06-12-2019 ------
6SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN (.PDF,JPG,JPEG,PNG)06-12-2019 ------
7CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT06-12-2019 View Document
8DEMARCATION PLAN06-12-2019 View Document
9A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS06-12-2019 View Document
10A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS (.PDF,JPG,JPEG,PNG06-12-2019 ------
11SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN (.PDF,JPG,JPEG,PNG)06-12-2019 ------
12ZONING PLAN06-12-2019 View Document
13SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN (.PDF,JPG,JPEG,PNG)06-12-2019 ------
14SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN06-12-2019 View Document
15A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS (.PDF,JPG,JPEG,PNG06-12-2019 ------
16SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN (.PDF,JPG,JPEG,PNG)06-12-2019 ------
17DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD06-12-2019 View Document
18A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS (.PDF,JPG,JPEG,PNG)06-12-2019 ------
19IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN06-12-2019 View Document
20DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.07-12-2019 View Document
21AIRPORT AUTHORITY CLEARANCE 202004-02-2020 ------
22LICENSE ALONG WITH LAND SCHEDULE04-02-2020 ------
23BUILDING PLAN APPROVAL LETTER04-02-2020 ------
24PLANS TOWER B&E04-02-2020 ------
25SITE PLAN04-02-2020 ------
26SECTIONS TOWER-D04-02-2020 ------
27SECTION & ELEVATION EWS (BLOCK-A)04-02-2020 ------
28FOREST CLEARANCE 60 ACRE04-02-2020 ------
29SECTIONS TOWER-C04-02-2020 ------
30ENVIRONMENT CLEARANCE LETTER04-02-2020 ------
31SECTIONS TOWER-B04-02-2020 ------
32ELEVATIONS TOWER-C04-02-2020 ------
33AREA CALCULATION SITE PLAN04-02-2020 ------
34SECTIONS TOWER-A04-02-2020 ------
35NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT04-02-2020 View Document
36SECTIONS TOWER-E04-02-2020 ------
37SERVICE ESTIMATE04-02-2020 ------
38LOI 33 60 ACRES04-02-2020 ------
39ELEVATIONS TOWER-E04-02-2020 ------
40PLANS TOWER A, C & D04-02-2020 ------
41CASH FLOW STATEMENT OF THE PROPOSED PROJECT04-02-2020 View Document
42FLOOR PLAN EWS (BLOCK- A)04-02-2020 ------
43LC IV FOR 60 ACRES04-02-2020 ------
44BASEMENT PLAN04-02-2020 ------
45ELEVATION EWS (BLOCK-A)04-02-2020 ------
46ELEVATIONS TOWER-D04-02-2020 ------
47ELEVATIONS TOWER-B04-02-2020 ------
48COMMERICAL BLOCK04-02-2020 ------
49ELEVATION OF TOWER -A04-02-2020 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 Extension No. 08 OF 2020 DATED-17.06.2020 04-08-2020 View Document
2 Extension No. 278 of 2017/7(3)/2021/2 Dated: 20.07.2021 22-08-2022 View Document