| 16-Jan-2026 |
PENDING |
|
|
--- |
--- |
| 18-Dec-2025 |
PENDING |
None is present on behalf of
the promoter. It is noticed that the Occupation
Certificate for the project has been obtained on 23.07.2021, copy of which
has been submitted in the Authority. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project
alongwith the status of Completion Certificate.
The
matter to come up on 16.01.2026.
|
VIJAY KUMAR GOYAL |
View Order |
07-Jan-2026 |
| 13-Nov-2025 |
PENDING |
THE MATTER IS ADJOURNED AND FIXED FOR 18.12.2025. |
ANU |
--- |
--- |
| 29-Oct-2025 |
PENDING |
The matter is adjourned and fixed for 13.11.2025. |
ANU |
--- |
--- |
| 01-Oct-2025 |
PENDING |
The matter is fixed for 29.10.2025. |
VIJAY KUMAR GOYAL |
--- |
--- |
| 29-Aug-2025 |
FIRST HEARING |
Due
to the meeting to discuss the issues of CREDAI, NAREDCO and BRICS related to
Haryana Real Estate Regulatory Authorities (Gurugram and Panchkula) under
chairmanship of W/CS, Haryana, today’s hearing is adjourned. The promoter is
directed to file the updated status of project completion and obtaining of
CC/OC, if any before next date of hearing.
The
matter to come up on 01.10.2025 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
19-Sep-2025 |