| 27-Mar-2025 |
DISPOSED |
1.
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts
of the case.
2.
Sh. Narender Singh (AVP), Sh. Manoj Tiwari (DGM) and Sh. Vipin Yadav (AR)
appeared on behalf of the promoter and state that the copy of the EC has been
received and submitted to the Authority vide Dak ID 88600 dated 21.03.2025 and
request to condone the delay as the same occurred due to vacancy at the level
of the SEAC.
3.
The Authority decided in its meeting dated 01.01.2024 that the
compliances by the promoters must be made without fail within the timeline of
conditional registration failing which the BG/ security be forfeited and
further action be initiated as per the provisions of the Act of 2016.
4.
It is not disputed that the promoter was granted conditional registration
at its own accord and depositing of security amount of Rs. 25 lakhs as a
security deposit to submit the environmental clearance within three months from
the date of grant of registration. It was clearly mentioned in the registration
certificate that this security amount shall be forfeited in case the promoter
fails to submit the environmental clearance within the stipulated time period.
5.
Since the promoter has obtained the environmental clearance with a delay
104 days, the security amount deposited vide DD no. 505692 dated 03.08.2024 in
lieu of the same is hereby forfeited.
6.
Since the compliance has now been made, the case is filed. Detailed order
shall follow.The order was passed on 27.03.2025 but couldn't be uploaded on the website of the Authority inadvertently. Now, the same is being uploaded. So, the concerned party may calculate the limitations from the date of upload of the order. |
ASHOK SANGWAN |
View Order |
25-Jul-2025 |