Complaint Detail:RERA-GRG-1589-2025
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA THROUGH NEERAJ V/S
CORONA REALTORS PRIVATE LIMITED
Self GURUGRAM DISPOSED NOT REQUIRED Not Yet NON COMPLIANCE OF RC CONDITIONS --
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
27-Mar-2025 DISPOSED 1.       Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. 2.       Sh. Narender Singh (AVP), Sh. Manoj Tiwari (DGM) and Sh. Vipin Yadav (AR) appeared on behalf of the promoter and state that the copy of the EC has been received and submitted to the Authority vide Dak ID 88600 dated 21.03.2025 and request to condone the delay as the same occurred due to vacancy at the level of the SEAC. 3.       The Authority decided in its meeting dated 01.01.2024 that the compliances by the promoters must be made without fail within the timeline of conditional registration failing which the BG/ security be forfeited and further action be initiated as per the provisions of the Act of 2016. 4.       It is not disputed that the promoter was granted conditional registration at its own accord and depositing of security amount of Rs. 25 lakhs as a security deposit to submit the environmental clearance within three months from the date of grant of registration. It was clearly mentioned in the registration certificate that this security amount shall be forfeited in case the promoter fails to submit the environmental clearance within the stipulated time period. 5.       Since the promoter has obtained the environmental clearance with a delay 104 days, the security amount deposited vide DD no. 505692 dated 03.08.2024 in lieu of the same is hereby forfeited. 6.       Since the compliance has now been made, the case is filed. Detailed order shall follow.The order was passed on 27.03.2025 but couldn't be uploaded on the website of the Authority inadvertently. Now, the same is being uploaded. So, the concerned party may calculate the limitations from the date of upload of the order. ASHOK SANGWAN View Order 25-Jul-2025
Complaint Final Judgement Details
Date of Judgement Party Details Judgement Uploading Date View Judgement
27-Mar-2025 HARERA THROUGH NEERAJ V/S
CORONA REALTORS PRIVATE LIMITED
--- ---