| Party Dtls | Self / Adv Name | District | Current Status | Next Date of Hearing | Complaint Dispatched | Complaint Dispatched On | Dispatched Tracking Id | Complaint Dispatched Remarks | First-Hearing/Scrutinized Remarks | View Notice |
|---|---|---|---|---|---|---|---|---|---|---|
| HARERA THROUGH NEERAJ V/S EMPERIUM INFRASTRUCTURE PRIVATE LIMITED |
Self | GURUGRAM | DISPOSED | NOT REQUIRED | Yes | 16-Jan-2025 | RERA-GRG-250-2025 | DISPATCHED TO AR | REGARDING NON COMPLIANCE OF RC CONDITIONS |
| Notice Number | Remarks | Dispatching Date | Dispatch Id | View Notice |
|---|---|---|---|---|
| First Notice | DISPATCHED TO AR | 16-Jan-2025 | RERA-GRG-250-2025 |
| Date of Hearing | Status | Proceedings of the day | Bench | Order | Order Uploaded On |
|---|---|---|---|---|---|
| 06-Mar-2025 | DISPOSED | Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Dinesh Anand (Finance Manger) appeared on behalf of the promoter and states that the EC has now been submitted vide Dak ID 87478 dated 24.02.2025 Since the compliance is now made, the case is filed. | ASHOK SANGWAN | View Order | 19-May-2025 |
| 30-Jan-2025 | FIRST HEARING | Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Dinesh Anand (Finance Manger) appeared on behalf of the promoter and states that the EC proposal was approved in the meeting of SEAC held on 29.07.2024 but certain documents were sought from the promoter by SEIAA due to which the approval is delayed and the approval is expected within 30 days. Heard. The Authority decided in its meeting dated 01.01.2024 that the compliances by the promoters must be made without fail within the timeline of conditional registration failing which the BG/ security be forfeited and further action be initiated as per the provisions of the Act of 2016. It is not disputed that the promoter was granted conditional registration at its own accord and depositing of security amount in the form of demand draft in lieu of submission of the requisite clearances within the time specified in the conditional registration. It was clearly mentioned in the registration certificate that these DD's shall be forfeited in favour of authority in case the conditions are not fulfilled by the promoter within the stipulated time period. In view of the above, the security amount deposited by the promoter in lieu of timely submission of environmental clearance is hereby forfeited. The security amount deposited on account of timely submission of fire scheme approval already stands refunded since the same was obtained within the stipulated time period mentioned in the conditions. Further, last opportunity is granted to the promoter to submit the pending compliance within a period of one month failing which proceedings u/s 7 are liable to be initiated. The matter to come up on 06.03.2025. | ASHOK SANGWAN | View Order | 03-Feb-2025 |
| Date of Judgement | Party Details | Judgement Uploading Date | View Judgement |
|---|---|---|---|
| 06-Mar-2025 | HARERA THROUGH NEERAJ V/S EMPERIUM INFRASTRUCTURE PRIVATE LIMITED |
--- | --- |
| Dak ID | Receiving Date | Submitted By | Remarks |
|---|---|---|---|
| 85426 | 16/01/2025 | HARERA THROUGH NEERAJ | NEW COMPLAINT |
| 88552 | 20/03/2025 | HARSHIT BATRA ADV | CERTIFIED COPY OF ORDER & 1ST NOTICE IN SOU-MOTO COMPLAINTS - 2 SET. |