| 30-Jan-2025 |
DISPOSED |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the
case.
Sh. Rajeev Gupta (Sr. VP) and Sh. Narendra Kumar (Manager) appeared
on behalf of the promoter and requests to condone the delay and request for
refund of security deposit of Rs. 25 lakhs deposited towards submission of fire
scheme approval. The promoter submits that the list of objections was issued by
the office of Deputy Director, Fire Station vide memo dated 20.07.2024 that
envisaged major revision in the entire fire scheme vis a vis its design
calculation and other related parameters but without affecting the already
approved building plans. He further states that the approval got delayed due to
festival season and the imposition of code of conduct and elections due to
which the concerned officers were deputed on election duty.
The
Authority decided in its meeting dated 01.01.2024 that the compliances by the
promoters must be made without fail within the timeline of conditional
registration failing which the BG/ security be forfeited and further action be
initiated as per the provisions of the Act of 2016.
It is not disputed that the
promoter was granted conditional registration at its own accord and depositing
of security amount in the form of demand draft in lieu of submission of the
requisite clearances within the time specified in the conditional registration.
It was clearly mentioned in the registration certificate that this security
amount shall be forfeited in case the promoter fails to submit the requisite
approvals within the stipulated time period.
In view of the above, the
security amount submitted in lieu of timely submission of the approved fire
scheme is hereby forfeited.
The security amount
deposited in lieu of timely submission of proved service plans & estimates
already stands refunded to the promoter. Since the compliance has now been
made, although with a delay, the case is filed.
Detailed order shall follow. |
ASHOK SANGWAN |
View Order |
10-Feb-2025 |