| 12-Dec-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the
case.
Sh. S K Kaushik (AR)
appeared on behalf of the promoter and requested to condone the delay.
The promoter has submitted a
representation stating that the approval of environmental clearance was delayed
primarily due to code of conduct with respect to the Haryana State Assembly elections.
However, it is not disputed
that the promoter was granted conditional registration at its own accord and
depositing of security amount in the form of demand draft in lieu of submission
of the requisite clearances within the time specified in the conditional
registration. It was clearly mentioned in the registration certificate that
this DD shall be forfeited in favour of Authority in case the conditions are
not fulfilled by the promoter within the stipulated time period.
In view of the above, the
security amount submitted in lieu of timely submission of environmental
clearance is hereby forfeited. The security amount submitted on account of
approved service plans & estimates already stands refunded as the same was
deposited within the stipulated time. Since the compliance has now been made,
although with a delay, the case is filed.
Detailed order shall follow. |
ASHOK SANGWAN |
View Order |
18-Dec-2024 |