Comprehensive Complaint Details
Complaint Detail:RERA-GRG-4371-2024
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA GURUGRAM THROUGH NEERAJ GAUTAM V/S
GANGA GLOBAL HOMES PRIVATE LIMITED
Self GURUGRAM PENDING 05-May-2025 Yes 02-Sep-2024 RERA-GRG-4371-2024 Dispatched to AR First hearing
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice Dispatched to AR 02-Sep-2024 RERA-GRG-4371-2024
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
05-May-2025 PENDING --- ---
06-Mar-2025 PENDING Ms. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. None appeared on the behalf of the promoter. It is noted that the promoter obtained the environmental clearance within the stipulated time period mentioned in the condition and the security amount deposited in lieu of the same has already been refunded to the promoter. The approval of fire scheme is obtained with a delay and the approval of service plans and estimates is obtained with a delay. It is clearly mentioned at G(ii) of the registration certificate that “the promoter submitted three DD vide no. 503876, 503875 and 503877 dated 12.10.2023 amounting to Rs. 25 lakhs each as a security amount towards submission of Environmental Clearance, Fire Scheme approval and Service plans and estimates approval respectively. These DD shall be forfeited in case the respective conditions are not fulfilled by the promoter within the stipulated time period mentioned in the conditions.”  Therefore, the security amount submitted by the promoter in lieu of timely submission of fire scheme approval and service plan and estimate approval is hereby forfeited. The security amount deposited on account of environmental clearance already stand refunded on 10.09.2024. The promoter has still not submitted the required compliance till date.It further noted on the perusal of reply dated 10.09.2024 that the promoter is in the process of revising the building plans of the project. Keeping in view the above, the promoter is restrained from creating any further third- party rights till the revised registration as per the revision in building plans is obtained from this Authority. The AR of the promoter states that the revised building plans are expected to be approved within a period of two months. Therefore, the matter may be fixed before the Authority on 05.05.2025. ASHOK SANGWAN --- ---
10-Oct-2024 PENDING The matter is adjourned to 06.03.2025. ASHOK SANGWAN --- ---
12-Sep-2024 FIRST HEARING Matter is adjourned to 10.10.2024. ASHOK SANGWAN --- ---
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
78268 02/09/2024 HARERA THROUGH NEERAJ NEW COMPLAINT
78671 10/09/2024 ASHWANI KUMAR REPLY TO SHOW-CAUSE NOTICE FOR FORFEITURE OF SECURITY AMOUNT OF PROJECT- 4371-2024, DT: 02.09.2024.