| 22-Aug-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Praveen Kumar Singh (AR)
appeared on behalf of the promoter and requests for condonation of delay.
However, it is not disputed that
the promoter was granted conditional registration at its own accord and
depositing of security amount in the form of DDs in lieu of submission of the
requisite clearances within the time specified in the conditional registration.
It was clearly mentioned in the registration certificate that this security
amount shall be forfeited in case the respective conditions are not fulfilled
by the promoter within the stipulated time period mentioned in the conditions.
Keeping in view the fact that the
environmental clearance is obtained with a delay of 21 days, the security
amount submitted in lieu thereof is hereby forfeited.
Since the compliances have now
been made, although with a delay, the case is filed.
Detailed order shall follow. |
ASHOK SANGWAN |
View Order |
23-Aug-2024 |