| 27-Aug-2025 |
PENDING |
|
|
--- |
--- |
| 30-Jul-2025 |
PENDING |
Sh.
Ravinder is present on behalf of the promoter.
The
AR of the promoter states that they have applied for continuation of project
which is under process and next date of hearing is 11.08.2025.
In
view of the above, the matter is adjourned and to come up on 27.08.2025.
|
VIJAY KUMAR GOYAL |
View Order |
26-Aug-2025 |
| 18-Jun-2025 |
PENDING |
THE MATTER IS FIXED FOR 30.07.2025. |
VIJAY KUMAR GOYAL |
--- |
--- |
| 02-Apr-2025 |
PENDING |
The matter is fixed for 18.06.2025. |
VIJAY KUMAR GOYAL |
--- |
--- |
| 19-Feb-2025 |
PENDING |
Sh.
Vineet Maheshwari, Sh. Siddhatha Kapoor and Sh. Vedant Batra are present on
behalf of the promoter.
The
AR of the promoter states that they have already applied for extension of
registration of project and matter is listed on 17.03.2025. Further, states
that the completion certificate has also been applied.
The
matter to come up on 02.04.2025.
|
VIJAY KUMAR GOYAL |
View Order |
25-Mar-2025 |
| 08-Jan-2025 |
PENDING |
Sh. Vineet Maheswari and Sh.
Vedant Batra are present on behalf of the promoter.
The AR states that the application
u/s 6 of the Act has been applied in the Authority which is under
consideration of the Authority.
The matter is adjourned and
fixed for 19.02.2025.
|
VIJAY KUMAR GOYAL |
View Order |
13-Jan-2025 |
| 20-Nov-2024 |
PENDING |
Sh.
Vedant (AR) is present on behalf of the promoter.
The
AR states that the application u/s 6 of the Act has been applied in the
Authority which is under consideration of the Authority.
The
matter is adjourned and fixed for 08.01.2025.
|
VIJAY KUMAR GOYAL |
View Order |
19-Dec-2024 |
| 30-Oct-2024 |
PENDING |
The
presiding member is on leave. The matter is adjourned and fixed for 20.11.2024.
|
VIJAY KUMAR GOYAL |
View Order |
13-Nov-2024 |
| 13-Sep-2024 |
PENDING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project.
The
matter to come up on 30.10.2024.
|
VIJAY KUMAR GOYAL |
View Order |
09-Oct-2024 |
| 09-Aug-2024 |
FIRST HEARING |
Sh.
Vedant Batra (CS) and Sh. Ravinder (Sr. Exe) are present on behalf of the
promoter.
The
AR of the promoter states that they have applied for continuation of project
which is under process. The matter to come up on 13.09.2024.
|
VIJAY KUMAR GOYAL |
View Order |
27-Aug-2024 |