| 16-Jan-2026 |
PENDING |
|
|
--- |
--- |
| 18-Dec-2025 |
PENDING |
None is present on behalf of
the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project failing
which the concerned PE to put up on file to initiate penal proceeding.
The
matter to come up on 16.01.2026.
|
VIJAY KUMAR GOYAL |
View Order |
07-Jan-2026 |
| 13-Nov-2025 |
PENDING |
THE MATTER IS ADJOURNED AND FIXED FOR 18.12.2025. |
ANU |
--- |
--- |
| 29-Oct-2025 |
PENDING |
The matter is adjourned and fixed for 13.11.2025. |
ANU |
--- |
--- |
| 27-Aug-2025 |
PENDING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project failing
which penal proceedings are liable to be initiated.
The
matter to come up on 29.10.2025.
|
VIJAY KUMAR GOYAL |
View Order |
28-Oct-2025 |
| 30-Jul-2025 |
PENDING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project.
The
matter to come up on 27.08.2025.
|
VIJAY KUMAR GOYAL |
View Order |
26-Aug-2025 |
| 18-Jun-2025 |
PENDING |
THE MATTER IS FIXED FOR 30.07.2025. |
VIJAY KUMAR GOYAL |
--- |
--- |
| 02-Apr-2025 |
PENDING |
The matter is fixed for 18.06.2025. |
VIJAY KUMAR GOYAL |
--- |
--- |
| 19-Feb-2025 |
PENDING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project.
The
matter to come up on 02.04.2025.
|
VIJAY KUMAR GOYAL |
View Order |
25-Mar-2025 |
| 08-Jan-2025 |
PENDING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project.
The
matter to come up on 19.02.2025.
|
VIJAY KUMAR GOYAL |
View Order |
13-Jan-2025 |
| 20-Nov-2024 |
PENDING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project.
The
matter to come up on 08.01.2025.
|
VIJAY KUMAR GOYAL |
View Order |
19-Dec-2024 |
| 30-Oct-2024 |
PENDING |
The
presiding member is on leave. The matter is adjourned and fixed for 20.11.2024.
|
VIJAY KUMAR GOYAL |
View Order |
13-Nov-2024 |
| 13-Sep-2024 |
PENDING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project.
The
matter to come up on 30.10.2024.
|
VIJAY KUMAR GOYAL |
View Order |
09-Oct-2024 |
| 09-Aug-2024 |
FIRST HEARING |
None
is present on behalf of the promoter. One more and final opportunity is being
given to the promoter to put appearance and apprise status of project.
The
matter to come up on 13.09.2024.
|
VIJAY KUMAR GOYAL |
View Order |
27-Aug-2024 |