| 29-Jan-2025 |
PENDING |
|
|
--- |
--- |
| 11-Dec-2024 |
PENDING |
Due to some administrative exigencies, the hearing in the matter could not be conducted. Therefore, the matter is adjourned and fixed for 29.01.2025.
|
VIJAY KUMAR GOYAL |
View Order |
10-Jan-2025 |
| 06-Nov-2024 |
PENDING |
Sh.
Mohd. Hissamuddin (Manager Compliance), Sh. Geetansh Nagpal (Advocate) and Sh.
Rishi Kapoor (Advocate) are present on behalf of the promoter.
Sh.
Sonu Kumar (AR) is present on behalf of the promoter.
The
AR of the promoter stated that they had applied for extension of registration
of the project and file is under consideration of the Authority. Further,
states that the completion certificate has also been obtained vide memo no.
LC-4241/JE(SK)/2024/29345 dated 17.09.2024 copy of which has been submitted
today.
The
matter to come up on 11.12.2024.
|
VIJAY KUMAR GOYAL |
View Order |
10-Dec-2024 |
| 27-Sep-2024 |
PENDING |
None
is present on behalf of the promoter.
However,
it is noticed that the extension has already applied and under consideration of
the Authority.
In
view of the same the matter to come up on 06.11.2024.
|
VIJAY KUMAR GOYAL |
View Order |
09-Oct-2024 |
| 09-Aug-2024 |
FIRST HEARING |
Sh.
Mohd. Hissamuddin (Manager Compliance) is present on behalf of the promoter.
The
AR of the promoter states that after completion of development works CC has
been applied and expected within 2-3 months. Further extension also applied
for the project. The matter to come up on 27.09.2024.
|
VIJAY KUMAR GOYAL |
View Order |
27-Aug-2024 |