| 18-Jul-2024 |
FIRST HEARING |
Ar. Neeraj Gautam (Associate Architectural Executive)
briefed the facts of the case.
Sh. Rishabh Goel, Sh. Amit Kumuth, Sh. Venkesh Singh
and Ms. Surabhi Kapoor appeared on behalf of the promoter and state that the
promoter had submitted the application for approval of service plans and estimates
to HSVP on 09.02.2024 and diligently followed up with the concerned department.
On 07.05.2024, HSVP informed the observations on the initial submission and directed
the promoter to make requisite corrections. The revised drawings were submitted
to HSVP on 30.05.2024. Further, as per LOI dated 07.06.2023, the promoter was
required to submit a bank guarantee equivalent to 25% of internal development
works. i.e., 119.609 lakhs which was submitted to DTCP on 26.06.2023. A letter
dated 10.07.2024 was received from DTCP to submit the additional bank guarantee
of Rs. 196.6335 lakhs in lieu of increase in estimated cost of IDW.
Accordingly, the bank guarantee amounting to Rs. 196.6335 lakhs was submitted
to DTCP on 15.07.2024.
The AR of the promoter further states that a lot of
time was lost due to Lok Sabha elections and Model Code of Conduct implemented
on 16.03.2024.
The AR of the promoter seeks 30 days’ time to submit
the approval of service plans and estimates and requests the Authority not to
forfeit the security amount and/or levy any penalty on the promoter.
However,
it is not disputed that the promoter was granted conditional registration at
its own accord and depositing of security amount in the form of bank guarantee
in lieu of submission of the requisite clearances within the time specified in
the conditional registration. It was clearly mentioned in the registration
certificate that these bank guarantees shall be forfeited in case the
conditions are not fulfilled by the promoter within the stipulated time period
mentioned in the conditions.
Keeping
in view the above, the security amount submitted on account of timely
submission of approved service plans
& estimates is hereby forfieted.
The promoter is directed to submit the approved service
plans and estimates in the Authority within a period of 30 days failing which
legal consequences shall follow.
The matter to come up on 22.08.2024. Detailed order shall
follow. |