| 12-May-2025 |
DISPOSED |
Ms. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Rishabh Jain (Advocate) is present on behalf of
the promoter.
The approval of service plans and estimates dated 25.10.2023 was already submitted by the promoter with a delay of 52 days. The
security amount of Rs. 25 lakhs deposited by the promoter on account of the
timely submission of approved service plans & estimates already stands
forfeited vide order dated 22.08.2024. The promoter has now submitted the
approval of electrification plan dated 06.05.2025 with a delay of 611 days and
no security amount was required to be submitted on account of timely submission
of the same.
Since the compliance has now been made by the
promoter, although with a delay, the case is filed. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN |
View Order |
06-Jun-2025 |
| 07-Apr-2025 |
PENDING |
Ms. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Rishabh Jain (Advocate) is present on behalf of
the promoter and seeks more time to submit the collaboration agreement
regarding arrangement for providing electricity with M/s Silverglades
Infrastructure Pvt. Ltd. duly acknowledged by DHBVN.
The matter to come up on 12.05.2025. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN |
View Order |
06-Jun-2025 |
| 06-Mar-2025 |
PENDING |
Ms. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Rishabh
Jain (Advocate) appeared on behalf of the promoter states that they have
entered into an irrevocable agreement with M/s Silverglades Infrastructure Pvt.
Ltd. on 06.02.2025 for arrangement of electricity in the said project.
It is observed that the said arrangement has not
been ratified/ approved by DHBVN. The AR of the promoter states that the matter
is pending before DHBVN for their approval.
The AR of the promoter is directed to submit the
above collaboration agreement executed with M/s Silverglades Infrastructure
Pvt. Ltd., duly approved by DHBVN.
Matter to come up on 07.04.2025. |
ASHOK SANGWAN |
View Order |
06-Jun-2025 |
| 10-Oct-2024 |
PENDING |
The matter is adjourned to 06.03.2025. |
ASHOK SANGWAN |
--- |
--- |
| 26-Sep-2024 |
PENDING |
Matter is adjourned to 10.10.2024. |
ASHOK SANGWAN |
--- |
--- |
| 22-Aug-2024 |
FIRST HEARING |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts
of the case.
Sh. Rishabh Jain (Advocate) appeared on behalf of
the promoter and requested for delay condonation and 45 days’ time to submit
the electrical load availability connection.
However, it
is not disputed that the promoter was granted conditional registration at its
own accord and depositing of security amount in the form of bank guarantee in
lieu of submission of the requisite clearances within the time specified in the
conditional registration. It was clearly mentioned in the registration
certificate that this bank guarantee shall be forfeited by the Authority in
case the promoter fails to submit the above approvals within the stipulated
time.
Further, the Authority, in its meeting dated 01.01.2024 decided that
the compliances by the promoters must be made without fail within the timeline
of conditional registration failing which the BG/ security be forfeited and
further action be initiated as per the provisions of the Act of 2016.
Keeping
in view the fact that the approval is service plans and estimates is obtained
with a delay of 22 days, the bank guarantee submitted by the promoter in lieu
of timely submission of service plans and estimates is hereby forfeited. The
promoter is directed to submit the approved electrical load availability
connection within a period of one month failing which legal consequences may
follow.
The
matter to come up for review on 26.09.2024. Detailed order shall follow. |
ASHOK SANGWAN |
View Order |
23-Aug-2024 |