| 18-Jul-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate Architectural Executive)
briefed the facts of the case.
Sh. Abhijeet Singh and Sh. Bharat Vigmal (AR)
appeared on behalf of the promoter and request for condonation of delay on the
ground that the bank guarantee amount to Rs. 2.04 crores for release of service
plans and estimates was deposited to the DTCP on 09.03.2023 against the
approval from Chief Engineer GMDA, Gurugram dated 16.12.2022, however, the
final approval of service plans and estimates was granted on 09.02.2024.
It
is not disputed that the promoter was granted conditional registration at its
own accord and depositing of security amount in lieu of submission of the
requisite clearances within the time specified in the conditional registration.
It was clearly mentioned in the registration certificate that these bank
guarantees shall be forfeited in case the conditions are not fulfilled by the
promoter within the stipulated time period mentioned in the conditions.
Keeping
in view the above, the security amount submitted on account of timely
submission of service plans and
estimates is hereby forfeited.
Since the promoter has now complied with the conditions
mentioned in the registration certificate, the case is filed. |