| 06-Jun-2024 |
DISPOSED |
Ar. Neeraj Gautam
(Associate Architectural Executive) briefed the facts of the case.
Sh. Rishi Gupta (AR) is
present on behalf of the promoter. The AR of the promoter requests for the
condonation of delay.
However, it is not disputed that the promoter was
granted conditional registration at its own accord and depositing of security
amount in the form of cheque in lieu of submission of the requisite clearances
within the time specified in the conditional registration. It was clearly
mentioned in the registration certificate that this guarantee shall be
forfeited by the Authority in case the promoter fails to submit the approved
service plans and estimates within the stipulated time.
In view of the fact that the promoter has failed to
submit the approval of service plans and estimates, and
fire scheme within the specified timeline of three months as per conditions of
the registration certificate no. 667/399/2023/11 dated 16.01.2023, the security
deposited by the promoter in lieu of the timely submission of the above
approvals is hereby forfeited.
The matter stands disposed of. Detailed order shall
follow. |
ASHOK SANGWAN |
View Order |
06-Jun-2024 |