Comprehensive Complaint Details
Complaint Detail:RERA-GRG-62-2024
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA THROUGH ASHA V/S
RMG DEVELOPERS PVT. LTD
Self GURUGRAM PENDING 04-Mar-2024 Not Yet Regarding Forensic Audit of the project. --
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
04-Mar-2024 PENDING --- ---
07-Feb-2024 PENDING Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the proiect.Sh. Lokesh Kumar(Counsel) is present on behalf of the promoter.Sh. Amit Gulati S/o Sh. Harvinder Pal Gulati (complainant) is present.The Authority observes that ever since the project was registered vide RC No. 206 of 2017 dated 15.09.2017, no QPR and 4(2) (I) (D) report has been filed by the promoter. It has also been brought to the notice of the Authority that as per the audited balance sheet of the promoter which is as on 31.03.2019, the statutory auditor of the company has pointed out that the promoter has violated the provisions of section 185 of the companies act and has given loans of Rs. 68.53 crore to its sister concerns without any repayment plan and further a sum of Rs. 25.39 crore is outstanding towards income tax demand. This raises doubts about the financial integrity of the project. In view of the above, the Authority deems it fit to order a forensic audit of the project. The Authority hereby directs the promoter to submit audited balance sheet of the project as on 31.03.2023 and all the previous balance sheets of the project within a period of two weeks. The promoter is further directed to submit all relevant documents and cooperate with the forensic auditor appointed by the Authority as and when required. The cost of the forensic audit shall be borne by the promoter.The matter to come up on 04.03.2024. ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN View Order 20-Feb-2024
05-Feb-2024 FIRST HEARING REGARDING FORENSIC AUDIT OF THE PROJECT. ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA --- ---
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
66027 07/02/2024 LOKESH KUMAR ADV REGARDING SHOW-CAUSE NOTICE PERTAINING TO SOU-MOTO COMPLAINT NO.- 62-2024.
64182 04/01/2024 ASHA NEW COMPLAINT