Comprehensive Complaint Details
Complaint Detail:RERA-GRG-3887-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA THROUGH NEERAJ GAUTAM V/S
AVIANA GREENS ESTATES PVT LTD
Self GURUGRAM PENDING 01-Mar-2024 Yes 21-Aug-2023 EH733094870IN NOTICE DISPATCHED TO THE RESPONDENT NON COMPLIANCE OF RC CONDITIONS
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice NOTICE DISPATCHED TO THE RESPONDENT 21-Aug-2023 EH733094870IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
01-Mar-2024 PENDING --- ---
02-Feb-2024 PENDING AR. NEERAJ GAUTAM ASSOCIATE ARCHITECTURAL EXECUTIVE BRIEFED THE FACTS OF THE CASE. SH. VIKRANT KAMBOJ GM OPERATIONS IS PRESENT ON BEHALF OF THE PROMOTER. IN VIEW OF THE FACT THAT THE PROMOTER HAS FAILED TO SUBMIT THE APPROVAL OF ENVIRONMENTAL CLEARANCE FIRE SCHEME AND SERVICE PLANS AND ESTIMATES WITHIN THE SPECIFIED TIMELINE OF THREE MONTHS AS PER CONDITIONS OF THE REGISTRATION CERTIFICATE DATED 30.01.2023 THE SECURITY DEPOSITED BY THE PROMOTER IN LIEU OF THE TIMELY SUBMISSION OF ALL THE ABOVE APPROVALS IS HEREBY FORFEITED. THE PROMOTER IS FURTHER DIRECTED TO SUBMIT THE APPROVAL FROM THE COMPETENT AUTHORITY WITHIN A PERIOD OF ONE MONTH FAILING WHICH LEGAL CONSEQUENCES INCLUDING BUT NOT RESTRICTED TO FREEZING OF BANK ACCOUNTS AND RESTRICTION FOR CREATING ANY FURTHER THIRD-PARTY RIGHTS SHALL FOLLOW. MATTER TO COME UP ON 01.03.2024. ASHOK SANGWAN View Order 12-Feb-2024
29-Dec-2023 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case.   One last opportunity is given to the promoter to submit the approved service plans and estimates in the Authority. Matter to come up on 02.02.2024. ASHOK SANGWAN --- ---
28-Dec-2023 PENDING Matter adjourned to 29.12.2023 ASHOK SANGWAN SANJEEV KUMAR ARORA --- ---
23-Nov-2023 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case.  None is present on behalf of the promoter. None is present on behalf of the promoter. A final opportunity is granted for submitting the above compliance subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 28.12.2023 for further proceedings. ASHOK SANGWAN View Order 24-Nov-2023
26-Oct-2023 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case.  None is present on behalf of the promoter. One opportunity is granted for submitting the above compliance subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 23.11.2023 for further proceedings. ASHOK SANGWAN View Order 31-Oct-2023
21-Sep-2023 FIRST HEARING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case.  Sh. Vikrant (AR) is present on behalf of the promoter. The AR of the promoter states that the assurance for electrical load was granted by DHBVN on 31.01.2023 (within stipulated time) and a copy of the same has been handed over during course of hearing. So far as the service plans and estimates are concerned, the same have been forwarded by HSVP, Panchkula to the DTCP on 13.04.2023 and are pending at the level of DTCP. He seeks one month time to comply with this condition. One opportunity is granted for submitting the above compliance subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate.   The matter to come up on 26.10.2023. ASHOK SANGWAN View Order 25-Sep-2023
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
114058 13/07/2026 BHEEM SINGH REQUEST FOR CLOSURE OF NON COMPLIANCE OF CONDITIONS OF REGISTRATION CERTIFICATE 19 OF 2023 DATED 30.01.2023 FOR PROJECT "CHINTAMANI'S"
57757 24/08/2023 HARERA THROGH NEERAJ GAUTAM NEW COMPLAINT