| 02-Feb-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashish Drall (AR) and
Sh. Pankaj Sharma (AR) are present on behalf of the promoter and state that the
final approval of service plan and estimates has been received from DTCP vide
memo dated 22.01.2024.
Since the approval of
service plans estimates is obtained with a delay of 146 days from the
stipulated time period, the security deposited by the promoter in lieu of the
timely submission of the above approval is hereby forfeited.
The security amount of Rs.25
lacs submitted on account of timely submission of fire scheme approval be
refunded to the promoter as the same is obtained by the promoter within the
stipulated time period.
The approvals are placed on
record. The matter is disposed of. |
ASHOK SANGWAN |
View Order |
12-Feb-2024 |
| 19-Jan-2024 |
PENDING |
THE MATTER IS ADJOURNED TO 02.02.2024. |
ASHOK SANGWAN |
View Order |
23-Jan-2024 |
| 15-Dec-2023 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashish Drall (AR) and
Sh. Pankaj Sharma (AR) are present on behalf of the promoter.
The AR of the promoter
states that they have received the demand letter for bank guarantees to be
submitted in the Department of Town and Country Planning, Haryana for the
approval of service plans and estimates. The AR of the promoter seeks one
month’s time to submit the approval in the Authority.
The AR of the promoter is
directed to submit the copy of bank guarantee as and when it is submitted with
the DTCP.
Matter to come up on 19.01.2024 |
ASHOK SANGWAN |
View Order |
20-Dec-2023 |
| 07-Dec-2023 |
PENDING |
THE MATTER TO COME UP ON 15.12.2023 |
ASHOK SANGWAN |
View Order |
12-Dec-2023 |
| 10-Nov-2023 |
PENDING |
THE MATTER TO COME UP ON 07.12.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
20-Nov-2023 |
| 27-Oct-2023 |
PENDING |
THE MATTER TO COME UP ON 10.11.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
02-Nov-2023 |
| 22-Sep-2023 |
FIRST HEARING |
Proceedings dated 22.09.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashish Drall (AR) and
Sh. Pankaj Sharma (AR) are present on behalf of the promoter.
One opportunity of thirty
days is granted for submitting the above compliance subject to the final
decision of the Authority regarding delay in submission of compliance in terms
of the registration certificate.
Matter to come up on 27.10.2023 for further proceedings. |
ASHOK SANGWAN |
View Order |
29-Sep-2023 |