| 19-Feb-2024 |
PENDING |
|
|
View Order |
19-Feb-2024 |
| 16-Feb-2024 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Vipul Kumar Dahiya (AR)
is present on behalf of the promoter.
The AR of the promoter seeks
two weeks’ time to deposit the bank guarantee with the DTCP. However, the
matter being similar to other cases in sector- 05, Sohna, the same may be
placed before the Authority for taking a view in the matter.
The matter to come up on 19.02.2024. |
ASHOK SANGWAN |
--- |
--- |
| 12-Jan-2024 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Vipul Kumar Dahiya (AR) is
present on behalf of the promoter.
The AR of the promoter states that
the promoter will deposit the bank guarantee mentioned in DTCP memo dated
17.07.2023 within a period of one month to the DTCP for approval of service
plans and estimates and an undertaking to this effect has also been submitted
in the Authority. The AR of the promoter requests for one month time to submit
the compliance in the Authority.
One final opportunity is granted to
the promoter for submitting the above compliance subject to the final decision
of the Authority regarding delay in submission of compliance in terms of the
registration certificate.
The matter to come up on 16.02.2024. |
ASHOK SANGWAN |
View Order |
12-Jan-2024 |
| 15-Dec-2023 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Vipul Kumar Dahiya (AR) is
present on behalf of the promoter.
It is noted that the BG of Rs. 188.39
lacs has been sought by the DTCP on account of internal development works for
the approval of service plans and estimates vide DTCP memo no.
LC-4834/JE(DS)/2023/23321 dated 17.07.2023, a copy of which is placed in file.
However, the promoter has submitted in its reply dated 02.11.2023 that DTCP had
not provided them the information pertaining to road levels, sewer systems and
water supply lines to enable them to align the services with the current status
of these components.
A letter dated 07.12.2023 seeking
confirmation of this fact submitted by the promoter has been written to DTCP by
this Authority and the reply is still awaited.
The promoter is directed to clarify
the status of the approval of service plans and estimates from DTCP within one week.
If the facts submitted by the promoter are found to be false, the promoter
shall be liable to punitive actions against him.
The matter to come up on 12.01.2024. |
ASHOK SANGWAN |
View Order |
20-Dec-2023 |
| 07-Dec-2023 |
PENDING |
THE MATTER TO COME UP ON 15.12.2023 |
ASHOK SANGWAN |
View Order |
12-Dec-2023 |
| 10-Nov-2023 |
PENDING |
THE MATTER TO COME UP ON 07.12.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
20-Nov-2023 |
| 27-Oct-2023 |
PENDING |
THE MATTER TO COME UP ON 10.11.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
02-Nov-2023 |
| 22-Sep-2023 |
FIRST HEARING |
Proceedings dated 22.09.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Vipul Kumar Dahiya (AR) is
present on behalf of the promoter.
The AR of the promoter seeks
60 days’ time to submit the compliance of the conditions imposed.
One opportunity of thirty
days is granted for submitting the above compliance subject to the final
decision of the Authority regarding delay in submission of compliance in terms
of the registration certificate.
Matter to come up on 27.10.2023 for further
proceedings. |
ASHOK SANGWAN |
View Order |
29-Sep-2023 |