22-Mar-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashish Drall (Sr.
General Manager) and Sh. Pankaj Sharma (AR) are present on behalf of the
promoter.
The security amount already stands
forfeited. Compliance has been made.
The matter be filed. |
ASHOK SANGWAN |
--- |
--- |
01-Mar-2024 |
PENDING |
MATTER TO
COME UP ON 22.03.2024. |
ASHOK SANGWAN |
View Order |
19-Mar-2024 |
02-Feb-2024 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashish Drall (AR) and
Sh. Pankaj Sharma (AR) are present on behalf of the promoter and state that the
letter dated 31.01.2024 has been received from DTCP for deposit of BG amounting
to Rs. 1.61 Cr has been deposited with DTCP and seeks one month’s time to
submit approval letter.
In view of the fact that the
promoter has failed to submit the approval of service plans and estimates
within the specified timeline of three months as per conditions of the
registration certificate dated 23.05.2023, the security deposited by the
promoter in lieu of the timely submission of the above approval is hereby
forfeited.
Matter to
come up on 01.03.2024. |
ASHOK SANGWAN |
View Order |
12-Feb-2024 |
19-Jan-2024 |
PENDING |
THE MATTER IS ADJOURNED TO 02.02.2024. |
ASHOK SANGWAN |
View Order |
23-Jan-2024 |
15-Dec-2023 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashish Drall (AR) and Sh. Pankaj
Sharma (AR) are present on behalf of the promoter.
The AR of the promoter states that
they have received the demand letter for bank guarantees to be submitted in the
Department of Town and Country Planning, Haryana for the approval of service
plans and estimates. The AR of the promoter seeks one month’s time to submit
the approval in the Authority.
The AR of the promoter is directed to
submit the copy of bank guarantee as and when it is submitted with the DTCP.
Matter to come up on 19.01.2024 |
ASHOK SANGWAN |
View Order |
20-Dec-2023 |
07-Dec-2023 |
PENDING |
THE MATTER TO COME UP ON 15.12.2023 |
ASHOK SANGWAN |
View Order |
12-Dec-2023 |
10-Nov-2023 |
PENDING |
THE MATTER TO COME UP ON 07.12.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
20-Nov-2023 |
27-Oct-2023 |
PENDING |
THE MATTER TO COME UP ON 10.11.2023 AT 11:30 AM |
ASHOK SANGWAN |
View Order |
02-Nov-2023 |
22-Sep-2023 |
FIRST HEARING |
Proceedings dated 22.09.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Ashish Drall (AR) and
Sh. Pankaj Sharma (AR) are present on behalf of the promoter.
One opportunity of thirty
days is granted for submitting the above compliance subject to the final
decision of the Authority regarding delay in submission of compliance in terms
of the registration certificate.
Matter to come up on 27.10.2023 for further
proceedings. |
ASHOK SANGWAN |
View Order |
29-Sep-2023 |