| Party Dtls | Self / Adv Name | District | Current Status | Next Date of Hearing | Complaint Dispatched | Complaint Dispatched On | Dispatched Tracking Id | Complaint Dispatched Remarks | First-Hearing/Scrutinized Remarks | View Notice |
|---|---|---|---|---|---|---|---|---|---|---|
| HARERA THROUGH NEERAJ GAUTAM V/S ADANI BRAHMA SYNERGY PVT LTD |
Self | GURUGRAM | DISPOSED | NOT REQUIRED | Yes | 21-Aug-2023 | EH733094968IN | NOTICE DISPATCHED TO THE RESPONDENT | NON COMPLIANCE OF RC CONDITIONS |
| Notice Number | Remarks | Dispatching Date | Dispatch Id | View Notice |
|---|---|---|---|---|
| First Notice | NOTICE DISPATCHED TO THE RESPONDENT | 21-Aug-2023 | EH733094968IN |
| Date of Hearing | Status | Proceedings of the day | Bench | Order | Order Uploaded On |
|---|---|---|---|---|---|
| 22-Mar-2024 | DISPOSED | THE CASE IS FILED. | ASHOK SANGWAN | View Order | 30-Oct-2025 |
| 29-Feb-2024 | PENDING | Matter is adjourned to 22.03.2024. | ASHOK SANGWAN | View Order | 19-Mar-2024 |
| 24-Nov-2023 | PENDING | Proceedings dated 24.11.2023 Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. The Authority is in the process of framing guidelines/Regulation to deal with cases of delayed compliance. The above matter shall be dealt according to the decision of the Authority in this regard. Till then, the proceedings may be kept pending. The matter to come up on 29.02.2024. | ASHOK SANGWAN | View Order | 28-Nov-2023 |
| 22-Sep-2023 | FIRST HEARING | Proceedings dated 22.09.2023 Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Atul Jain (AR), Sh. Praveen Kumar (AR) and Sh. Vijay Singh (AR) are present on behalf of the promoter and seek two months’ time to comply with the condition which could not have been complied due to constraints imposed by the RBI Policy guidelines. One opportunity is granted for submitting the above compliance subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 24.11.2023 for further proceedings. | ASHOK SANGWAN | View Order | 29-Sep-2023 |
| Date of Judgement | Party Details | Judgement Uploading Date | View Judgement |
|---|---|---|---|
| 22-Mar-2024 | HARERA THROUGH NEERAJ GAUTAM V/S ADANI BRAHMA SYNERGY PVT LTD |
--- | --- |
| Dak ID | Receiving Date | Submitted By | Remarks |
|---|---|---|---|
| 57363 | 16/08/2023 | HARERA THROUGH NEERAJ GAUTAM | NEW COMPLAINT |
| 59042 | 22/09/2023 | VIJAY SINGH | REPLY TO SHOW-CAUSE NOTICE- 3866-2023, DATED: 21.08.2023. |
| 61322 | 03/11/2023 | VIJAY SINGH | REPLY TO SHOW-CAUSE NOTICE - 3866-2023, DATED: 21.08.2023. |