| 22-Mar-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Virender Dhar (VP),
Jitendra Kumar (AR) and Rahul Johari (AR) are present on behalf of the
promoter.
The security for service
plans and estimates already stands forfeited. The security amount submitted in
lieu of filing of QPRs be refunded as the compliance has been made by the
promoter within the stipulated time period.
The matter is disposed of. |
ASHOK SANGWAN |
--- |
--- |
| 02-Feb-2024 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Jitender Kumar (AR) and
Sh. Rahul Johari (AR) are present on behalf of the promoter and states that the
BG of Rs. 69,72,250/- has been deposited with DTCP on 31.01.2024 against the
demand letter dated 11.04.2023 and final approval is awaited.
In view of the fact that the
promoter has failed to submit the approval of service plans and estimates
within the specified timeline of three months as per conditions of the
registration certificate dated 30.01.2023, the security deposited by the
promoter in lieu of the timely submission of the above approval is hereby
forfeited.
The promoter is further
directed to submit the approval from the competent authority within a period of
one month.
Matter to come up on 22.03.2024. |
ASHOK SANGWAN |
View Order |
12-Feb-2024 |
| 29-Dec-2023 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Jitender Kumar (AR) and
Sh. Rahul Johari (AR) are present on behalf of the promoter.
The AR of the promoter requests more time to
submit the approval of service plans and estimates in the Authority.
One more opportunity is granted for
submitting the above compliance subject to the final decision of the Authority
regarding delay in submission of compliance in terms of the registration
certificate.
Matter to come up on 02.02.2024 |
ASHOK SANGWAN |
--- |
--- |
| 28-Dec-2023 |
PENDING |
Matter adjourned to 29.12.2023 |
ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 23-Nov-2023 |
PENDING |
Proceedings dated 23.11.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Jitender Kumar (AR) and Sh. Rahul Johari
(AR) are present on behalf of the promoter.
The AR of the promoter
states that the DTCP has granted the approval for availing benefit of “Samadhan
se Vikas” to the promoter for the license pertaining to this project vide memo
dated 22.11.2023. the AR further states that the service plans and estimates
are in the final stage of approval and the same will be obtained shortly. The
AR of the promoter requests more time to submit the approval of service plans
and estimates in the Authority.
A final opportunity is granted for submitting the
above compliance subject to the final decision of the Authority regarding delay
in submission of compliance in terms of the registration certificate.
Matter to come up on 28.12.2023 for further
proceedings. |
ASHOK SANGWAN |
View Order |
24-Nov-2023 |
| 26-Oct-2023 |
PENDING |
Proceedings dated 26.10.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
None is present on behalf of the
promoter.
One final opportunity is granted for submitting the
above compliance subject to the final decision of the Authority regarding delay
in submission of compliance in terms of the registration certificate.
The matter to come up on 23.11.2023 for further
proceedings. |
ASHOK SANGWAN |
View Order |
31-Oct-2023 |
| 21-Sep-2023 |
FIRST HEARING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Virender Dhar (AR) is
present on behalf of the promoter.
The AR of the promoter seeks
one month time to submit the approval of service plans and estimates. One
opportunity is granted for submitting the above compliance subject to the final
decision of the Authority regarding delay in submission of compliance in terms
of the registration certificate.
The matter to come up on 26.10.2023. |
ASHOK SANGWAN |
View Order |
25-Sep-2023 |