Comprehensive Complaint Details
Complaint Detail:RERA-GRG-3819-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA THROUGH NEERAJ GAUTAM V/S
LOON LAND DEVELOPMENT LIMITED
Self GURUGRAM PENDING 01-Jan-2024 Yes 21-Aug-2023 EH733094764IN NOTICE DISPATCHED TO THE RESPONDENT NON COMPLIANCE OF RC CONDITIONS
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice NOTICE DISPATCHED TO THE RESPONDENT 21-Aug-2023 EH733094764IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
01-Jan-2024 PENDING --- ---
15-Dec-2023 PENDING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Bharat Vigmal (AR), Sh. Manik Sharma (AR) and Sh. Abhijeet Singh (AR) are present on behalf of the promoter. The AR of the promoter submits that the license no. 195 of 2022 dated 29.11.2022 was granted to Ajay Pal and others in collaboration with Loon Land Development Ltd. With a condition that 12.46555 acres land will remain freezed for the purpose of sale of plots till the said land is either purchased by the developer or collaboration agreement with the land owners is registered. The same condition was imposed in the RERA registration certificate of the project and the 12.46555 acres land was marked in the approved layout and zoning plan also. The AR further submits that the DTCP has issued revised land schedule of 24.74375 to be read with the license no. 195 of 2022 and accordingly the revised layout plan and zoning plan has also been approved. The promoter has applied for supersession of earlier granted registration no. 05 of 2023 in the Authority on 12.12.2023. This suo motu complaint no. RERA-GRG-3819-2023 along with suo- motu complaint no. RERA-GRG-3818-2023 shall be clubbed with the matter of supersession of registration certificate. The matter to come up on 01.01.2024. ASHOK SANGWAN View Order 20-Dec-2023
07-Dec-2023 PENDING THE MATTER TO COME UP ON 15.12.2023. ASHOK SANGWAN View Order 12-Dec-2023
26-Oct-2023 PENDING Proceedings dated 26.10.2023 Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Bharat Vigmal (AR) and Sh. Abhijeet Singh (AR) are present on behalf of the promoter. The AR of the promoter states that the service plans and estimates are pending at the level of DTCP and shall certainly be submitted within a period of one month. One final opportunity is granted for submission of approved service plans and estimates subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 07.12.2023. ASHOK SANGWAN View Order 31-Oct-2023
21-Sep-2023 FIRST HEARING Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Abhijeet Singh (AR) and Sh. Bharat Vigmal (AR) are present on behalf of the promoter. The AR of the promoter seeks one month time to submit the compliance of the conditions imposed. One opportunity is granted for submitting the above compliance subject to the final decision of the Authority regarding delay in submission of compliance in terms of the registration certificate. Matter to come up on 26.10.2023 for further proceedings. ASHOK SANGWAN View Order 25-Sep-2023
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
57346 16/08/2023 HARERA THROUGH NEERAJ GAUTAM NEW COMPLAINT
58759 18/09/2023 BHARAT VIGMAL REPLY TO SHOW-CAUSE NOTICE- 3819-2023, DATED: 21.08.2023.
63157 12/12/2023 BHARAT VIGMAL REQUEST FOR DEFERMENT OF HEARING FOR SOU-MOTO COMPLAINT- 3819-2023.