| 01-Jan-2024 |
PENDING |
|
|
--- |
--- |
| 15-Dec-2023 |
PENDING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Bharat Vigmal (AR), Sh.
Manik Sharma (AR) and Sh. Abhijeet Singh (AR) are present on behalf of the
promoter.
The AR of the promoter
submits that the license no. 195 of 2022 dated 29.11.2022 was granted to Ajay
Pal and others in collaboration with Loon Land Development Ltd. With a
condition that 12.46555 acres land will remain freezed for the purpose of sale
of plots till the said land is either purchased by the developer or
collaboration agreement with the land owners is registered. The same condition
was imposed in the RERA registration certificate of the project and the
12.46555 acres land was marked in the approved layout and zoning plan also.
The AR further submits that
the DTCP has issued revised land schedule of 24.74375 to be read with the
license no. 195 of 2022 and accordingly the revised layout plan and zoning plan
has also been approved. The promoter has applied for supersession of earlier
granted registration no. 05 of 2023 in the Authority on 12.12.2023.
This suo motu complaint no.
RERA-GRG-3818-2023 along with suo- motu complaint no. RERA-GRG-3819-2023 shall
be clubbed with the matter of supersession of registration certificate.
The matter to come up on
01.01.2024. |
ASHOK SANGWAN |
View Order |
20-Dec-2023 |
| 07-Dec-2023 |
PENDING |
MATTER TO COME
UP ON 15.12.2023. |
ASHOK SANGWAN |
View Order |
12-Dec-2023 |
| 26-Oct-2023 |
PENDING |
Proceedings dated 26.10.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Bharat Vigmal (AR) and Sh.
Abhijeet Singh (AR) are present on behalf of the promoter.
The AR of the promoter states that
the service plans and estimates are pending at the level of DTCP and shall
certainly be submitted within a period of one month. One final opportunity is granted
for submission of approved service plans and estimates subject
to the final decision of the Authority regarding delay in submission of
compliance in terms of the registration certificate.
Matter to come
up on 07.12.2023. |
ASHOK SANGWAN |
View Order |
31-Oct-2023 |
| 21-Sep-2023 |
FIRST HEARING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Abhijeet Singh (AR) and
Sh. Bharat Vigmal (AR) are present on behalf of the promoter.
The AR of the promoter seeks
one month time to submit the compliance of the conditions imposed.
One opportunity is granted
for submitting the above compliance subject to the final decision of the
Authority regarding delay in submission of compliance in terms of the
registration certificate.
Matter to come up on 26.10.2023 for further
proceedings. |
ASHOK SANGWAN |
View Order |
25-Sep-2023 |