| 22-Mar-2024 |
DISPOSED |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts
of the case. Sh. Vedant Batra (CS) and Sh. Ravinder (Executive) appeared on
behalf of the promoter. He states that the promoter had applied for the
requisite clearances on time but the delay was on the part of the concerned
department.
However, it is not disputed that the promoter was
granted conditional registration at its own accord and depositing of security
amount in the form of cheque in lieu of submission of the requisite clearances
within the time specified in the conditional registration. It was clearly
mentioned in the registration certificate that these cheques shall be forfeited
in case the conditions are not fulfilled by the promoter within the stipulated
time period mentioned in the conditions.
In view of the fact that the promoter
has failed to submit the approval of fire scheme and, service plans and
estimates within the specified timeline of three months as per conditions of
the registration certificate no.
659/391/2023/03 dated 12.01.2023, the security deposited by the promoter in lieu of the
timely submission of the above approvals is hereby forfeited.
Further, the security amount
submitted in lieu of environmental clearance shall be refunded as the promoter
had obtained the environmental clearance within the stipulated time.
The matter stands disposed of. |
ASHOK SANGWAN |
--- |
--- |
| 29-Feb-2024 |
PENDING |
Matter is adjourned to 22.03.2024. |
ASHOK SANGWAN |
View Order |
19-Mar-2024 |
| 23-Nov-2023 |
PENDING |
Proceedings dated 23.11.2023
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
The Authority is in the
process of framing guidelines/Regulation to deal with cases of delayed
compliance. The above matter shall be dealt according to the decision of the
Authority in this regard. Till then, the proceedings may be kept pending.
The matter to come up on 29.02.2024. |
ASHOK SANGWAN |
View Order |
24-Nov-2023 |
| 21-Sep-2023 |
FIRST HEARING |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
Sh. Anurag Srivastava (GM)
and Sh. Vedant Batra (CS) are present on behalf of the promoter
The Authority is in the
process of framing guidelines/Regulation to deal with cases of delayed
compliance. The above matter shall be dealt according to the decision of the
Authority in this regard. Till then, the proceedings may be kept pending.
The matter to come up on 23.11.2023. |
ASHOK SANGWAN |
View Order |
25-Sep-2023 |