Comprehensive Complaint Details
Complaint Detail:RERA-GRG-3264-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
HARERA GURUGRAM THROUGH ASHISH KUSH RC EXPIRED V/S
EMAAR MGF LAND LTD.
Self GURUGRAM PENDING 05-Feb-2024 Yes 12-Jul-2023 EH316606768IN Violation of Section 42lC First hearing on 26.07.2023 at 2 PM.
Notice Details
Notice Number Remarks Dispatching Date Dispatch Id View Notice
First Notice Violation of Section 42lC 12-Jul-2023 EH316606768IN
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
05-Feb-2024 PENDING --- ---
27-Dec-2023 PENDING The AR of the promoter stated that the application for CC is still pending with the DGTCP. The matter to come up on 05.02.2024 for further proceedings. VIJAY KUMAR GOYAL View Order 28-Dec-2023
22-Nov-2023 PENDING The AR submits that the OC has been received and application for CC is still pending with the DGTCP. The matter to come up on 27.12.2023. VIJAY KUMAR GOYAL View Order 22-Dec-2023
25-Oct-2023 PENDING Sh. Anitesh Singh (AR), Sh. Purushottam Grover (V.P) and Sh. Kulbhushan (Sr. GM) are present on behalf of the promoter. The AR of the promoter stated that the OC for all the towers has already been obtained and also uploaded on the website. Further he states that the CC is applied and submit the same after obtaining from DTCP. The matter to come up on 22.11.2023 for further proceedings. VIJAY KUMAR GOYAL View Order 16-Nov-2023
13-Sep-2023 PENDING Sh. Anitesh Singh (Sr. Manager – Govt. Affairs) is present on behalf of the promoter. The AR submits that OC in respect of all the units has already been obtained within the prescribed timeline and possession also offered/handed over to RWA and CC for the whole of the project has already been applied to DTCP and hence extension may not be insisted in such cases. The AR is given six weeks’ time for submission of CC.  The matter to come up on 25.10.2023. VIJAY KUMAR GOYAL View Order 16-Nov-2023
16-Aug-2023 PENDING Sh. Anitesh Singh (Sr. Manager – Govt. Affairs) is present on behalf of the promoter. The AR submits that OC has been received before the expiry of registration for the entire project and has already been uploaded on the website. Further, states that CC is being applied and the status of CC will be submitted within the next two weeks. The matter to come up on 13.09.2023. VIJAY KUMAR GOYAL View Order 18-Aug-2023
26-Jul-2023 FIRST HEARING Sh. Anitesh Singh (Sr. Manager- Govt. affairs) is present on behalf of the promoter. The AR of the promoter states that OC in respect of construction and sold units have been received and handed over to the allottees. Reply will be filed within 2 weeks. The matter to come up on 16.08.2023. VIJAY KUMAR GOYAL View Order 09-Aug-2023
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
56169 20/07/2023 ANITESH SINGH REPLY TO SHOW-CAUSE NOTICE OF 4(2)(L)(C)- 3264-2023, DATED: 11.07.2023.
58132 01/09/2023 ANITESH SINGH REPLY TO SHOW-CAUSE NOTICE OF 4(2)(L)(C)- 3264-2023, DATED: 11.07.2023.
55527 11/07/2023 ASHISH NEW COMPLAINT