| 22-Nov-2023 |
PENDING |
|
|
View Order |
22-Dec-2023 |
| 25-Oct-2023 |
PENDING |
The
AR of the promoter requested telephonically that they are unable to attend
the hearing and requested for the short adjournment.
The
matter to come up on 22.11.2023 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
16-Nov-2023 |
| 11-Oct-2023 |
PENDING |
The AR submits that the OC for all the units
has been received before expiry of the Registration Certificate and units
already offered/handed over to the allottees. The status pertaining to
obtaining of CC will be filed within one week.
The matter to come up on 25.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 13-Sep-2023 |
PENDING |
None is present on behalf of the promoter.
The promoter has requested telephonically for
four weeks adjournment and has further informed that OC in respect of the
project has already been received and also uploaded on the website of the
Authority.
The matter to come up on 11.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
16-Nov-2023 |
| 16-Aug-2023 |
PENDING |
None is present on behalf of the promoter.
The Reply has been received intimating that the OC
has been received before expiry of registration of the project but the status
of obtaining CC is not clear. One more opportunity is being given.
The matter to come up on 13.09.2023.
|
VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
18-Aug-2023 |
| 26-Jul-2023 |
FIRST HEARING |
Adv. Priyanka Agarwal is present on behalf of
the promoter. The AR seeks two weeks time to file the reply as OC of all the
units has been obtained in the year 2022 and shall be filing its copy in the
Authority.
The matter to come up on 16.08.2023.
|
VIJAY KUMAR GOYAL |
View Order |
09-Aug-2023 |