| 25-Oct-2023 |
PENDING |
|
|
View Order |
16-Nov-2023 |
| 06-Oct-2023 |
PENDING |
The AR of the promoter stated that they have
applied for extension. But it is not accordance with the requirement of the
application for registration. Therefore, the application is return with the
directions to submit complete file alongwith the requisite fee failing which
further penal action shall be initiated.
The matter to come up on 25.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 08-Sep-2023 |
PENDING |
The AR could not travel due to traffic
restriction in view of the G20 conference.
The matter to come up on 06.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 16-Aug-2023 |
PENDING |
Sh. Parshant Gupta (A.G.M) is present on behalf
of the promoter.
The AR of the promoter submits that OC in
respect of whole project has already been received and a copy has been
attached with the reply which be uploaded on the website. Further, they have
applied for grant of CC to DGTCP and also applying for extension within 2
weeks.
The matter to come up on 08.09.2023.
|
VIJAY KUMAR GOYAL |
View Order |
18-Aug-2023 |
| 26-Jul-2023 |
FIRST HEARING |
Sh. Parshant Gupta (A.G.M) is present on behalf
of the promoter. The AR of the promoter states that OC for all the units has
been received in 2019 and Deed of Declaration also filed. The AR of the
promoter stated that all the construction work is completed and seeks 4 weeks’
time for applying for extension required till obtaining CC.
The matter to come up on 16.08.2023.
|
VIJAY KUMAR GOYAL |
View Order |
09-Aug-2023 |