| 05-Feb-2024 |
PENDING |
|
|
--- |
--- |
| 27-Dec-2023 |
PENDING |
The
AR of the promoter stated that they have applied for the extension of the
registration on 14.12.2023 which is under consideration of the Authority. The
matter to come up on 05.02.2024 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
28-Dec-2023 |
| 22-Nov-2023 |
PENDING |
The AR submits that the
application for seeking renewal has been prepared but could not be applied
till date due to some technical glitch on the HAERA Website as the copies of
the DPI are not getting downloaded after filling up. The renewal application
shall be made within this week. The AR also clarified that the structure work
is complete and MEP work is in progress and will be completed within one year.
In view of the same the matter to come
up on 27.12.2023.
|
VIJAY KUMAR GOYAL |
View Order |
22-Dec-2023 |
| 25-Oct-2023 |
PENDING |
Sh.
Avinash (AR) is present on behalf of the promoter. The AR of the promoter
stated that the license is expired and the same is applied for renewal.
Further the AR requests for three weeks’ time to apply for extension of the
registration failing which the Public notice be issued in the newspaper for
the information of general public regarding this project. The matter to come
up on 22.11.2023 for further proceedings.
|
VIJAY KUMAR GOYAL |
View Order |
16-Nov-2023 |
| 06-Oct-2023 |
PENDING |
The AR of the promoter seeks ten days time to
apply for extension.
The matter to come up on 25.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 08-Sep-2023 |
PENDING |
The AR could not travel due to traffic
restriction in view of the G20 conference.
The matter to come up on 06.10.2023.
|
VIJAY KUMAR GOYAL |
View Order |
15-Nov-2023 |
| 16-Aug-2023 |
PENDING |
SH. AVINASH SHARMA IS PRESENT ON BEHALF OF THE
PROMOTER.
THE AR OF THE PROMOTER REQUESTS FOR ONE WEEK
MORE TIME TO APPLY FOR EXTENSION WHICH HAS ALREADY EXPIRED ON 16.02.2023. THE
AR FURTHER CLARIFY THAT 70 OF THE WORK IS COMPLETED AND REMAINING WORK IS
LIKELY TO BE COMPLETED IN ABOUT ONE MORE YEAR AND DETAILS OF THE STATUS OF
THE PROJECT WILL BE SUBMITTED ALONG WITH THE EXTENSION APPLICATION. ONE LAST
OPPORTUNITY FOR DOING THE NEEDFUL WITHIN 2 WEEKS IS GRANTED FAILING WHICH
FURTHER PROCEEDINGS UNDER SECTION 7 AND 8 OF THE ACT SHALL BE INITIATED.
THE MATTER TO COME UP ON 08.09.2023. |
VIJAY KUMAR GOYAL |
View Order |
18-Aug-2023 |
| 26-Jul-2023 |
FIRST HEARING |
Sh. Avinash Sharma is present on behalf of the
promoter. The AR of the promoter request for two weeks’ time to applying for
extension and another two weeks’ time for compliance of QPR and section
4(2)(l)(D). The request is allowed, failing which penal action shall be
initiated.
The matter to come up on 16.08.2023.
|
VIJAY KUMAR GOYAL |
View Order |
09-Aug-2023 |