09-Sep-2024 |
PENDING |
|
|
--- |
--- |
23-Aug-2024 |
PENDING |
THE MATTER TO COME UP ON 09.09.2024 |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
05-Sep-2024 |
08-Jul-2024 |
PENDING |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case.None is present on behalf of the promoter.One more opportunity is provided to the promoter to submit the approved electrical loadin the Authority within two months.The matter to come up on 23.08.2024. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
20-Aug-2024 |
22-Apr-2024 |
PENDING |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed
the facts of the case.
Sh. Sanjay Sachdeva (AR) is present on behalf of the promoter.
The AR of the promoter states that they need two months time
to submit the approval of electrical load availability from the competent
authority failing which the Authority may suspend the registration of the
project.
The matter to come up on 08.07.2024. |
ARUN KUMAR ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
15-Apr-2024 |
PENDING |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case.Sh. Sanjay Sachdeva (AR) is present on behalf of the promoter and request for one week time to submit the deficit documents.The matter to come up on 22.04.2024. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
22-Apr-2024 |
12-Feb-2024 |
PENDING |
NONE PRESENT ON BEHALF OF THE PROMOTER. THE BANK GUARANTEE SUBMITTED FOR TIMELY COMPLIANCE FOR SUBMITTING SERVICE PLANS AND ESTIMATES BE FORFIETED IN VIEW OF THE LATE SUBMISSION OF THE SAME. FURTHER, ONE MORE AND LAST OPPORTUNITY FOR SUBMISSION OF ELECTRIC LOAD AVAILABILITY IS BEING GIVEN TO THE PROMOTER WITHIN SIX WEEKS IN THE AUTHORITY.MATTER TO COME UP ON 15.04.2024. |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
05-Apr-2024 |
08-Jan-2024 |
PENDING |
Proceedings
dated 08.01.2024
Ar.
Neeraj Gautam (Associate Architectural Executive) briefed the facts of the
case.
Sh.
Prince Kumar (Sr. Manager) is present on
behalf of the promoter.
The
AR of the promoter present with the promoter states that the electrical load
availability has been received from DHBVN on 20.11.2023 and has been submitted
in the Authority on 08.01.2024.
The
present proceedings are closed. So far as the delay in submission of approved
service plans and estimates is concerned, the same shall be dealt separately. The
matter to come up on 12.02.2024 |
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
16-Jan-2024 |
04-Dec-2023 |
PENDING |
Ar.
Neeraj Gautam (Associate Architectural Executive) briefed the facts of the
case.
Sh.
Prince Kumar (AR) is present on behalf of the promoter. The AR of the promoter
seeks more time to submit the approved electrical load in the Authority.
One
final opportunity is provided to the promoter to submit the approved electrical
load in the Authority.
The
matter to come up on 08.01.2024. |
VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
26-Dec-2023 |
20-Nov-2023 |
PENDING |
Proceedings dated 20.11.2023 Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. None present on behalf of the promoter. One last opportunity is given to the promoter to submit the approved electrical load availability in the Authority before the next date of hearing. Matter to come up on 04.12.2023 for further proceedings. |
ARUN KUMAR GUPTA VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
29-Nov-2023 |
16-Oct-2023 |
PENDING |
Ar. Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case.Sh. Prince Kumar (AR) is present on behalf of the promoter. The AR seeks two weeks' timefor submission of approval of electrical load availability in the Authority.The matter to come up on 20.11.2023 |
VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
26-Oct-2023 |
18-Sep-2023 |
PENDING |
Matter to come up on 16.10.2023 for follow up. |
VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
27-Sep-2023 |
28-Aug-2023 |
PENDING |
Sh. Prince Kumar is present on behalf of the promoter. The AR of the promoter is requesting for two weeks' time to submit the required documnets. The same is allowed. The matter to come up on 18.09.2023 |
VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
18-Sep-2023 |
14-Aug-2023 |
FIRST HEARING |
The coram is not complete. therefore, the matter is adjourned to 28.08.2023. |
VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
16-Aug-2023 |