| 09-Jun-2026 |
DISPOSED |
Ar. Neeraj Gautam (Associate
Architectural Executive) briefed the facts of the case.
None appeared on behalf of the
promoter.
Order pronounced.
The Authority has carefully
considered the record of the case, the submissions made by the
Respondent–Promoter, the documents placed on record, and the directions issued
by the Hon’ble Haryana Real Estate Appellate Tribunal vide order dated
05.12.2025 in Appeal No. 436 of 2024.
The Authority observes that the
record unequivocally establishes that the Promoter, with full knowledge that
the approved service plans and estimates were not available at the time of
consideration of its application, consciously and voluntarily requested grant
of conditional registration. At the time of the issuance of the Registration
Certificate, the Promoter, in order to secure registration of the project,
deposited the requisite Security Amount on 27.10.2022 as an assurance for
timely submission of the approved service plans and estimates. The said deposit
was made to demonstrate bonafides despite admitted deficiencies. The Promoter
had expressly undertaken to obtain and submit service plans and estimates
within a period of three months from the date of issuance of the Registration
Certificate and accepted the conditional registration with open eyes and
without protest. Having voluntarily sought conditional registration and
furnished the Security Amount as a solemn assurance of compliance, the Promoter
is now estopped from assailing the very conditions which it had itself
requested and agreed to abide by.
Registration certificate itself recorded that any DDs deposited for
non-submission of the specified approvals within the stipulated time would
stand forfeited in favour of the Authority. The forfeiture clause was expressly
incorporated in the registration certificate under clause “(G) COMPLIANCES TO
BE MADE BY THE PROMOTER” and was brought to the Promoter’s notice at the time
of grant of conditional registration.
On perusal of the record, it is noted that the application for approval of
service plans and estimates was submitted on 10.01.2023, the competent
authority, i.e., DTCP, Haryana, vide communication dated 14.03.2023,
specifically required the Promoter to furnish a Bank Guarantee of Rs. 112.21
lakhs immediately to enable processing of the approval. However, the Promoter
failed to comply with the said requirement and, by its own admission, furnished
the Bank Guarantee only on 15.04.2023, after an inordinate and unexplained
delay of around 32 days. Upon submission of the requisite Bank Guarantee, the
concerned department acted with due promptitude and approved the service plans
and estimates on 01.05.2023 i.e., within 16 days of furnishing the said Bank
Guarantee. The sequence of events clearly establishes that the delay was
entirely attributable to the Promoter’s own inaction and negligence, and not to
any alleged lapse on the part of the authorities.
In view of the above, Authority hereby directs that the security amount of
Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only) deposited by the
Respondent-Promoter for ensuring timely submission of the service plans and
estimates shall be forfeited.
The matter stands disposed of accordingly. Detailed order shall follow. |
ARUN KUMAR |
View Order |
12-Jun-2026 |