Comprehensive Complaint Details
Complaint Detail:RERA-GRG-2447-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
MRS SANTOSH SHARMA V/S
VSR INFRATECH PVT.LTD.
RAJAN GUPTA AND HEMAN GUPTA GURUGRAM DISPOSED NOT REQUIRED Not Yet first hearing --
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
07-Mar-2025 DISPOSED Matter stands disposed of. File be consigned to the registry. ARUN KUMAR View Order 13-Mar-2025
14-Feb-2025 PENDING The present complaint has been received on 01.06.2023 and the reply on behalf of respondent was received on 24.05.2024. On last date of hearing i.e., 08.11.2024 the counsel for the parties states that settlement talks are going on to settle the matter amicably. Both the parties, states at bar that settlement talks are still going on between the parties and are at advance stage. Hence, requests for a short adjournment. Request is allowed. Matter to come up on 07.03.2025 for further proceedings. ARUN KUMAR View Order 19-Feb-2025
10-Jan-2025 PENDING The present complaint has been received on 01.06.2023 and the reply on behalf of respondent was received on 24.05.2024. Both the counsels for the parties have stated at bar that settlement talks between the parties are going on and request for a short adjournment. Request is allowed. Matter to come up on 14.02.2025 for further proceedings. ARUN KUMAR View Order 16-Jan-2025
08-Nov-2024 PENDING The present complaint has been received on 01.06.2023 and the reply on behalf of respondent was received on 24.05.2024. On last date of hearing i.e., 09.08.2024 the counsel for the parties stated that settlement talks are going on to settle the matter amicably. The counsel for the respondent states at bar that OC was received on 02.08.2019 and the settlement talks are at advance stage and requests for a short adjournment. Matter to come up on 10.01.2025 for filing settlement deed failing which arguments shall be heard on merits. ARUN KUMAR View Order 12-Nov-2024
09-Aug-2024 PENDING The present complaint was received on 01.06.2023 and the reply on behalf of respondent was received on 24.05.2024. Both the counsels of the parties state that settlement talks are in progress to settle the matter amicably.  Matter is adjourned to 08.11.2024 for filing settlement deed. SANJEEV KUMAR ARORA View Order 27-Aug-2024
24-May-2024 PENDING Reply filed by the respondent in the registry today taken on the record. Copy of reply also supplied to the learned counsel for the complainant. Cost of Rs. 15,000/- also paid to the complainant. As pleadings are complete so matter is listed before the authority on 09.08.2024 for final arguments. HARISH GUPTA View Order 03-Jun-2024
29-Mar-2024 PENDING Reply not filed. Adjournment requested. Now the case is adjourned for 24.05.2024. Respondent is hereby directed to file reply within three weeks of this order,  in the registry with advance copy to the complainant, along with  cost of Rs. 15,000/- to be paid to the complaint. HARISH GUPTA View Order 02-Apr-2024
01-Mar-2024 PENDING Reply not filed. Adjournment requested. Now come upon 29.03.2024 for filing reply subject to last opportunity failing which defence of respondent may be struck off. HARISH GUPTA View Order 05-Mar-2024
09-Feb-2024 PENDING In compliance of order dated 12.12.2023 complainant filed application for bringing on record additional documents. Now the case is adjourned for 01.03.2024 for filing reply of the complaint by respondent. HARISH GUPTA View Order 16-Feb-2024
22-Dec-2023 PENDING  The counsel for the respondent has filed an application for dismissal of the complaint on the ground that complaint is not accompanied with affidavit and also the relief sought by the complainant is not clear as to whether the complainant is seeking assured return or the refund but the above can be no ground of dismissal. One opportunity is being given to the complainant to file affidavit within one week after supplying a copy to the counsel for the respondent.  In the meanwhile, the complainant shall  clear the relief whether she wants to refund or the assured return and to file affidavit, as stated above within a period of two weeks. Matter to come up on 09.02.2024 for further proceedings. VIJAY KUMAR GOYAL View Order 28-Dec-2023
20-Oct-2023 FIRST HEARING The court is adjourned today i.e. 20.10.2023 due to power cut in the HARERA Gurugram office. Matter to come up on 22.12.2023  for the purpose  already fixed. SANJEEV KUMAR ARORA View Order 30-Oct-2023
Complaint Final Judgement Details
Date of Judgement Party Details Judgement Uploading Date View Judgement
07-Mar-2025 MRS SANTOSH SHARMA V/S
VSR INFRATECH PVT.LTD.
28-Mar-2025
Documents Submitted
Dak ID Receiving Date Submitted By Remarks
54009 01/06/2023 RAJAN GUPTA AND HEMAN GUPTA NEW COMPLAINT
61052 30/10/2023 ARTLO APPLICATION FOR DISMISSAL OF COMPLAINT ON BEHALF OF RESPONDENT ALONG WITH AFFIDAVIT AND BOARD RESOLUTION
65618 31/01/2024 ADV RAJAN GUPTA APP ON BEHALF OF COMPLAINANT FOR ADDITIONAL DOCUMENTS
109111 30/03/2026 SUKHBIR YADAV 2 CERTIFIED COPY OF ORDER. (2447-2023, 2449-2023)
72091 24/05/2024 ARTLO REPLY RECEIVED