25-Nov-2022 |
FIRST HEARING |
Proceedings dated: 25-11-2022
Sh. Naveen Agarwal (CS) and Sh. Charanjeet
Monga (Asstt. Manager) are present on behalf of the promoter. The fire scheme
approval was obtained on 26.05.2022 with a delay of 25 days. Regarding service
estimates and plans, the AR submits that the matter is pending at the level of
DTCP and is likely to take 3 months.
In view of the above it is clear that the condition
No. 1 as mentioned in the registration certificate No.
RC/REP/HARERA/GGM/529/261/20222/04, dated 31.01.2022 has not been complied
with. Therefore, the BG of Rs. 10 lakhs submitted in lieu of compliance of the
above condition within a period of 3 months be forfeited. The
promoter/developer requests that another 3 months’ time may be given to comply
with the condition to submit approved service estimates and plans for which he
shall submit a fresh BG for Rs. 25 lakhs within a period of 15 days. In case
the same is not submitted, action under section 7(1) of the Act, 2016 shall be
taken.
The matter to come up on 09.12.2022. |