| 16-Jun-2026 |
PENDING |
|
|
--- |
--- |
| 09-Jun-2026 |
PENDING |
THE MATTER IS ADJOURNED TO 16.06.2026 |
ANU |
View Order |
09-Jun-2026 |
| 30-Mar-2026 |
PENDING |
THE MATTER IS ADJOURNED TO 09.06.2026 |
ANU |
View Order |
22-May-2026 |
| 02-Mar-2026 |
PENDING |
THE MATTER IS ADJOURNED TO 30.03.2026 |
ANU |
View Order |
10-Mar-2026 |
| 25-Jul-2024 |
PENDING |
THE MATTER TO COME UP ON 02.03.2026 |
ANU |
--- |
--- |
| 25-Jun-2024 |
PENDING |
Ar. Neeraj Gautam (Associate Architectural Executive)
briefed the facts of the case.
Sh. Rajeev Srivastava (VP), Sh. Pawan Kumar (AR)
and Sh. Vipul Suchdeva (MD) appeared on behalf of the promoter.
Th AR states that the
promoter had applied for the approval of fire fighting scheme on 28.07.2022
whereupon objections dated 28.07.2022 were issued by the concerned department
to which the promoter responded immediately. The promoter had then requested the
Authority to release the BG vide application dated 10.11.2022 and on 11.11.2022
submitted a letter regarding change in the procedure of approval of fire
fighting scheme. The promoter had again requested the Authority on 20.03.2024
to release the bank guarantee.
The AR further states that
the promoter had applied for approval of service plans and estimates on
24.03.2022 and vide letter dated 20.09.2022 informed the Authority that the
service plans and estimates were in the office of DTCP for final approval and
requested the Authority for extension of time for submission of final approval.
Thereafter, on 07.11.2022, the final approval of service plans and estimates
were submitted in the Authority. The promoter requested for the release of
security amount vide applications dated 10.11.2022, 11.11.2022, 08.12.2022 and
20.03.2024.
The AR of the promoter
requests to condone the delay and release the security amount as the same was
not on account of any default by the promoter. Further, he states that the
project is held up on account of non-clearance by the wildlife board and the
promoter is suffering huge losses on account of delay in starting the project
despite initial clearances granted by the DTCP as well as RERA.
However,
it is not disputed that the promoter was granted conditional registration at
its own accord and depositing of security amount in the form of bank guarantee
in lieu of submission of the requisite clearances within the time specified in
the conditional registration. It was clearly mentioned in the registration
certificate that these bank guarantees shall be forfeited in case the
conditions are not fulfilled by the promoter within the stipulated time period
mentioned in the conditions.
Since
the bank guarantees deposited by the promoter have already expired on
23.05.2023, the promoter is directed to deposit the security amount in lieu of
the condition in registration certificate within a period of 30 days.
Meanwhile, the registration certificate issued for the project shall remain in
suspension. |
ASHOK SANGWAN |
View Order |
11-Jul-2024 |
| 03-Mar-2023 |
PENDING |
MATTER
ADJOURNED FOR 03-03-2023.
|
ARUN KUMAR VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 16-Dec-2022 |
PENDING |
Matter
adjourned for 03-03-2023.
|
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 02-Dec-2022 |
FIRST HEARING |
Proceedings
dated: 02-12-2022
Sh. Vipul
Sachdeva (Director), Sh. Kamlesh Virmani (PD) and Sh. Rajeev Srivastava (GM)
are present on behalf of the promoter.
The
promoter has requested time for submitting delay condonation application.
The matter to come up on
16.12.2022. |
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
02-Jan-2023 |