| 08-Aug-2024 |
DISPOSED |
Ar. Neeraj Gautam
(Associate
Architectural Executive) briefed the facts of the case.
Sh. Saurabh Mishra (AR) appeared
on behalf of the promoter and stated that they had submitted the service plans
and estimates to HSVP on 30.03.2022 and pursued with the department. The AR
request to condone the delay in obtaining the approval of service plans and
estimates.
However, it is not disputed that
the promoter was granted conditional registration at its own accord and
depositing of security amount in the form of cheque in lieu of submission of
the requisite clearances within the time specified in the conditional
registration. It was clearly mentioned in the registration certificate that
this security cheque shall be forfeited in case the conditions are not
fulfilled by the promoter within the stipulated time period mentioned in the conditions.
Since the promoter has obtained
the approval of service plans and estimates with a delay of 149 days, the
security amount of Rs. 10 lacs deposited on account of the same is hereby
forfeited.
There are two complaint nos. RERA-GRG-7043-2022
and RERA-GRG-3562-2024 generated against the present matter. Both be clubbed
together.
In view of the fact that the
compliances have been made, although with a delay, the case is filed. |
ASHOK SANGWAN |
--- |
--- |
| 03-Mar-2023 |
PENDING |
MATTER TO COME UP ON 08.08.2024 |
ASHOK SANGWAN |
--- |
--- |
| 16-Dec-2022 |
PENDING |
Matter
adjourned for 03-03-2023.
|
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 02-Dec-2022 |
FIRST HEARING |
Proceedings
dated: 02-12-2022
Sh.
Saurabh Mishra (Asstt. Manager-Legal) is present on behalf of the promoter.
The
promoter states that the cheque has already been encashed. The same to be
confirmed from Accounts Branch.
The matter to come up on
16.12.2022. |
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |