| 06-Mar-2025 |
DISPOSED |
Ms. Neeraj Gautam (Associate Architectural Executive) briefed the facts
of the case.
Sh. Anitesh Singh (AR) appeared on behalf of the
promoter and states that the application for the approval of standard design
was made in timely manner. The application was kept pending by the concerned
authority for the purpose of framing guidelines/ standard operating procedures
of approvals of architectural control sheet/ standard design in respect of all
such kind of projects of commercial plotted colonies being developed in the
state. It is further stated in the application that the promoter had written a
letter dated 03.02.2021 along with undertaking at DTCP for issuance of approval
and the final order for SOP got issued on 31.01.2022. The promoter’s
application was processed by DTCP and final approval was granted on 19.04.2024.
The promoter has requested vide application dated
30.08.2024 to release the security deposit as the delay in getting the approval
was solely in the purview of competent authority.
However, it is not disputed that the promoter was
granted conditional registration at its own accord and depositing of security
amount of Rs. 50 lakhs as a guarantee for submission of the requisite
clearances within the time specified in the conditional registration. It was
clearly mentioned in the registration certificate that this bank guarantee
shall be forfeited in case the conditions are not fulfilled by the promoter
within the stipulated time period mentioned in the conditions.
The bank guarantee of Rs. 25 lakhs submitted on
account of submission of approved service plans & estimates already stands
refunded to the promoter. Further on request of the promoter, the bank
guarantees of Rs. 25 lakhs bearing nos. 572GT02213560004
dated 22.12.2021 (Original) and 572GT01232420002 dated 30.08.2023 (Revalidated) on account of approved architectural control sheet have
already been returned to the promoter on submission of DD no. 784375 dated 03.07.2024 of the same amount.
Keeping in view the fact that the promoter has
submitted the approved standard designs with a delay of 85 days, the security
amount of Rs. 25 lakhs is hereby forfeited.
Since the compliances have been made, although with
a delay, the case is filed. |
ASHOK SANGWAN |
--- |
--- |